PLANNING AND ENVIRONMENT COURT OF QUEENSLAND
CITATION:
JH Northlakes Pty Ltd v Moreton Bay Regional Council [2022] QPEC 18
PARTIES:
JH NORTHLAKES PTY LTD
(ACN 633 496 278)(applicant)
v
MORETON BAY REGIONAL COUNCIL
(respondent)
FILE NO/S:
3269 of 2021
DIVISION:
Planning and Environment Court
PROCEEDING:
Originating application
ORIGINATING COURT:
Planning and Environment Court, Brisbane
DELIVERED ON:
9 June 2022
DELIVERED AT:
Brisbane
HEARING DATE:
26 April 2022
JUDGE:
Williamson QC DCJ
ORDER:
The Originating application be mentioned at 9am on 10 June 2022.
CATCHWORDS:
PLANNING AND ENVIRONMENT – ORIGINATING APPLICATION – DECLARATORY PROCEEDING – where the applicant made a development application to the respondent comprising an application for a preliminary approval and a variation request under the Planning Act 2016 – where the variation request sought to vary the effect of the Mango Hill Infrastructure Development Control Plan – where the respondent did not accept the applicant’s development application – where the applicant seeks declaratory relief under s 11(a), (b) and (d) of the Planning and Environment Court Act 2016 – whether the development application should have been made under the Integrated Planning Act 1997 – whether the Mango Hill Infrastructure Development Control Plan forms part of the respondent’s planning scheme – whether a variation request can be made under s 50 of the Planning Act 2016 to vary the effect of the Mango Hill Infrastructure Development Control Plan – whether the applicant’s development application is a properly made application for the purposes of s 51(5) of the Planning Act 2016.
LEGISLATION:
Acts Interpretation Act 1954, s 35C
Integrated Planning Act1997, ss 3.2.1, 6.1.28, 6.1.29, 6.1.30 and 5.9.1
Planning Act 2016, ss 8, 50, 51, 61, 286, 316 and Schedule 2
Planning and Environment Court Act 2016, s 11
Statutory Instruments Act 1992, s 23Sustainable Planning Act 2009, ss 80, 82, 84, 86, 88 and 857
CASES:
Cannon Hill Investments Pty Ltd & Anor v Malt Brewing Company Pty Ltd & Ors [2021] QCA 281
Fewstone Pty Ltd v Ross Nielson Properties Pty Ltd & Anor [2003] QSC 82
Lagoon Gardens Pty Ltd v Whitsunday Regional Council & Ors [2010] QPELR 74
Patsalis v State of New South Wales [2012] NSWCA 307
Pope v WS Weather & Sons Pty Ltd [2006] VSCA 227Sanderson Computers Pty Ltd v Urica Library Systems BV (1998) 44 NSWLR 73
COUNSEL:
Mr D Gore QC and Mr M Batty for the applicant
Mr B Job QC and Mr J Ware for the respondentSOLICITORS:
Corrs Chambers Westgarth for the applicant
McCullough Robertson for the respondent
Table of Contents
Introduction
The development application
The Action Notice and letter of 3 November 2021
Objections to the applicant’s affidavit material
A threshold difficulty for the applicant
The issues
Does the development application identify ‘development’ for which approval is sought?
Does the development application seek to vary the effect of a local planning instrument?
The ‘properly made’ points
Was the development application made in the approved form?
Were the mandatory…
Keep reading for free
Create a free CaseChat account to read JH Northlakes Pty Ltd v Moreton Bay Regional Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QPEC 18
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether the development application should have been made under the Integrated Planning Act 1997. It also had to determine if the Mango Hill Infrastructure Development Control Plan was part of the respondent's planning scheme. Additionally, the court had to decide if a variation request could be made under section 50 of the Planning Act 2016 to alter the Mango Hill Infrastructure Development Control Plan's effect. Lastly, the court had to establish if the applicant's development application was correctly made under section 51(5) of the Planning Act 2016.
The court found that the development application should have been made under the Integrated Planning Act 1997. It also determined that the Mango Hill Infrastructure Development Control Plan was part of the respondent's planning scheme. However, the court ruled that a variation request could not be made under section 50 of the Planning Act 2016 to change the Mango Hill Infrastructure Development Control Plan's effect. As a result, the applicant's development application was not properly made under section 51(5) of the Planning Act 2016.
The court ordered that the originating application be mentioned at 9 am on 10 June 2022.
Orders
Orders of the court
The Originating application be mentioned at 9am on 10 June 2022.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi