Jeteld Pty Ltd v Toowoomba Regional Council

Link copied
Case Copied 17 min read

PLANNING AND ENVIRONMENT COURT

OF QUEENSLAND

CITATION:

Jeteld Pty Ltd v Toowoomba Regional Council [2024] QPEC 36

PARTIES:

JETELD PTY LTD ACN 009 904 456

(Appellant)

v

TOOWOOMBA REGIONAL COUNCIL

(Respondent)

FILE NO/S:

1675/24

DIVISION:

Planning and Environment

PROCEEDING:

Application in Pending Proceeding

ORIGINATING COURT:

Planning and Environment Court, Brisbane

DELIVERED ON:

19 August 2024

DELIVERED AT:

Brisbane

HEARING DATE:

5 August 2024

JUDGE:

Kefford DCJ

ORDER:

THE TIME FOR STARTING THIS APPEAL NO. 1675 OF 2024 BE EXTENDED TO 18 JUNE 2024.

THE MATTER BE LISTED FOR MENTION ON TUESDAY 20 AUGUST 2024.

CATCHWORDS:

PLANNING AND ENVIRONMENT – APPEAL – APPLICATION IN PENDING PROCEEDING – where the applicant did not file its notice of appeal within time – where the applicant sought an order extending the time for starting an appeal against the infrastructure charges notice under s 32 of the Planning and Environment Court Act 2016

LEGISLATION:

Planning Act 2016 (Qld) ss 49, 60, 63, 65, 122, 128, 145, 229, sch 1

Planning and Environment Court Act 2016 (Qld) ss 11, 32, 47

CASES:

Bayview Gardens Pty Ltd v Shire of Mulgrave [1989] 1 Qd R 1, cited

Hollis v Atherton Shire Council [2003] QSC 147; (2003) 128 LGERA 348; [2003] QPELR 482, cited

Lloyd v Robinson [1962] HCA 36; (1962) 107 CLR 142, cited

Supreme Renovators Pty Ltd v Logan City Council [2019 QPEC 63; [2020] QPELR 805, approved

COUNSEL:

A Skoien for the Appellant
M Rodgers for the Respondent

SOLICITORS:

Wonderley & Hall Solicitors Toowoomba for the Appellant
Corrs Chambers Westgarth for the Respondent

TABLE OF CONTENTS

Introduction

What is the Court’s power to extend the appeal period?

What is the relevant context in which the appeal was filed?

Is the subject appeal fundamentally flawed?

What are the grounds advanced by Jeteld Pty Ltd?

Is there an adequate explanation for the delay?

Is there any prejudice to the Council because of the delay?

Is there a public interest consideration that favours the extension?

Does the appeal have merit?

Do considerations of fairness support the grant of the extension?

Conclusion

Introduction

  1. On 18 June 2024, Jeteld Pty Ltd filed the Notice of Appeal that commenced this proceeding.  The Notice of Appeal identifies the relevant right of appeal as that which arises under “sections 229 and 230 and Item 4 of Table 1 of Schedule 1 of the Planning Act 2016”, being a right of appeal against an infrastructure charges notice given by Toowoomba Regional Council (“the Council”). 

  2. The issues at the crux of Jeteld Pty Ltd’s appeal are the proper characterisation of infrastructure works and the entitlement to a credit or offset in relation to such works in the calculation of the infrastructure charge.

  3. Jeteld Pty Ltd accepts that its Notice of Appeal was filed about four and a half months after the expiry of the relevant appeal period. The issue presently before the Court is whether Jeteld Pty Ltd should succeed on its application for an extension of time…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Jeteld Pty Ltd v Toowoomba Regional Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] QPEC 36
Decision Date

CaseChat Overview and Summary

Jeteld Pty Ltd applied for an extension to the time for starting an appeal against an infrastructure charges notice issued by the Toowoomba Regional Council. The application was heard in the Planning and Environment Court of Queensland. The central issue before the court was whether the applicant was entitled to an extension of time to commence the appeal, given that it had not filed its notice of appeal within the statutory time limit. The applicant argued that the extension should be granted on the basis of fairness and the need to resolve the dispute over the infrastructure charges.

The court considered the arguments advanced by Jeteld Pty Ltd regarding fairness and the need to resolve the dispute over the infrastructure charges. While the court did not place significant weight on the applicant's first argument concerning ongoing dealings between the parties, it found merit in the second argument. The court concluded that considerations of fairness supported granting the extension, as it would prevent the Council from securing a potential windfall gain to which it was not legally entitled. The court determined that there were sufficient grounds to allow an extension to the appeal period in relation to the infrastructure charges notice. Consequently, the Council's application for costs was dismissed.

The court ordered that the time for starting the appeal be extended to 18 June 2024, and the matter was listed for mention on 20 August 2024 to discuss appropriate orders.

Orders

Orders of the court

THE TIME FOR STARTING THIS APPEAL NO. 1675 OF 2024 BE EXTENDED TO 18 JUNE 2024.

THE MATTER BE LISTED FOR MENTION ON TUESDAY 20 AUGUST 2024.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Although I place no meaningful weight on Jeteld Pty Ltd’s first argument, the second weighs in support of a favourable exercise of my discretion. Conclusion On balance, I am persuaded that there are sufficient grounds to allow an extension to the appeal period in relation to the infrastructure charges notice. In those circumstances, the Council’s application for costs fails. I will list the matter for mention on Tuesday 20 August 2024 so that I may hear from the parties about appropriate orders.

Ratio Decidendi

Legal Principle Established

I have set out the crux of the case advanced by Jeteld Pty Ltd about these works, and the entitlement to an offset, in paragraph [24] above. At face value, Jeteld Pty Ltd has an arguable case.Do considerations of fairness support the grant of the extension? Jeteld Pty Ltd makes two arguments with respect to fairness. First, given there have been, and are, ongoing dealings between the parties about the issue on which the appeal will turn, Jeteld Pty Ltd submits that considerations of fairness militate strongly in favour of granting the extension. It says that resolution of the issue will benefit the parties by resolving the dispute about the infrastructure charges notice the subject of this appeal. According to Jeteld Pty Ltd, it will also inform these parties and others in a way that may assist in planning for other developments where this question arises. Second, Jeteld Pty Ltd submits that, as a matter of fairness, the issue should be litigated because otherwise the Council will potentially secure a windfall gain to which it is not legally entitled. On Jeteld Pty Ltd’s case, the Council would secure payment for the infrastructure under the infrastructure charges notice and simultaneously require the developer to assume the burden of constructing (at the developer’s cost) the infrastructure in question. Although I place no meaningful weight on Jeteld Pty Ltd’s first argument, the second weighs in support of a favourable exercise of my discretion. Conclusion On balance, I am persuaded that there are sufficient grounds to allow an extension to the appeal period in relation to the infrastructure charges notice. In those circumstances, the Council’s application for costs fails. I will list the matter for mention on Tuesday 20 August 2024 so that I may hear from the parties about appropriate orders.