Jamac Construction Group Pty Ltd v De Mol Investments Pty Ltd

Link copied
Case Copied 9 min read

JAMAC CONSTRUCTION GROUP PTY LTD -v- DE MOL INVESTMENTS PTY LTD [2013] WASC 360



SUPREME COURT OF WESTERN AUSTRALIACitation No:[2013] WASC 360
Case No:CIV:1873/201320 SEPTEMBER 2013
Coram:KENNETH MARTIN J27/09/13
8Judgment Part:1 of 1
Result: Temporary stay of arbitration
B
PDF Version
Parties:JAMAC CONSTRUCTION GROUP PTY LTD
DE MOL INVESTMENTS PTY LTD

Catchwords:

Arbitration
Stay application
Partial or full stay
Discretionary consideration
Turns on own facts

Legislation:

Commercial Arbitration Act 1984 (WA), s 47

Case References:

Nil

JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
    IN CHAMBERS
CITATION : JAMAC CONSTRUCTION GROUP PTY LTD -v- DE MOL INVESTMENTS PTY LTD [2013] WASC 360 CORAM : KENNETH MARTIN J HEARD : 20 SEPTEMBER 2013 DELIVERED : 27 SEPTEMBER 2013 FILE NO/S : CIV 1873 of 2013 BETWEEN : JAMAC CONSTRUCTION GROUP PTY LTD
    Plaintiff

    AND

    DE MOL INVESTMENTS PTY LTD
    Defendant

Catchwords:

Arbitration - Stay application - Partial or full stay - Discretionary consideration - Turns on own facts

Legislation:

Commercial Arbitration Act 1984 (WA), s 47

Result:

Temporary stay of arbitration


Category: B


Representation:

Counsel:


    Plaintiff : Mr J A Thomson SC
    Defendant : Mr C G Colvin SC

Solicitors:

    Plaintiff : Tottle Partners
    Defendant : Hotchkin Hanly



Case(s) referred to in judgment(s):

Nil


1 KENNETH MARTIN J: There is an arbitration pending (ARB 3654) between these two parties, commenced in 2012 by the plaintiff as claimant against the defendant as respondent.

2 By its originating summons commencing this action on 31 May 2013 the plaintiff (Jamac) seeks that this court either by s 47 of the Commercial Arbitration Act 1984 (WA) or, in its inherent jurisdiction, strike out or permanently stay aspects of the defendant's (De Mol) points of defence and counterclaim in the arbitration.

3 Jamac's strike-out or stay application is pursued on the basis that aspects of the arbitration (raised by De Mol by its points of defence and counterclaim in the arbitration), present issues which have already been raised before this court in CIV 2192 of 2010 (the Rodgers litigation). This has arisen in circumstances where both Jamac and De Mol are defendants and essentially cross-claimants against each other in the Rodgers litigation. The Rodgers litigation has been case managed in my CMC list since 2010.

4 The Rodgers litigation concerns claimed physical and economic damage to a building in Beaufort Street, Mount Lawley, arising from sheet piling work (and the consequent vibrations) carried out from the immediately adjacent land, together with the removal of support for the Rodgers land by reason of the adjacent land's deep excavation.

5 The property development works upon the adjacent land in Beaufort Street was De Mol's project. To that end, it had engaged Jamac under a head contract of 14 January 2010, effectively as its head contractor.

6 In turn, Jamac had engaged (in excess of 40) subcontractors. One of which, GFWA Pty Ltd (GFWA), was engaged by Jamac to carry out sheet piling…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Jamac Construction Group Pty Ltd v De Mol Investments Pty Lt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] WASC 360
Decision Date

CaseChat Overview and Summary

Jamac Construction Group Pty Ltd brought an originating summons before the Supreme Court of Western Australia, seeking either a strike-out or a permanent stay of aspects of De Mol Investments Pty Ltd's points of defence and counterclaim in an arbitration that was pending between the two parties. The dispute centred on whether certain issues raised by De Mol in the arbitration overlapped with issues that had already been raised before the court in another litigation, referred to as the Rodgers litigation. The court was required to determine whether the issues raised in the arbitration should be stayed either partially or in full, and whether there was a need for additional proceedings to be commenced in the court to resolve the residual aspects of the dispute.

The court held that there should be a temporary stay of the whole arbitration pending the determination of the Rodgers litigation. The court arrived at this decision based on several reasons, including the potential for issue crossover in relation to sheet piling and vibration issues, the need for the court to be the primary forum in which all such issues were finally resolved, the realistic option of commencing fresh proceedings and having them consolidated with or arranged with the Rodgers litigation, and the potential resolution of the Rodgers litigation being assisted and more likely if all aspects of the underlying disputes between parties in that litigation were resolved together at the one time and in one forum. The court took a wider and less legalistic view towards hopefully achieving a viable, overall potential solution for the parties regarding all their disputes.

In the circumstances, the court issued a temporary stay of the arbitration in its entirety. Should correlative proceedings be commenced out of the court as foreshadowed in the judgment, it may be that the temporary stay would then be upgraded to permanent. The court resolved on the papers, if necessary, the resulting orders and costs in light of these reasons which would be published to the parties.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established