QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
PARTIES:
BINNY JACOB
(applicant)v JUAN PABLO LARRAIN CERDA
(respondent)
APPLICATION NO/S:
BDL284-16
MATTER TYPE:
Building matters
DELIVERED ON:
5 August 2018
HEARING DATE:
13 October 2017
HEARD AT:
Brisbane
DECISION OF:
Member McLean Williams
ORDERS:
1. The Respondent is to pay the Applicant $15,665.70 within 28 days.
2. The Respondent’s counterclaim is dismissed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – building contract for landscaping works – respondent abandoned site prior to completion of works – claim by applicant for costs of completion and rectification – counterclaim by respondent for uncharged works
APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondent:
Self-represented
REASONS FOR DECISION
By an Application for Domestic Building Disputes filed on 3 November 2016, Ms Binny Jacob (‘the Applicant’) brings a claim before QCAT against Mr Lorrain Juan Pablo Cerda (‘the Respondent’).
The Respondent had constructed a series of block retaining walls at the front and rear of the Applicant’s home at 6 Hawkesbury Avenue at Pacific Pines, as well as a set of external block stairs from the footpath up to the front entrance of the house. The Applicant now claims these works to be defective, and incomplete.
The Applicant says that on 12 July 2016 she accepted a type-written quote (quote number 519) presented by the Respondent for landscaping works at her home for $20,500. The scope of work included in the quote was:
Back yard:
1. Demolition and preparation of areas for paving and retaining wall;
2. [Construct a] Retaining wall 15 metres long. Height to vary from 400 mm high to one metre high with charcoal blocks to match an existing retaining wall
3. [Install] exposed aggregate in 3 different sections: 10 square metres, approx., cream in colour
4. Garden bed will be built between retaining wall and paving area from 1 metre to 1.5 metres wide and 15 metres long (Plants not included).
Front yard:
Retaining wall, 2 piers [sic, should be ‘tiers’]. First will be 10 metres long by 400mm high with a one metre set of steps between
Second pier (second level) will be 10 metres long by 600mm high with a one metre wide set of steps between Retaining walls will be built with charcoal ‘Versablock’ 400 x 200.
A garden bed will be built between the 2 retaining walls Plants are not included.
Top level exposed aggregate.
There were some further negotiations before the Applicant and the Respondent signed the quote. Under a further section entitled ‘comments from clients to be agreed with JPL Landscaping’ there appears a hand-written insertion: ‘please see the comments attached (2 pages)’. Then, attached to the quote, and duly initialled by the Applicant and Respondent is a further type-written list, of 14 conditions. Presumably, these 14 conditions were drawn up by the Applicant.
It is not necessary here to traverse all of the 14 ‘extra’ conditions. It…
Continue reading Jacob v Cerda
Sign in free to access the full text
- AGLC
- Jacob v Cerda [2018] QCAT 255
- Case
- [2018] QCAT 255
- Decision Date
CaseChat Overview and Summary
The key legal issue before the Tribunal was whether the respondent was entitled to payment for the uncharged works he claimed to have completed, and if not, what amount, if any, the applicant owed the respondent for the landscaping works. The applicant denied that any of the respondent’s works were delayed as a result of her requesting changes, and that the only extra work or changes that were required were in consequence of deficiencies in the quality of work already completed by the respondent. The Tribunal had to consider the evidence presented by both parties, including the engineering report and the text messages between the parties, to determine the merits of the claims and counterclaims.
The Tribunal found that the respondent had not provided sufficient evidence to support his claim for uncharged works and dismissed his counterclaim. The Tribunal held that the applicant had provided evidence that the respondent had made mistakes in laying out the front stairs, which resulted in gaps around the stairs where they did not properly meet with the adjoining tiered walls. The Tribunal also found that the respondent had not constructed the retaining walls correctly, and that sub-drainage was not installed prior to backfilling behind any of the walls. The Tribunal held that the respondent was liable to pay the applicant $15,665.70 for the landscaping works, which represented the cost of completing the works and rectifying the deficiencies.
The Tribunal ordered that the respondent pay the applicant $15,665.70 within 28 days and dismissed the respondent’s counterclaim. The Tribunal did not make any orders regarding the uncharged works claimed by the respondent. The applicant was therefore successful in her claim for the costs of completion and rectification, while the respondent’s counterclaim for uncharged works was dismissed.
Orders
Orders of the court
1. The Respondent is to pay the Applicant $15,665.70 within 28 days.
2. The Respondent’s counterclaim is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.