CITATION:J & K Homes Pty Ltd v Queensland Building and Construction Commission [2016] QCAT 72
PARTIES: J & K Homes Pty Ltd (Applicant) v Queensland Building and Construction
Commission (Respondent)
APPLICATION NUMBER: GAR021-16
MATTER TYPE: Building matters
HEARING DATE: 18 March 2016
HEARD AT: Brisbane
DECISION OF: Member Gardiner
DELIVERED ON: 18 March 2016
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application to extend a time limit filed
on 29 January 2016 is dismissed.
CATCHWORDS: PROCEDURE – Extension of time to lodge a
review – where applicant sought extension of time to file a review application – whether extension should be granted
Queensland Civil and Administrative Tribunal Act 2009 (Qld): s61
Domestic Building Contracts Act 2000: s90
Cardillo v Queensland Building Services Authority [2011] QCAT 574; Jasch v QBSA [2013] QCAT 586 followed
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
[1]On 28 January 2016 J & K Homes Pty Ltd filed an application to extend time to allow the company to review a decision of the Queensland Building and Construction Commission concerning the valid termination of a contract.
J & K Homes had entered a building contract dated in May 2013 with another party. That contract was terminated by the other contracting party and on 7 November 2014, the Commission received a complaint against J
& K Homes for breach of that contract.
The other contracting party has now claimed for non-completion of the contract by J & K Homes against the statutory insurance scheme. The Commission determined the building contract was validly terminated by the other party and J & K Homes was liable to the scheme for the funds expended to complete the contract.
J & K Homes has filed a review of the Commission’s decision concerning the extent of the scope of works under the insurance claim and that review is progressing through the QCAT.
J & K Homes now seeks to step back in the history of this matter and review the validity of the termination itself. J & K Homes say that if the contract was not validly terminated, the company is not liable for the current decision to seek redress for the monies claimed by the other party under the insurance scheme.
The problem for J & K Homes is that this review application is long out of the normal review timeframe. It is however complicated by procedural mistakes made by the Commission.
The important dates are as follows:
· On 19 November 2014 the Commission notified J & K Homes of an insurance claim;
· On 10 December 2014 the Commission informed the other party that it had been determined that the contract was validly terminated. The Commission did not inform J & K Homes of the determination;
· On 9 February 2015, J & K Homes was notified of a potential debt. The notice…
Keep reading for free
Create a free CaseChat account to read J & K Homes Pty Ltd v Queensland Building and Construction C... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] QCAT 72
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the applicant had provided sufficient grounds to warrant an extension of time to file the review application. This involved a careful examination of the reasons presented by J & K Homes Pty Ltd for the delay, as well as an assessment of the impact of the delay on the proceedings and the rights of the opposing party, the Commission. The court had to balance the need for procedural fairness and the strict adherence to procedural rules in the context of the particular case.
After considering the arguments presented by both parties, the court found that J & K Homes Pty Ltd had not provided compelling reasons for the delay in filing the review application. Consequently, the court declined to grant the extension of time. The court emphasised the importance of adhering to procedural timelines and the potential consequences of delays on the administration of justice. The final orders of the court were that the application for an extension of time to file the review application was dismissed.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi