Iskra v MMIR Pty Ltd
Case
•
[2019] NSWCA 126
•30 May 2019
Details
AGLC
Case
Decision Date
Iskra v MMIR Pty Ltd [2019] NSWCA 126
[2019] NSWCA 126
30 May 2019
CaseChat Overview and Summary
The appeal concerned a dispute arising from an adjudication under the *Building and Construction Industry Security of Payment Act 1999* (NSW). The appellant, Ganni John Iskra, had made a payment claim against the respondent, MMIR Pty Ltd, for work performed. MMIR Pty Ltd failed to provide a valid payment response, leading the adjudicator to determine the claimed amount in default. MMIR Pty Ltd subsequently sought judicial review of the adjudicator's decision. The appeal was heard by Bathurst CJ, Gleeson and Payne JJA of the Court of Appeal of New South Wales.
The central legal issues before the Court of Appeal were whether the adjudicator had merely allowed the payment claim in default due to the absence of a valid response, or whether the adjudicator had engaged in a process of evaluating the claim. The court also considered whether the adjudicator's decision could be set aside for jurisdictional error, and whether the *Building and Construction Industry Security of Payment Act 1999* (NSW) required the adjudicator to use legally correct language or subjected their determination to a "fine-tooth comb" examination.
The Court of Appeal held that an adjudicator is not required to use legally correct language and that their determination should not be subjected to a "fine-tooth comb" approach. The court found that the adjudicator had exercised their statutory function to determine the value of the construction work, even in the absence of a valid payment response. The court reasoned that the adjudicator's task was to determine the amount that was, in their opinion, due and payable, and that this process did not necessitate a detailed legal analysis of the claim when no opposing submissions were made. The court distinguished between a jurisdictional error and an error of fact or law, noting that the latter would not ordinarily be a ground for setting aside an adjudication.
The Court of Appeal allowed the appeal, vacated a stay order, and set aside the orders made by the primary judge. In their place, the court ordered that the summons filed by MMIR Pty Ltd be dismissed, that MMIR Pty Ltd pay the costs of the proceedings, and that the sum paid into court by MMIR Pty Ltd be paid out to Ganni John Iskra. The first respondent was also ordered to pay the appellant's costs of the appeal.
The central legal issues before the Court of Appeal were whether the adjudicator had merely allowed the payment claim in default due to the absence of a valid response, or whether the adjudicator had engaged in a process of evaluating the claim. The court also considered whether the adjudicator's decision could be set aside for jurisdictional error, and whether the *Building and Construction Industry Security of Payment Act 1999* (NSW) required the adjudicator to use legally correct language or subjected their determination to a "fine-tooth comb" examination.
The Court of Appeal held that an adjudicator is not required to use legally correct language and that their determination should not be subjected to a "fine-tooth comb" approach. The court found that the adjudicator had exercised their statutory function to determine the value of the construction work, even in the absence of a valid payment response. The court reasoned that the adjudicator's task was to determine the amount that was, in their opinion, due and payable, and that this process did not necessitate a detailed legal analysis of the claim when no opposing submissions were made. The court distinguished between a jurisdictional error and an error of fact or law, noting that the latter would not ordinarily be a ground for setting aside an adjudication.
The Court of Appeal allowed the appeal, vacated a stay order, and set aside the orders made by the primary judge. In their place, the court ordered that the summons filed by MMIR Pty Ltd be dismissed, that MMIR Pty Ltd pay the costs of the proceedings, and that the sum paid into court by MMIR Pty Ltd be paid out to Ganni John Iskra. The first respondent was also ordered to pay the appellant's costs of the appeal.
Details
Key Legal Topics
Areas of Law
-
Administrative Law
-
Commercial Law
-
Statutory Interpretation
Legal Concepts
-
Judicial Review
-
Jurisdiction
-
Procedural Fairness
-
Appeal
-
Costs
-
Statutory Construction
Actions
Download as PDF
Download as Word Document
Citations
Iskra v MMIR Pty Ltd [2019] NSWCA 126
Most Recent Citation
Saath Pty Ltd v Seascape Constructions Pty Ltd [2021] VSC 358
Cases Citing This Decision
10
Martinus Rail Pty Ltd v Qube RE Services (No.2) Pty Ltd
[2025] NSWCA 49
Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd
[2020] NSWCA 172
Cases Cited
15
Statutory Material Cited
2
MMIR Pty Limited v Iskra
[2019] NSWSC 35
Cockram Construction Ltd v Fulton Hogan Construction Pty Ltd
[2018] NSWCA 107
Weal v Bathurst City Council
[2000] NSWCA 88
Cited Sections