DISTRICT COURT OF SOUTH AUSTRALIA
(Civil)
IRONWILL v ALLBUT & ANOR (No 2)
[2021] SADC 24
Judgment of his Honour Judge Burnett
16 March 2021
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS - GENERAL RULE: COSTS FOLLOW EVENT - EVENT: WHAT CONSTITUTES
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS - DEPRIVING SUCCESSFUL PARTY OF COSTS - CONDUCT OF PARTY OR PROCEEDING - INFLATED CLAIMS
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS - OFFERS OF COMPROMISE, PAYMENTS INTO COURT AND SETTLEMENTS - INFORMAL OFFERS AND CALDERBANK LETTERS
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - JUDGMENTS AND ORDERS - INTEREST ON JUDGMENTS - TIME FROM WHICH INTEREST RUNS
At trial, the Court ordered that the applicant was entitled to damages for loss of profits in the sum of $50,000 and that the counter-claim made by the respondents was liable to be dismissed. The claim of the applicant was for damages for repudiation of a contract for the hire of a Caterpillar D7H Bulldozer that the applicant had entered into with the respondents. The applicant’s loss arose because it was unable to complete as much land clearing work under a contract it held with a third party to clear certain properties in New South Wales.
The applicant sought interest from a mid-way point of the relevant period of the land clearing contract. The respondents submitted that interest should be calculated from the date of the issue of the proceedings.
The applicant sought indemnity costs on the basis of an informal or Calderbank offers that had been made by it prior to the institution of the proceedings. Alternatively, the applicant sought party party costs on the standard basis. The respondents submitted that there be no order as to costs or alternatively, the respondents pay the applicant 5% of its costs, but not including costs associated with the obtaining of expert reports.
In its statement of claim the applicant sought damages in the sum of $966,745. In its closing address, it sought damages in the sum of $544,089. Ultimately, following receipt of a fourth expert report, the applicant reduced its claim for damages to between $77,858 and $102,604. Ultimately, it received $50,000 in damages.
In these circumstances, the respondents submitted that the applicant had not been successful in the proceedings or had only been nominally successful. The respondents further submitted that the applicant’s claim, in the circumstances described above, had been exaggerated. The respondents also submitted that there had been wasted costs associated with the obtaining of the further expert reports.
Held:
1. The applicant is entitled to interest from the mid-way point of the land clearing contracts.
2. Pre-judgment interest is included in the judgment and is to be considered part of the award for the purposes of considering whether the applicant obtained more than $60,000; Conroy’s Smallgoods Pty Ltd v Channel Seven Adelaide Pty Ltd [2007] SASC 76 applied.
3. The applicant is not entitled to indemnity costs…
Continue reading Ironwill v Allbut
Sign in free to access the full text
- AGLC
- Ironwill v Allbut [2021] SADC 24
- Case
- [2021] SADC 24
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Held:
1. The applicant is entitled to interest from the mid-way point of the land clearing contracts.
2. Pre-judgment interest is included in the judgment and is to be considered part of the award for the purposes of considering whether the applicant obtained more than $60,000; Conroy’s Smallgoods Pty Ltd v Channel Seven Adelaide Pty Ltd [2007] SASC 76 applied.
3. The applicant is not entitled to indemnity costs because of the informal or Calderbank offers. Although it bettered those offers, they were made prior to the institution of proceedings, did not articulate the basis upon which the various components of the offers were calculated and were made during the continuance of the land clearing contract. Ultimately, the basis of the claim made by the applicant in the proceedings was different from the basis of the claim at the time that the offers were made.
4. The applicant could not be considered to have been only nominally successful. It obtained damages in the sum of $50,000 and the counterclaim of the respondents in a similar amount was dismissed.
5. There were some wasted costs incurred in relation to the further expert reports obtained by the applicant. The respondents are entitled to a deduction in the costs which would otherwise be payable to the applicant for those wasted costs.
6. The claim, in its initial form, was exaggerated. This caused the respondents to incur some additional costs in relation to the further expert reports. The respondents also lost the opportunity of negotiating a settlement, although it is not possible to quantify the loss of that chance.
7. Taking all these matters into consideration, the applicant is entitled to 60% of its costs on the standard basis.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.