Ironlaw Pty Ltd v Wollondilly Shire Council

Link copied
Case Copied 12 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Ironlaw Pty Ltd v Wollondilly Shire Council [2012] NSWLEC 262
Hearing dates:29 November 2012
Decision date: 29 November 2012
Jurisdiction:Class 1
Before: Craig J
Decision:

1.Grant leave to the Council to rely upon the Amended Statement of Facts and Contentions attached to its Notice of Motion filed on 21 November 2012.

2.Order that the following question be determined separately from and before the trial of any other question or issue in the proceedings:

"Whether the Applicant's development application is an application 'in respect of designated development' within the meaning of s 78A(8) of the Environmental Planning and Assessment Act 1979 by reason of the matters articulated in subparagraphs 1(a) to (c) inclusive of Part B of the Council's Amended Statement of Facts and Contentions attached to its Notice of Motion filed on 21 November 2012."

3.Order that any Notice of Motion proposed to be filed by the Council directed to the utility of conducting the proceedings in the absence of the consent by the Crown to the applicant's development application and any realistic prospect of that consent being obtained before a final hearing of the proceedings be filed and served by 4.00pm on Wednesday 5 December 2012.

4.Direct that the Council file and serve with any such Notice of Motion the evidence upon which it proposes to rely in support of that Motion.

5.Direct that the Applicant file and serve any evidence upon which it proposes to rely in answer to any such Notice of Motion by 4.00pm on Wednesday 12 December 2012.

6.Fix Tuesday 18 December 2012 at 9.30am before me for the hearing of any Notice of Motion filed in accordance with Order 3.

7.Give leave to the parties to approach the Registrar forthwith to obtain a date for hearing of the separate question that is identified in Order 2.

8.Direct that by Monday 17 December 2012 the parties file an Agreed Statement of Facts upon which they will rely for the purpose of arguing the separate question identified in Order 2.

9.Costs reserved.

Catchwords: PROCEDURE - interlocutory application for separate question to be heard in Class 1 proceedings pursuant to Pt 28 r 28.2 of the Uniform Civil Procedure Rules 2005 - whether separate and preliminary question should be ordered - parties agree that question will have significant impact on remaining issues for determination and will result in considerable savings in costs and time - separate question ordered
Legislation Cited: Environmental Planning and Assessment Act 1979
Environmental Planning and Assessment Regulations 2000
Uniform Civil Procedure Rules 2005
Cases Cited:

Fobitu Pty Ltd v Marrickville Council [2012] NSWLEC 81

Metropolitan Local Aboriginal Land Council v The Minister Administering the Crown Lands Act [2006] NSWLEC 57; (2006) 145 LGERA 276

Reysson v Roads and Traffic Authority [2011] NSWLEC 153

Wollongong City Council v Vic Vellar Nominees Pty Ltd [2011] NSWLEC 138

Young v Parramatta City Council [2006] NSWLEC 116; (2006) 144 LGERA 193
Category:Procedural…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ironlaw Pty Ltd v Wollondilly Shire Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] NSWLEC 262
Decision Date

CaseChat Overview and Summary

The case of Ironlaw Pty Ltd v Wollondilly Shire Council involved a dispute regarding the approval of a development application by Ironlaw, which was contested by the Wollondilly Shire Council. The matter was heard in the Supreme Court of New South Wales. The central issue before the court was whether Ironlaw's development application constituted "designated development" under the Environmental Planning and Assessment Act 1979. This determination was critical as it would influence the procedural aspects of the application process, particularly concerning the need for consent from the Crown.

The court was tasked with deciding whether the application met the criteria for designated development as outlined in section 78A(8) of the Act, particularly in relation to the matters articulated in the Council's Amended Statement of Facts and Contentions. The court's decision was to address this specific question separately from other issues in the proceedings, ensuring a clear and focused determination on the eligibility of the application as designated development. This approach was intended to streamline the litigation process and provide clarity on the procedural requirements moving forward.

In its ruling, the court granted the Council leave to rely on the amended statement of facts and contentions filed on 21 November 2012, and it ordered that the specific question regarding the designated development be determined before any other issues in the case. The court also set a timeline for the filing and serving of any notices of motion by both parties, and it directed the parties to prepare an agreed statement of facts to be used in the argument of the designated development question. The court reserved its decision on costs, indicating that this matter would be addressed at a later stage in the proceedings.

Orders

Orders of the court

1.Grant leave to the Council to rely upon the Amended Statement of Facts and Contentions attached to its Notice of Motion filed on 21 November 2012.

2.Order that the following question be determined separately from and before the trial of any other question or issue in the proceedings:

"Whether the Applicant's development application is an application 'in respect of designated development' within the meaning of s 78A(8) of the Environmental Planning and Assessment Act 1979 by reason of the matters articulated in subparagraphs 1(a) to (c) inclusive of Part B of the Council's Amended Statement of Facts and Contentions attached to its Notice of Motion filed on 21 November 2012."

3.Order that any Notice of Motion proposed to be filed by the Council directed to the utility of conducting the proceedings in the absence of the consent by the Crown to the applicant's development application and any realistic prospect of that consent being obtained before a final hearing of the proceedings be filed and served by 4.00pm on Wednesday 5 December 2012.

4.Direct that the Council file and serve with any such Notice of Motion the evidence upon which it proposes to rely in support of that Motion.

5.Direct that the Applicant file and serve any evidence upon which it proposes to rely in answer to any such Notice of Motion by 4.00pm on Wednesday 12 December 2012.

6.Fix Tuesday 18 December 2012 at 9.30am before me for the hearing of any Notice of Motion filed in accordance with Order 3.

7.Give leave to the parties to approach the Registrar forthwith to obtain a date for hearing of the separate question that is identified in Order 2.

8.Direct that by Monday 17 December 2012 the parties file an Agreed Statement of Facts upon which they will rely for the purpose of arguing the separate question identified in Order 2.

9.Costs reserved.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established