Land and Environment Court
New South Wales
- Amendment notes
Medium Neutral Citation: Investments NQ Pty Ltd v Tweed Shire Council [2024] NSWLEC 1108 Hearing dates: 4 March 2024 Date of orders: 14 March 2024 Decision date: 14 March 2024 Jurisdiction: Class 1 Before: O’Neill C Decision: The Court directs that:
(1) The parties are directed to file a revised set of agreed conditions that omit any reference to the approval of subdivision or subdivision works, within two weeks of the date of this judgment.
Catchwords: DEVELOPMENT APPLICATION – Torrens title subdivision and construction of two dwellings – works in the public reserve requiring owner’s consent from Crown Lands – part of the site is mapped as littoral rainforest – the subdivision of the site is on land mapped as littoral rainforest – the proposal is designated development pursuant to s 2.7(2) of the State Environmental Planning Policy (Resilience and Hazards) 2021 and the development application is to be accompanied by an environmental impact statement pursuant to ss 4.10(1) and 4.12(8) of the Environmental Planning and Assessment Act 1979
Legislation Cited: Environmental Planning and Assessment Act 1979 ss 1.5, 4.10, 4.12, 4.16, 6.2, 8.7
Land and Environment Court Act 1979 s 34AA
Environmental Planning and Assessment Regulation 2021 s 23
State Environmental Planning Policy (Resilience and Hazards) 2021 Ch 2, ss 2.1, 2.3, 2.7, 2.8, 2.10 and s 4.6
Tweed City Centre Local Environmental Plan 2012 (LEP 2012) cl 2.6, 4.3, 4.4, 6.1, 6.6, 6.10
Cases Cited: Mulyan Pty Ltd v Cowra Shire Council & Anor [1999] NSWLEC 212; (1999) 105 LGERA 26
Rose Bay Afloat Pty Ltd v Woolahra Council [2002] NSWLEC 208
D L Newport Pty Ltd v Northern Beaches Council [2017] NSWLEC 1661
Category: Principal judgment Parties: Investments NQ Pty Ltd (Applicant)
Tweed Shire Council (Respondent)Representation: Counsel:
Solicitors:
A Gadiel (Solicitor) (Applicant)
A Seton (Solicitor) (Respondent)
Mills Oakley (Applicant)
Marsdens Law Group (Respondent)
File Number(s): 2023/57604 Publication restriction: Nil
Judgment
-
COMMISSIONER: This is an appeal pursuant to the provisions of s 8.7(1) of the Environmental Planning and Assessment Act 1979 (EPA Act) against the refusal of Development Application No. 22/0423 for a two lot Torrens title subdivision and construction of two dwellings (the proposal), at 5 Razorback Road, Tweed Heads (the site), by Tweed Shire Council (the Council).
-
The appeal was subject to conciliation on 4 March 2024, in accordance with the provisions of s 34AA of the Land and Environment Court Act 1979 (LEC Act). As agreement was not reached, the conciliation conference was terminated and a hearing held forthwith, pursuant to s 34AA(2)(b)(ii) of the LEC Act.
Issues
-
All the merit issues raised in the Statement of Facts and Contentions filed with the court on 30 March 2023 have been resolved by amendments made to the application, as reflected in the Amended Statement of Facts and Contentions (Exh 1), except for two jurisdictional issues raised by the Council, as follows:
The application must be refused because the application has not been accompanied by…
Keep reading for free
Create a free CaseChat account to read Investments NQ Pty Ltd v Tweed Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWLEC 1108
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the conditions attached to the approval of the subdivision were valid and enforceable. Specifically, the court needed to determine if the conditions, which included restrictions on subdivision works, were ultra vires the council's statutory powers. Additionally, the court had to consider whether the conditions were ambiguous and, if so, how this ambiguity should be resolved.
The court held that the conditions regarding the approval of subdivision or subdivision works were invalid as they exceeded the statutory powers of the council. The court found that the council did not have the authority to impose such conditions as they related to the approval of subdivision, which is a distinct process from the approval of subdivision works. The court also determined that the conditions were ambiguous, and in the absence of clear statutory authority, the conditions were unenforceable. The court further directed the parties to file revised conditions that omit any reference to the approval of subdivision or subdivision works. The court's decision underscored the importance of statutory limits on council powers and the need for clarity in planning conditions.
Orders
Orders of the court
The Court directs that:
(1) The parties are directed to file a revised set of agreed conditions that omit any reference to the approval of subdivision or subdivision works, within two weeks of the date of this judgment.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi