QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Instyle Homes Qld Pty Ltd v Queensland Building and Construction Commission [2018] QCAT 289
PARTIES:
INSTYLE HOMES QLD PTY LTD
(applicant)v QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION
(respondent)
APPLICATION NO/S:
GAR256-17
MATTER TYPE:
Building matters
DELIVERED ON:
30 August 2018
HEARING DATE:
12 April 2018; 1 June 2018
HEARD AT:
Brisbane
DECISION OF:
Member Gardiner
ORDERS:
The decision of the Queensland Building and Construction Commission made on 4 August 2017 to issue direction to rectify to Instyle Homes Qld Pty Ltd is confirmed.
CATCHWORDS:
PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – where new owner claims defective building work – where Queensland Building and Construction Commission makes a decision to issue a direction to rectify to the contractor, the brother of the seller – where contractor accepts he is responsible for work but says unfair to issue notice – where contractor says work is not defective because there was a reduction of the sale price and the purchaser was buying the property “as is” – whether decision to issue a notice to rectify defects was unreasonable
Queensland Building and Construction Commission Act 1991 (Qld), s 3, s 72, s 72A
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 24
APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondent:
N Thirumoorthi, legal counsel of the Queensland Building and Construction Commission
REASONS FOR DECISION
Ms Elizabeth Frangieh owed a home in a suburb of Brisbane. Her brother Mr Joseph Frangieh is a licensed builder and director of Instyle Homes Qld Pty Ltd.
On 1 June 2016, Mr Zeb Foster entered into a contract with Ms Frangieh to purchase the property. It is not disputed that Mr Frangieh had previously carried out building work at the Property.
On 8 June 2016, Mr Foster obtained a building and pest inspection report on the home revealing various defects including problems with the drainage and leaking of the upper level balcony. Mr Foster obtained an estimate of $22,000 to rectify the defects in the upper balcony.
On 9 June 2016, the selling agent notified Mr Frangieh of the defects highlighted by the Building Report.
On 10 June 2016, Mr Frangieh responded that the property was sold on an "as is" basis and that the defects in the upper balcony had been rectified approximately 9 months earlier. He denied there could be any leaking.
On the same day, the selling agent again raised the concerns of Mr Foster about the drainage issues.
Mr Frangieh says Mr Foster was aware of the defects in the early stages of the negotiation to buy the property and that the price had been reduced by his sister to allow for these issues.
On 14 June 2016 and after receipt of the building report, the…
Keep reading for free
Create a free CaseChat account to read Instyle Homes Qld Pty Ltd v Queensland Building and Construc... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QCAT 289
- Decision Date
CaseChat Overview and Summary
The court examined the relevant statutory framework and the principles of administrative law that apply to the QBCC’s decision-making process. It considered whether the QBCC had correctly interpreted and applied the legislation in reaching its decision. The court also assessed whether the QBCC had taken into account all relevant considerations and whether it had exercised its discretion in a manner that was lawful, rational, and procedurally fair. In doing so, the court gave deference to the expertise and specialised knowledge of the QBCC in matters concerning building work.
The court concluded that the QBCC’s decision was not unreasonable. It found that the QBCC had properly interpreted and applied the relevant legislation and had exercised its discretion in a lawful and rational manner. The court further held that the reduction in the sale price and the "as is" nature of the sale did not absolve the contractor of responsibility for defective building work. Consequently, the court confirmed the decision of the QBCC made on 4 August 2017 to issue a direction to rectify to Instyle Homes Qld Pty Ltd.
Orders
Orders of the court
The decision of the Queensland Building and Construction Commission made on 4 August 2017 to issue direction to rectify to Instyle Homes Qld Pty Ltd is confirmed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi