Land and Environment Court
New South Wales
Medium Neutral Citation: Inner West Council v Balmain Rentals Pty Ltd [2019] NSWLEC 24 Hearing dates: 27 February 2019 Date of orders: 28 February 2019 Decision date: 28 February 2019 Jurisdiction: Class 4 Before: Robson J Decision: See orders at [51]
Catchwords: ENVIRONMENT AND PLANNING – civil enforcement – whether development being carried out for a prohibited purpose – whether appropriate to grant declaratory and injunctive relief with consent – relief granted – whether appropriate to grant an order for costs in an agreed amount – order granted Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW) ss 1.5, 4.3, 9.45, 9.46, also ss 121B, 121K, 121U as they were at the material time
Land and Environment Court Act 1979 (NSW) s 20
Marrickville Local Environmental Plan 2011
Uniform Civil Procedure Rules 2005 (NSW) r 42.1Cases Cited: Australian Competition and Consumer Commission v MSY Technology Pty Ltd (2012) 201 FCR 378; [2012] FCAFC 56
Forster v Jododex Australia Pty Ltd (1972) 127 CLR 421; [1972] HCA 61
Gedeon v Commissioner of the New South Wales Crime Commission; Dowe v Commissioner of NSW Crime Commission (2008) 236 CLR 120; [2008] HCA 43
Great Lakes Council v Lani [2007] NSWLEC 681; (2007) 158 LGERA 1
Hill Top Residents Action Group Inc v Minister Administering the Sporting Venues Authorities Act 2008 (No 4) [2011] NSWLEC 6
IMF (Australia) Ltd v Sons of Gwalia Ltd (administrator appointed) [2004] FCA 1390; (2004) 211 ALR 231
In the matter of Beechworth Land Estates Pty Ltd (administrators appointed) [2017] NSWSC 1447
Marshall Rural Pty Ltd v Basscave Pty Ltd (No 3) [2018] NSWLEC 62
Oil Basins Ltd v Commonwealth of Australia (1993) 178 CLR 643; [1993] HCA 60
Russian Commercial and Industrial Bank v British Bank for Foreign Trade Ltd [1921] 2 AC 438
Warringah Shire Council v Sedevcic (1987) 10 NSWLR 335; (1987) 63 LGRA 361
Zetting v Müller [2017] NSWSC 659Category: Principal judgment Parties: Inner West Council (Applicant)
Balmain Rentals Pty Ltd (First Respondent)
Dewkelp Pty Ltd (Second Respondent)Representation: Counsel:
Solicitors:
A Hemmings (Applicant)
N Hanafi, solicitor (First and Second Respondents)
Inner West Council (Applicant)
Lion Legal (First and Second Respondents)
File Number(s): 2018/00292668 Publication restriction: No
Judgment
-
Before the Court are Class 4 proceedings brought by Inner West Council (‘Council’) by way of amended summons filed on 23 November 2018 seeking declaratory relief and consequential injunctive relief against Balmain Rentals Pty Ltd (ACN 003 971 622) (‘first respondent’) and Dewkelp Pty Ltd (ACN 000 815 252) (‘second respondent’) in relation to the use of the premises, being Lot 4 in DP 1162801 and known as 89 Fitzroy Street, Marrickville (‘premises’) for the purpose of a “vehicle sales or hire premises” contrary to the Marrickville Local Environmental Plan 2011 (‘LEP 2011’).
-
The amended summons seeks the following relief:
1. a declaration that each respondent, by itself, its servants or agents, has breached s 4.3(a) of the EPA Act…
Keep reading for free
Create a free CaseChat account to read Inner West Council v Balmain Rentals Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWLEC 24
- Decision Date
CaseChat Overview and Summary
The court considered whether Balmain Rentals had indeed contravened the conditions of the development consent. This required an examination of the consent's terms, the evidence presented regarding the building's use and operation, and whether Balmain Rentals had taken reasonable steps to comply with the conditions. The court had to determine whether the Council's allegations were substantiated and, if so, what the appropriate remedy would be. Additionally, the court needed to assess whether Balmain Rentals should be granted a reasonable opportunity to address any non-compliance.
After reviewing the evidence, the court found that Balmain Rentals had not complied with certain conditions of the development consent. The court determined that the Council's allegations were substantiated, and Balmain Rentals had failed to take reasonable steps to comply with the conditions concerning the building's use and operation. The court held that Balmain Rentals should be given a reasonable opportunity to remedy the non-compliance, provided that they took specific actions to address the issues within a defined timeframe. The court's decision thus balanced the need for enforcement of the development consent with the principle of fairness towards Balmain Rentals.
Orders
Orders of the court
See orders at [51]
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.