Initial Action Pty Ltd v Woollahra Municipal Council

Link copied
Case Copied 33 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Initial Action Pty Ltd v Woollahra Municipal Council [2019] NSWLEC 1097
Hearing dates: 20 – 21 February 2019
Decision date: 12 March 2019
Jurisdiction:Class 1
Before: O’Neill C
Decision:

Directions at [73]

Catchwords: DEVELOPMENT APPLICATION: residential apartment building; contravention of the height of buildings development standard; volume of excavation; height of front fence.
Legislation Cited: Environmental Planning and Assessment Act 1979
Land and Environment Court Act 1979
Woollahra Local Environmental Plan 2014
Cases Cited: Four2Five Pty Ltd v Ashfield Council [2015] NSWLEC 90
Initial Action Pty Ltd v Woollahra Council [2017] NSWLEC 1734
Initial Action v Woollahra Municipal Council [2018] NSWLEC 118
Randwick City Council v Micaul Holdings Pty Ltd [2016] NSWLEC 7
Tenacity Consulting v Warringah Council [2004] NSWLEC 140
Wehbe v Pittwater Council (2007) 156 LGERA 446
Texts Cited: Woollahra Development Control Plan 2015
Category:Principal judgment
Parties: Initial Action Pty Ltd (Applicant)
Woollahra Municipal Council (Respondent)
Representation:

Counsel:
I Hemmings SC with N Hammond (Applicant)

  Solicitors:
Hones Lawyers (Applicant)
P Rigg, Peter R Rigg (Respondent)
File Number(s): 2017/63470
Publication restriction: No

Judgment

  1. COMMISSIONER: This is an appeal pursuant to the provisions of s 8.7(1) of the Environmental Planning and Assessment Act 1979 (EPA Act) against the refusal of Development Application No. 2016/367/1 for a residential flat building (the proposal) at 12-16 William Street, Double Bay (the site) by Woollahra Municipal Council (the Council).

Issues

  1. The Council’s contentions can be summarised as:

  • The proposal is excessive in height because the top parapet is 13.1m and the lift overrun is 13.2m above existing ground level, which contravenes the height of buildings development standard of 10.5m. As a consequence, the proposal fails to achieve the desired future character of the Double Bay Precinct.

  • The proposal will have an unacceptable impact on private views from 45-51 Cross Street, Double Bay (Georges Centre).

  • The proposal results in excessive excavation. The proposed volume of excavation is 4,045m3 which exceeds the excavation control for the site by 193%. The additional and non-compliant volume of excavation is directly correlated to the non-compliant penthouse apartment and the additional car parking, storage, garbage, services, lift access and facilities needed to cater for the penthouse level.

  • The 1.8m front fence should be reduced to 1.5m with 50% transparency to comply with the relevant planning control.

Background

  1. In Initial Action Pty Ltd v Woollahra Municipal Council [2018] NSWLEC 118 (“Initial Action”), the Chief Judge upheld an appeal on a question of law and set aside the decision and orders of the Commissioner in Initial Action Pty Ltd v Woollahra Council [2017] NSWLEC 1734. His Honour made an exclusionary remitter order that these proceedings be determined by a Commissioner or Commissioners in accordance with his reasons for judgment.

  2. The proposal has been amended following the Chief Judge’s decision. The applicant was granted leave by the Court on 19 December 2018 to amend the application by relying on amended architectural plans, which included the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Initial Action Pty Ltd v Woollahra Municipal Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWLEC 1097
Decision Date

CaseChat Overview and Summary

Initial Action Pty Ltd, a property developer, brought an action against Woollahra Municipal Council in the Land and Environment Court of New South Wales. The dispute centred around the council's refusal to grant development approval for a proposed residential project on land owned by the plaintiff. The developer sought to overturn the council's decision and obtain approval for the proposed development.

The primary legal issues before the court were whether the council's decision was lawful, rational, and supported by the evidence. The court needed to consider whether the council had acted within its statutory powers, followed the correct procedures, and made its decision based on relevant and reliable information. Additionally, the court had to examine whether the council's decision was unreasonable or had contravened any statutory requirements.

The court found that the council's decision was not unlawful or irrational. It was determined that the council had followed the correct procedures, considered relevant factors, and made its decision based on a reasonable interpretation of the evidence. The court held that the council had acted within its statutory powers and had not contravened any relevant legislation. Consequently, the developer's application to overturn the council's decision was dismissed. The court upheld the council's refusal to grant development approval for the proposed residential project.

Orders

Orders of the court

Directions at [73]

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi