LAND COURT OF QUEENSLAND
CITATION: Inglis v State of Queensland (No. 3) [2016] QLC 28 PARTIES: Robert Mallalieu Inglis, Marion Inglis and Paul Mallalieu Inglis
(applicants)
v
State of Queensland
(respondent)
FILE NO: AQL863-12 DIVISION: General Division PROCEEDING: Application for costs DELIVERED ON: 10 May 2016 DELIVERED AT: Brisbane HEARD ON: Heard on the papers
Decision reserved on 14 March 2016
HEARD AT: Brisbane MEMBER: WA Isdale ORDER: The General Application filed on behalf of the respondent on 1 April 2014 is dismissed.
CATCHWORDS: COSTS – COMPULSORY ACQUISITION – s 27 Acquisition of Land Act 1967 – where the constructing authority was substantially successful – whether costs should be awarded to the constructing authority – factors governing the exercise of discretion
Acquisition of Land Act 1967, s 27(2)
Land Court Act 2000, s 34Inglis v State of Queensland (No. 2) [2014] QLC 7
State of Queensland v Inglis & Ors [2015] QLAC 3
Mio Art Pty Ltd & Ors v Brisbane City Council [2010] QLC 86
Yalgan Investments Pty Ltd v Council of the Shire of Albert (1997-1978) 17 QLCR 401APPEARANCES: Not applicable.
The parties provided written submissions.
Background
On 12 March 2014 this Court decided the applicants were entitled to certain compensation, disturbance costs and interest.[1] Both parties appealed and the appeals were dismissed on 15 October 2015.[2]
[2]Inglis & Ors v State of Queensland (No. 2); State of Queensland v Inglis & Ors [2015] QLAC 3.
The application
The General Application brought on behalf of the respondent for an order for costs was filed on 1 April 2014. It has been adjourned while the appeals were heard. The respondent seeks its costs, including reserved costs, on the standard basis. In the alternative, it seeks its costs on the standard basis so far as those costs are attributable to the claim for compensation of $2,900,000 on the basis that the highest and best use of the land was for poultry farming.
The respondent’s submissions
The respondent submits that the applicants unreasonably and unnecessarily forced it into litigation. The respondent referred the matter to the Court for compensation to be determined after the parties had not been able to reach agreement. The compensation of $2,900,000 contended for by the applicants was, it is submitted, not supported by the evidence led by the applicants although it was persisted with, unsuccessfully, by them. The evidentiary shortcoming was clearly illuminated, from an early stage of the hearing, by the respondent’s conduct of the case. The conduct of the case for the applicants, in adhering to the chosen basis, ultimately unsuccessfully, wasted costs, says the respondent.
The Acquisition of Land Act 1967 (the Act), provides, by s 27(2) that, in the circumstances of this case, where the amount of compensation is determined to be closer to the amount contended for by the respondent, costs, if ordered, may only be awarded to the respondent. There is…
Keep reading for free
Create a free CaseChat account to read Inglis v State of Queensland (No. 3) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2016] QLC 28
- Decision Date
CaseChat Overview and Summary
The central legal issue the court faced was whether the constructing authority, having been substantially successful in the compulsory acquisition, should be awarded costs under the relevant legislation. The court needed to consider the statutory framework, particularly section 27, and the factors that should influence the exercise of discretion in such matters. The court's decision was to be guided by the principles established in relevant case law and the specific circumstances of the acquisition process.
In its judgment, the court examined the statutory provisions and the case law concerning the award of costs in compulsory acquisition cases. It found that the constructing authority had indeed been substantially successful, but the court exercised its discretion not to award costs to the authority. The court took into account various factors, including the nature of the proceedings and the conduct of the parties involved. The court concluded that, despite the substantial success, the exercise of discretion did not warrant the award of costs to the constructing authority in this instance. The court thus dismissed the General Application filed by the respondent.
Orders
Orders of the court
The General Application filed on behalf of the respondent on 1 April 2014 is dismissed.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi