In the termination of the McKinlay Shire Council – Certified Agreement 2012 – 2014

Case

[2018] QIRC 121

20 September 2018


QUEENSLAND INDUSTRIAL RELATIONS COMMISSION

CITATION:  

In the termination of the McKinlay Shire Council – Certified Agreement 2012 – 2014 [2018] QIRC 121

PARTIES:  

McKinlay Shire Council

and

Construction, Forestry, Mining & Energy, Industrial Union of Employees, Queensland

and

Australian Workers' Union of Employees, Queensland

and

Queensland Services, Industrial Union of Employees

CASE NO:

CB/2018/125

PROCEEDING:

Termination of a certified agreement after nominal expiry date

DELIVERED ON:

20 September 2018

HEARING DATE: 

20 September 2018

HEARD AT:

Brisbane

MEMBER:

Black IC

ORDER:

1. The McKinlay Shire Council – Certified Agreement 2012 – 2015 is terminated.

CATCHWORDS:

INDUSTRIAL LAW – Application for termination after nominal expiry date – Requirements for termination – Agreement terminated

LEGISLATION:

Industrial Relations Act 2016, s 228

APPEARANCES: Ms N Todd for the McKinlay Shire Council
Mr A Santelises for The Australian Workers' Union of Employees, Queensland
Mr J Donaghy for Queensland Services, Industrial Union of Employees

Reasons for Decision

  1. The McKinlay Shire Council has applied to terminate the McKinlay Shire Council – Certified Agreement 2012 – 2015. It does so pursuant to s 228(1) of the Industrial Relations Act 2016.

  1. The Agreement nominally expired on 30 June 2015 and the parties consent to its termination.

  2. Having regard to the affidavit of John Kelly dated 20 August 2018 and on the basis that the agreement does not include any provisions recording that any particular conditions need to be met before it may be terminated; that the Commission is satisfied that the Council has given notice of its intention to apply to terminate the agreement; that the other parties to the agreement agree to it being terminated; and that the termination of the agreement is not contrary to the public interest; the McKinlay Shire Council – Certified Agreement 2012 – 2015 is terminated as from 20 September 2018.

  3. I make the following order:

    1.The McKinlay Shire Council – Certified Agreement 2012 – 2015 is terminated.