In the matter of Yowie Group Ltd (No 2)

Link copied
Case Copied 11 min read


Supreme Court

New South Wales

Case Name: 

In the matter of Yowie Group Ltd (No 2)

Medium Neutral Citation: 

[2025] NSWSC 605

Hearing Date(s): 

On the papers

Date of Orders:

12 June 2025

Decision Date: 

12 June 2025

Jurisdiction: 

Equity - Corporations List

Before: 

Nixon J

Decision: 

1. Order, pursuant to section 98(4)(c) of the Civil Procedure Act 2005 (NSW), that the Defendant pay the Plaintiff’s costs of the proceeding in the gross sum of $33,000 (inclusive of GST).
2. Order, pursuant to section 98(4)(c) of the Civil Procedure Act 2005 (NSW), that the Defendant pay the Plaintiff’s costs of the Interlocutory Process filed on 29 May 2025 in the gross sum of $4,400 (inclusive of GST).

Catchwords: 

COSTS – application for gross sum cost order pursuant to s 98(4) of the Civil Procedure Act 2005 (NSW) – whether appropriate to make a gross sum cost order – quantum of gross sum – no issue of principle

Legislation Cited: 

Civil Procedure Act 2005 (NSW) s 98
Corporations Act 2001 (Cth) ss 173, 1303

Cases Cited: 

Bolton v WAM Active Ltd (No 2) [2025] NSWCA 99
Gabrielle v Abood (No 4) [2023] NSWCA 100
Green Camel Pty Ltd v Urban Ecological Systems Ltd [2017] NSWSC 362
Gupta v Fordham Laboratories Pty Ltd (No 2) [2018] NSWSC 694
Hamod v State of New South Wales & Anor [2011] NSWCA 375
Harrison v Schipp (2002) 54 NSWLR 738; [2002] NSWCA 213
In the matter of Boss Constructions (NSW) Pty Ltd (No 2) [2019] NSWSC 554
In the matter of Cardinal Group Pty Ltd (in liq) and Cardinal Project Services Pty Ltd (in liq) (Lump Sum Costs) [2018] NSWSC 895
In the matter of Ji Woo International Education Centre Pty Ltd [2019] NSWSC 338
In the matter of Keybridge Capital Limited (No 2) [2025] NSWSC 354
In the matter of Keybridge Capital Limited (No 3) [2025] NSWSC 423
In the matter of Keybridge Capital Limited [2025] NSWSC 240
In the matter of Palladium Consulting Pty Limited [2013] NSWSC 92
In the matter of Yowie Group Ltd [2025] NSWSC 524
Lorenzato v Lorenzato & Anor (No 2) [2011] NSWSC 790
Pritchard v Fryer (No 2) [2018] NSWSC 261
Salmon v Albarran (No 2) [2025] NSWCA 115,
WAM Active Limited v Keybridge Capital Limited (No 2) [2024] NSWSC 1496

Category: 

Costs

Parties: 

Keybridge Capital Limited (Plaintiff)
Yowie Group Ltd (Defendant)

Representation: 

Counsel:


Solicitors:
Mills Oakley (Plaintiff)

File Number(s): 

2025/181404

Publication Restriction: 

Nil

JUDGMENT

  1. By Interlocutory Process filed on 29 May 2025, the Plaintiff, Keybridge Capital Limited, seeks a gross sum costs order against the Defendant, Yowie Group Limited.

  2. This proceeding was commenced by way of Originating Process filed in Court by the Plaintiff on 12 May 2025, seeking an order, pursuant to ss 173 and 1303 of the Corporations Act 2001 (Cth), that Yowie forthwith deliver to Keybridge a complete copy of Yowie’s register of members. At the hearing on 21 May 2025, Yowie sought an adjournment, which I refused. Yowie did not otherwise…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read In the matter of Yowie Group Ltd (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NSWSC 605
Decision Date

CaseChat Overview and Summary

In the matter of Yowie Group Ltd (No 2), the Plaintiff, Keybridge, applied for an order that Yowie Group Ltd, the Defendant, deliver a complete copy of its register of members. The application was made under sections 173 and 1303 of the Corporations Act 2001 (Cth). Yowie did not oppose the application. The Court made a judgment in favour of Keybridge, ordering Yowie to deliver the register of members. Following the judgment, Keybridge applied for its costs to be paid on a gross sum basis. The application for gross sum costs raised legal issues concerning the appropriate circumstances for making such an order and the appropriate quantum of those costs.

The Court considered the relevant authority for making a gross sum costs order under s 98(4)(c) of the Civil Procedure Act 2005 (NSW). The Court noted that gross sum costs may be awarded when the quantum of costs is small, and if formal assessment would likely result in delay and expense disproportionate to the amount at issue. The Court also noted that the power to award gross sum costs is discretionary, and the Court must have sufficient confidence in arriving at an appropriate sum on the materials available. The Court found that the circumstances of this case warranted a gross sum costs order and set the quantum at $15,000.

The Court granted Keybridge’s application for costs on a gross sum basis and ordered that Yowie pay $15,000 to Keybridge within 28 days of the date of the judgment. The Court also ordered that if Yowie did not pay within that time, interest would accrue on the amount owing at the rate of 4% per annum. The Court noted that Yowie did not file any submissions in response to the application, and the Court proceeded on the basis that Yowie did not seek to be heard.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

This proceeding was commenced by way of Originating Process filed in Court by the Plaintiff on 12 May 2025, seeking an order, pursuant to ss 173 and 1303 of the Corporations Act 2001 (Cth), that Yowie forthwith deliver to Keybridge a complete copy of Yowie’s register of members. At the hearing on 21 May 2025, Yowie sought an adjournment, which I refused. Yowie did not otherwise make any submissions in opposition to Keybridge’s application. I delivered ex tempore reasons for judgment: In the matter of Yowie Group Ltd [2025] NSWSC 524 (the Primary Judgment). Following the delivery of the Primary Judgment, Keybridge indicated to the Court that it intended to make an application for its costs to be paid on a gross sum basis. Accordingly, I made directions for evidence and submissions to be served in respect of any such application, with the intent that the application be determined on the papers. Keybridge filed its application, evidence and submissions on 29 May 2025. Yowie was directed to file any evidence and submissions in response by 4 June 2025. As at the date of this judgment, 12 June 2025, Yowie has not filed any such material. I have accordingly proceeded on the basis that Yowie does not seek to be heard on this application. For reasons set out below, I am satisfied that an order for gross sum costs should be made. Section 98 of the Civil Procedure Act 2005 (NSW) enlivens a broad power to award costs, including a power to award costs in a specific gross sum instead of assessed costs (s 98(4)(c)). In Hamod v State of New South Wales & Anor [2011] NSWCA 375 at [816], Beazley JA, with whom Giles and Whealy JJA agreed, observed that:"The terms of s 98(4), together with the more general considerations reflected in the Civil Procedure Act ..., suggest that factors that merit particular consideration include: the relative responsibility of the parties for the costs incurred ...; the degree of any disproportion between the issue litigated and the costs claimed; the complexity of proceedings in relation to their cost; and the capacity of the unsuccessful party to satisfy any costs liability ..." In Gabrielle v Abood (No 4) [2023] NSWCA 100 at [6], the Court (Bell CJ, Kirk and Adamson JJA), referred to Hamod and said that: “The power to make a gross sum costs order provided by s 98(4)(c) of the Civil Procedure Act 2005 (NSW) is discretionary. Authority establishes that the discretion is not confined and may be exercised whenever the circumstances warrant its exercise; it should only be exercised when the Court considers that it can do so fairly between the parties, and that includes having sufficient confidence in arriving at an appropriate sum on the materials available; courts have typically applied a discount in assessing costs on a gross sum basis; and the court is not required to undertake a detailed examination of the kind that would be appropriate to taxation or formal costs assessment...” In particular, gross sum costs have been awarded in situations where the quantum of costs is small and the history of the litigation indicates a likelihood, if assessment were to occur, of delay and expense, which would be disproportionate to the amount at issue: see, for example, In the matter of Palladium Consulting Pty Limited [2013] NSWSC 92 at [14] (Black J); Pritchard v Fryer (No 2) [2018] NSWSC 261 at [2], [13] (Fullerton J); In the matter of Cardinal Group Pty Ltd (in liq) and Cardinal Project Services Pty Ltd (in liq) (Lump Sum Costs) [2018] NSWSC 895 at [6] (Gleeson JA); and In the matter of Boss Constructions (NSW) Pty Ltd (No 2) [2019] NSWSC 554 at [3] (Rees J).

Ratio Decidendi

Legal Principle Established