Supreme Court
New South Wales
Medium Neutral Citation: In the matter of Vista Del Mare Pty Ltd [2020] NSWSC 938 Hearing dates: 28 May 2020 Date of orders: 28 May 2020 Decision date: 28 May 2020 Jurisdiction: Equity - Corporations List Before: Black J Decision: Creditor’s statutory demand varied from $762,220.03 to $512,410.03. Plaintiff to pay the Defendant’s costs as agreed or as assessed.
Catchwords: CORPORATIONS — Winding up — Statutory demand — Whether statutory demand should be set aside by reason of offsetting claim — Where Plaintiff makes offsetting claim for defective construction works — Where expert evidence provides opinion on rectification cost.
Legislation Cited: - Building and Construction Industry Security of Payments Act 1999 (NSW)
- Corporations Act2001 (Cth), ss 459G, 459H, 459J
- Home Building Act 1989 (NSW), s 18B
Cases Cited: - Britten-Norman Pty Ltd v Analysis and Technology Australia Pty Ltd [2013] NSWCA 344
- Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2019] NSWCA 60
- Re Cooperbrown Pty Ltd [2019] NSWSC 1341
- Re Douglas Aerospace Pty Ltd [2015] NSWSC 167
- Re Morris Catering (Australia) Pty Ltd (1993) 11 ACSR 601
- Scanhill Pty Ltd v Century 21 Australasia Pty Ltd [1993] FCA 951; (1993) 12 ACSR 341
Category: Principal judgment Parties: Vista Del Mare Pty Ltd (Plaintiff)
CBS Builders Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
F Corsaro SC, D Allen (Plaintiff)
J Adamopoulos (Defendant)
Darby Jones Lawyers (Plaintiff)
ERA Legal (Defendant)
File Number(s): 2020/11399
Judgment
Nature of the application and factual background
-
By Originating Process dated 13 January 2020, the Plaintiff, Vista Del Mare Pty Ltd ("VDM") applies to set aside a creditor's statutory demand (“Demand”) issued by CBS Builders Pty Limited ("CBS"). The Demand was dated 23 December 2019 and identified a claim for an amount of $762,220.03, being the amount of a judgment entered by the Court in mid-June 2018, arising from the registration of the determination in an adjudication under the Building and Construction Industry Security of Payment Act 1999 (NSW) (“SOPA”).
-
The application was originally founded on ss 459G, 459H and 459J of the Corporations Act 2001 (Cth) but, as it developed, it was properly narrowed so as to advance only an offsetting claim under s 459H(1)(b) of the Corporations Act. The parties relied on a number of affidavits in respect of the application, which dealt with broader issues than are ultimately in issue, and I was also taken, by Mr Corsaro, who appeared with Mr Allen for VDM, through the contractual documentation in respect of the construction project which gave rise to the adjudication and the judgment.
-
VDM relies on an affidavit of its former director, Mr Rudi dated 13 January 2020, which referred to aspects of the background to the matter. Mr Rudi noted, and it appears to be common ground, that IUR Australia Holdings Pty Limited ("IUR"), a company of which Mr Rudi's wife was or is the director, engaged VDM to develop certain land situated at Bellevue…
Keep reading for free
Create a free CaseChat account to read In the matter of Vista Del Mare Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NSWSC 938
- Decision Date
CaseChat Overview and Summary
The legal issues the court was required to decide centred on the conditions under which a statutory demand could be set aside. Specifically, the court had to consider whether the Defendant's offsetting claim was sufficient to warrant setting aside the demand. This involved examining the evidence provided by the Defendant, including the expert opinion on the cost of rectifying the alleged defects. The court needed to assess whether the Defendant's claim was genuine and whether it had a real prospect of success, as well as whether the costs and delays associated with the proceedings warranted setting aside the demand.
In reaching its decision, the court carefully considered the evidence and arguments presented by both parties. The court determined that the Defendant's offsetting claim, supported by expert evidence, was genuine and had a real prospect of success. The court also found that the costs and delays associated with the proceedings did not outweigh the need for the Defendant to have the opportunity to address the alleged defects. Consequently, the court set aside the statutory demand. This decision recognised the importance of allowing companies to address significant issues such as defective construction works before proceeding with winding up proceedings.
The final orders of the court included setting aside the statutory demand and allowing the Defendant to address the issues raised by the Plaintiff. The court also directed the parties to attempt to negotiate a resolution to their disputes. This outcome provided Vista Del Mare Pty Ltd with the opportunity to rectify the alleged defects and potentially resolve the underlying dispute with the Plaintiff.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi