| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
judicial review and appeals list
S CI 2015 06503
| IMERVA CORPORATION PTY LTD (ACN 124 486 308) | Plaintiff |
| v | |
| ANTON KUNA & JAGA KUNA | Defendants |
---
JUDGE: | McDonald J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 20 and 21 July 2016 |
DATE OF JUDGMENT: | 18 August 2016 |
CASE MAY BE CITED AS: | Imerva Corporation Pty Ltd v Kuna |
MEDIUM NEUTRAL CITATION: | [2016] VSC 461 |
---
ADMINISTRATIVE LAW – Application for leave to appeal from Victorian Civil and Administrative Tribunal on questions of law – whether parties to a major domestic building contract had agreed that the progress payments regime prescribed by the Domestic Building Contracts Act 1995 did not apply – whether plaintiff able to contend that defendants were estopped from insisting upon compliance with the statutory regime for progress payments – decision of Tribunal not attended by sufficient doubt to warrant the grant of leave to appeal – Victorian Civil and Administrative Tribunal Act 1998 s 148 – Domestic Building Contracts Act 1995 ss 11, 40, 132 – Domestic Building Contract Regulations 2007 reg 12.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr M Robins QC | Guymer Lawyers Pty Ltd |
| For the Defendants | Mr R Andrew | Noble Lawyers |
HIS HONOUR:
The plaintiff (‘Imerva’) seeks leave to appeal against orders made by the Victorian Civil and Administrative Tribunal (‘the Tribunal’) constituted by Senior Member Walker dated 27 November 2015. Leave to appeal is sought pursuant to s 148 of the Victorian Civil and Administrative Tribunal Act 1998 (‘VCAT Act’).[1]
[1]Summons on Originating Motion filed 23 December 2015, [1].
The proceedings in the Tribunal involved a dispute between Imerva and Anton and Jaga Kuna (‘the owners’) in respect of a major domestic building contract within the meaning of the Domestic Building Contracts Act1995 (‘the Act’).
Under the contract Imerva agreed to construct two units for the owners for a price of $1,983,024.00 inclusive of GST.
‘Schedule 3 Method 2’ of the contract states that the parties agreed:
(i) that the Progress Payments fixed by Section 40 of the Domestic Building Contracts Act 1995 do not apply; and
(ii) that instead the percentage of the Contract Price and the amounts payable are as follows:[2]
Thereafter a table, annexed to this judgment marked ‘Annexure A’, prescribes progress payments of varying percentages and amounts for 20 separate stages totalling $1,983,024.00.
[2]‘Victorian New Homes Contract for 4 Inner Crescent Brighton’ dated 13 January 2013, 9.
Immediately following on from Schedule 3 Method 2, at page 10 of the contract is a document headed ‘Attachment 1’. Thereunder appears the sub-heading ‘FORM 1 OF THE REGULATIONS – REGULATION 6(A) WARNING TO OWNER – CHANGE OF LEGAL RIGHTS’.[3] The full text of this document, with the initials redacted, is annexed to this judgment marked ‘Annexure B’.
[3]Ibid 10.
Both at first instance and in the current proceedings it was not in dispute that payments totalling $872,531.00 were made by the owners to Imerva.[4]…
Keep reading for free
Create a free CaseChat account to read Imerva Corporation Pty Ltd v Kuna and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] VSC 461
- Decision Date
CaseChat Overview and Summary
The Court examined the nature of the contractual agreement between the parties, the applicability of the statutory regime, and the potential for an estoppel preventing the defendants from insisting on compliance with the statutory regime. The Court concluded that the Tribunal's findings were well-reasoned and supported by evidence, and that the decision did not contain sufficient doubt to merit an appeal. The Court held that the defendants were not estopped from enforcing the statutory regime, and that the plaintiff's arguments did not present a substantial question of law warranting appellate jurisdiction.
In light of the above, the Court dismissed the plaintiff's application for leave to appeal, affirming the Tribunal's decision. The Court found that the statutory regime for progress payments was applicable to the defendants' domestic building contract, and that the defendants were not estopped from enforcing the statutory requirements. The Court's decision underscores the importance of clear contractual terms and the need for parties to adhere to the statutory framework governing domestic building contracts in Victoria.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.