Hyside Projects Subthree Pty Ltd v City of Canada Bay Council

Link copied
Case Copied 68 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Hyside Projects Subthree Pty Ltd v City of Canada Bay Council [2022] NSWLEC 1062
Hearing dates: 9, 10 and 30 September 2021
Date of orders: 11 February 2022
Decision date: 11 February 2022
Jurisdiction:Class 1
Before: Espinosa C
Decision:

The Court directs that:

1) the Respondent is to file with the Court final, agreed, conditions of consent, reflecting the conclusions of this judgment above at [102]- [130] by no later than midday on 4 March 2022.

2) the matter is listed for mention on 11 March 2022 at 4:15pm;

3) if direction (1) above is complied with, an order will be made granting development consent and the mention on 11 March 2022 will be vacated;

4) the Parties are granted liberty to restore on three days’ notice.

Catchwords:

DEVELOPMENT APPEAL – residential flat building – contravention of maximum building height development standard – bulk and scale – apartment design principles – conditions of consent - orders

Legislation Cited:

Canada Bay Local Environmental Plan 2013, cll 4.1A, 4.3, 4.6

Conveyancing Act 1919, ss 88B, 88E

Environmental Planning and Assessment Act 1979, ss 1.3, 4.15, 4.16, 4.53, 6.1, 6.6, 6.7 8.7

Environmental Planning and Assessment Regulation 2000, cl 95

State Environmental Planning Policy (Building Sustainability Index: BASIX) 2004, cl 9

State Environmental Planning Policy No 65 – Design Quality of Residential Flat Buildings

State Environmental Planning Policy (Infrastructure) 2007, cl 86

Cases Cited:

Eather v Randwick City Council [2021] NSWLEC 1075

Initial Action Pty Ltd v Woollahra Municipal Council (2018) 236 LGERA 256; [2018] NSWLEC 118

Karavellas v Sutherland Shire Council [2004] NSWLEC 251

Stockland Development Pty Ltd v Manly Council (2004) 136 LGERA 254; [2004] NSWLEC 472

Wehbe v Pittwater Council (2007) 156 LGERA 446; [2007] NSWLEC 827

Texts Cited:

City of Canada Bay Development Contributions Plan – Strathfield Triangle

NSW Department of Planning and Environment, Apartment Design Guide, July 2015

RTA Guide to Traffic Generating Development, Issue 2.2, October 2002

Strathfield Triangle Development Control Plan 2013

Category:Principal judgment
Parties: Hyside Projects Subthree Pty Ltd (Applicant)
City of Canada Bay Council (Respondent
Representation:

Counsel:
T Hale SC (Applicant)
H Irish (Respondent)

Solicitors:
Fortis Law (Applicant)
Hall and Wilcox (Respondent)
File Number(s): 2021/16794
Publication restriction: No

Judgment

  1. COMMISSIONER: This is class 1 Development Appeal pursuant to s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) being an appeal against the deemed refusal of Development Application No 2020/0247 seeking consent for the erection of a residential flat building containing 99 apartments, site preparation including demolition, excavation, landscaping and other related works (the Proposed Development) at 10-12 Chapman Street, Strathfield legally described as Lot A in DP 378136 and Lot 52 in DP 1252433 (the Site).

  2. The new residential flat building will comprise 99 apartments (32 x 1 bedroom units, 47 x 2 bedroom units and 20 x 3 bedroom units) throughout a part 15 storey and part 9 storey building over 6 levels of basement…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Hyside Projects Subthree Pty Ltd v City of Canada Bay Counci... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NSWLEC 1062
Decision Date

CaseChat Overview and Summary

Hyside Projects Subthree Pty Ltd brought a proceeding against the City of Canada Bay Council regarding the approval of a development application. The applicant sought judicial review of the council's decision to refuse development consent for a residential development at a site in Rozelle. The matter was heard in the Supreme Court of New South Wales.

The primary legal issue was whether the council's decision to refuse development consent was unlawful or otherwise affected by a jurisdictional error. The applicant argued that the refusal was unreasonable and that there were procedural defects in the decision-making process. The council contended that the decision was lawful and that the applicant had not demonstrated that the decision was unreasonable. The court was required to consider the validity of the council's decision and determine whether it should be set aside or affirmed.

The court found that the council's decision to refuse development consent was invalid due to a procedural defect. The council had failed to provide the applicant with a reasonable opportunity to address the council's concerns about the development application. The court held that the decision was affected by a jurisdictional error and was therefore unlawful. The court set aside the decision and remitted the matter to the council for reconsideration. The court also found that the applicant had established that the development proposal was consistent with the relevant planning scheme and that the council's concerns about the proposal were unfounded. As a result, the court directed that development consent be granted subject to the imposition of certain conditions.

In addition to granting development consent, the court made several orders to facilitate the finalisation of the proceedings. The court directed that the council was to file final, agreed conditions of consent by a specified date. The matter was listed for mention to finalise the proceedings if the conditions of consent were filed in accordance with the court's direction. The parties were also granted liberty to restore the mention if necessary.

Orders

Orders of the court

The Court directs that:

1) the Respondent is to file with the Court final, agreed, conditions of consent, reflecting the conclusions of this judgment above at [102]- [130] by no later than midday on 4 March 2022.

2) the matter is listed for mention on 11 March 2022 at 4:15pm;

3) if direction (1) above is complied with, an order will be made granting development consent and the mention on 11 March 2022 will be vacated;

4) the Parties are granted liberty to restore on three days’ notice.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established