Hunter Development and Brokerage Pty Ltd v Cessnock City Council

Link copied
Case Copied 16 min read
Reported Decision: [2005] NSWCA 169
(2006) LGERA 460

Land and Environment Court


of New South Wales


CITATION:

Hunter Development and Brokerage Pty Ltd v Cessnock City Council [2005] NSWLEC 727

PARTIES:

APPLICANT:
Hunter Development and Brokerage Pty Ltd

RESPONDENT:
Cessnock City Council

FILE NUMBER(S):

11564 of 2003

CORAM:

Bignold J

KEY ISSUES:

Costs :- in class 1 proceedings—normative approach that there be no costs should be applied

LEGISLATION CITED:

Rules of Court
Part 16 Rule 4

CASES CITED:

Broadwater Action Group Inc v Richmond Valley Council (No 2) (2003) 129 LGERA 401;
Gee v Port Stephens Council;
(2003) 131 LGERA 325;
MacDonald v Mosman Municipal Council (No 2) (2000) 107 LGERA 211;
Outdoor Australia v Auburn Council (1996) 89 LGERA 365;
Smith v Wyong Council (1984) 53 LGRA 170

DATES OF HEARING: 16/12/2005
 
DATE OF JUDGMENT: 


16/12/2005

EX TEMPORE JUDGMENT DATE:

16/12/2005

LEGAL REPRESENTATIVES:

APPLICANT:
Mr J Kildea, Barrister
SOLICITORS
Thompson Norrie

RESPONDENT:
Ms J Jagot, Barrister
SOLICITORS
Cleaves Mallick Gibbs


JUDGMENT:


test

          THE LAND AND
          ENVIRONMENT COURT
          OF NEW SOUTH WALES

          BIGNOLD J

          16 December 2005

          11564 of 2005 HUNTER DEVELOPMENT AND BROKERAGE PTY LIMITED v CESSNOCK CITY COUNCIL

          JUDGMENT

      HIS HONOUR:

      1 This is an application by the Applicant in class 1 proceedings (in which it failed before me) for costs in the proceedings, as a result of a successful appeal to the Court of Appeal and the remitter to this Court by the Court of Appeal of the proceedings. The proceedings involved an appeal pursuant to the Environmental Planning and Assessment Act 1979, s 109K against the Council’s refusal to issue a construction certificate in respect of subdivision work for a subdivision of land situated at North Rothbury in accordance with a development consent that had been granted by the Council in February 1998.

      2 As my reasons for judgment at first instance in a judgment delivered on 17 August 2004 indicate the sole reason stated by the Council for its refusal to issue the construction certificate was that the development consent is deemed to have lapsed pursuant to the provisions of the Environmental Planning and Assessment Act, s 95.

      3 According to the statement of issues filed in the proceedings by each party, the only issue raised by the appeal concerned the question whether or not the development consent had lapsed on 24 February 2003, being the expiry of the relevant lapsing period of five years prescribed by s 95 subs (1A).

      4 In the result, as I have indicated, the Applicant was unsuccessful before me on this sole issue and the appeal was dismissed (see (2004) NSWLEC 454).

      5 However, on appeal to the Court of Appeal, the Court of Appeal reversed my decision and held that the development consent granted in 1998 had not relevantly lapsed pursuant to the statutory lapsing provision.

      6 Upon the remitter, the parties agreed as to the ultimate disposal of the case, save for the question of costs, and by consent, orders were made by…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Hunter Development and Brokerage Pty Ltd v Cessnock City Cou... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2005] NSWLEC 727
Decision Date

CaseChat Overview and Summary

Hunter Development and Brokerage Pty Ltd sought a costs order against Cessnock City Council following a successful appeal to the Court of Appeal. The original proceedings involved an appeal against the Council’s refusal to issue a construction certificate in relation to a land subdivision. The Land and Environment Court dismissed the appeal, but the Court of Appeal reversed the decision and held that the development consent had not lapsed. The issue before the Land and Environment Court was whether it was fair and reasonable to order the Council to pay the Applicant’s costs.

The court noted that the prevailing norm in planning and building appeals was that no order for costs would be made unless the court considered it fair and reasonable to do so. The court considered submissions from both parties on the appropriate approach to the exercise of this discretion. The Applicant argued that the Council should pay costs due to their ultimate success on appeal. The Council argued that the Applicant should not be awarded costs because they could have, and should have, pursued the issue in separate proceedings.

The court found that the Applicant had deliberately chosen to proceed with the class 1 appeal despite the Council raising the issue of whether the development consent had lapsed. The court held that the Council was acting on a prevailing view of the law and that the issue of statutory lapsing was an important one that had only recently been settled by the Court of Appeal. Given these factors, the court did not consider it fair and reasonable to order the Council to pay the Applicant’s costs.

The court did, however, order that each party pay their own costs of the motion for costs, in line with the usual practice of the court. The court held that there was no binding authority establishing governing principles for the exercise of the discretion under the new rule, and that each case must be considered on its own facts.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.