NEW SOUTH WALES COURT OF APPEAL
CITATION: HSH Hotels v Multiplex [2004] NSWCA 302
FILE NUMBER(S):
40088/04
HEARING DATE(S): 21 July 2004, 22 July 2004
JUDGMENT DATE: 15/09/2004
PARTIES:
HSH Hotels (Australia) Ltd
Multiplex Constructions Pty Limited
JUDGMENT OF: Mason P Hodgson JA Tobias JA
LOWER COURT JURISDICTION: Supreme Court - Equity Division
LOWER COURT FILE NUMBER(S): SC 55002/00
LOWER COURT JUDICIAL OFFICER: Bergin J
COUNSEL:
A: Mr A Sullivan QC / Mr Watts QC
R: Mr Rudge SC / Mr D Miller
SOLICITORS:
A: Griffins, Sydney
R: Minter Ellison, Sydney
CATCHWORDS:
Contract - Building contracts - Construction of - Completion - Minor defects - If considered collectively - Referee's report
Evidence - No cross-examination - Whether practical - Evidence in direct contradiction - Rejection of non-cross-examined evidence
Practice and Procedure - Amendments - Prejudice - Trial in near future
Costs - Offer of compromise - Addressed to two parties - Only acceptable by both - One party reasonably refuses offer - Other party liable in amount greater than offer - Whether indemnity costs may be ordered against other party
LEGISLATION CITED:
Nil
DECISION:
(a) Appeal dismissed with costs
(b) Cross-appeal dismissed with costs.
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
CA 40088/04
SC 55002/00MASON P
HODGSON JA
TOBIAS JAWednesday 15 September 2004
HSH HOTELS (AUSTRALIA) LIMITED as trustee of SHR KENT STREET TRUST v MULTIPLEX CONSTRUCTIONS PTY LIMITED
A dispute arose over whether certain stages of a hotel development had been completed properly. In particular, there were said to be 16,000 defects, one of which was the fact that, at the said completion of the first stage, only one out of a possible four lifts serviced every floor of the hotel.
The contract defined a stage as being complete when two conditions were satisfied (the completion conditions). First, where the stage was completed except for minor defects that did not prevent, and whose correction would not prejudice, the ability to use the stage as intended. Secondly, where the builder (Multiplex) had done everything the contract required prior to completion.
The issues on appeal, following the handing down of a referee’s report which had been accepted by the primary judge, included:
- Whether, in virtue of the second of the completion conditions, a stage could be said to be properly completed where any minor defects remained;
- Whether the referee erred in preferring the evidence of the builder’s witnesses, in relation to the seriousness of the defects, over non-cross-examined evidence led by the owner’s expert witness;
- Whether the referee erred in not considering if several minor defects could collectively equate to a ‘major’ defect;
- Whether the referee ought to have allowed the owner (HSH) to amend the particulars of their defence; and
- Whether the primary judge ought to have found that Multiplex was entitled to indemnity costs from the date of an offer of compromise.
HELD: (per Tobias JA with Mason P and Hodgson JA agreeing) (1) It was…
Continue reading HSH Hotels (Australia) Ltd v Multiplex Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- HSH Hotels (Australia) Ltd v Multiplex Constructions Pty Ltd [2004] NSWCA 302
- Case
- [2004] NSWCA 302
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the primary judge erred in upholding a referee's finding that Stage 1A was complete, despite the unavailability of certain lifts to all relevant levels. This involved construing the terms of the building contract, particularly the definition of "Completion" and the "Completion Requirements" as set out in the Contract Particulars, and assessing whether the omission of lift access to certain levels constituted a "minor Defect" that did not prevent the stage from being reasonably capable of use for its intended purposes.
The court's reasoning focused on the interpretation of the contract's completion provisions. Multiplex argued that sufficient and continuous access was provided by the goods lift (Lift 4), which was capable of transporting furnishings from the loading dock to all accommodation levels. They contended that the omission of lifts 1 and 2 to certain levels was a "minor Defect" because it did not prevent the intended use of Stage 1A for fitout and sales activities, and that the installation of these lifts would not prejudice the convenient use of the levels. The primary judge had found that the referee's conclusion that the access arrangements satisfied the contractual test was open to him and that no relevant error had been demonstrated.
The appeal and cross-appeal were both dismissed with costs.
Orders
Orders of the court
(a) Appeal dismissed with costs
(b) Cross-appeal dismissed with costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.