Land and Environment Court
of New South Wales
CITATION: Hornsby Shire Council v Symon [2003] NSWLEC 410 PARTIES: PROSECUTOR
DEFENDANT
Hornsby Shire Council
George SymonFILE NUMBER(S): 50038 of 2003 CORAM: Talbot J KEY ISSUES: Prosecution :- development without construction certificate - plea of guilty - penalty
LEGISLATION CITED: Environmental Planning and Assessment Act 1979 s 81A(2) CASES CITED: DATES OF HEARING: 24/11/2003 EX TEMPORE
JUDGMENT DATE :
11/24/2003LEGAL REPRESENTATIVES: DEFENDANT
PROSECUTOR
Mr P R Clay (Barrister)
SOLICITORS
McKees
Mr A M Pickles (Barrister)
SOLICITORS
Colin Biggers & Paisley
JUDGMENT:
IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
50038 of 2003
24 November 2003Talbot J
- Prosecutor
- Defendant
Introduction
1 HIS HONOUR: The defendant, George Symon, is charged that between 7 November 2002 and 3 December 2002 he caused development to be carried out at 8 Roach Avenue, Thornleigh, being his residence, in accordance with a development consent prior to the issue of a construction certificate, a thing forbidden to be done under s 81A(2) of the Environmental Planning and Assessment Act 1979 (“the EP&A Act”).
2 The works complained of were actually carried out between 7 November 2002 and 11 November 2002 and comprised three elements. Firstly, the excavation of a trench for footings, secondly, the pouring of concrete into the trench for the purpose of construction of footings and thirdly, the pouring of the concrete slab in the location of approved extensions.
3 A private certifier had been engaged. The certifier issued a construction certificate on 3 December 2002. On its face the construction certificate appears to deal with the works that already had been carried out.
4 Notwithstanding that the works were by then complete in respect of those three aspects, the certifier nevertheless issued a certificate on 3 December 2002. It is difficult for the Court to speculate as to what really happened, but it is noted that the certifier did not even receive the plans until 28 November 2002. That is apparent from the face of the certificate yet the work was carried out between 7 and 11 November 2002.
5 Mr Pickles, who appears for the defendant, made a submission from the bar table that the defendant had a conversation with the certifier prior to carrying out the work and he then indicated to him that it would be all right to proceed.
6 I find that submission difficult to accept in the circumstances. It certainly is a question of timing, as Mr Pickles submits, but I do not think it is a question of timing in the context that he put it. One would be entitled to infer that the certifier may not have even received instructions, or at least complete instructions, until after the work had been completed.
7 Mr Clay, who appears for Hornsby Shire Council (“the council”), has informed the Court that the council raises no issue as to there being any environmental harm. Furthermore, it is an agreed…
Keep reading for free
Create a free CaseChat account to read Hornsby Shire Council v Symon and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] NSWLEC 410
- Decision Date
CaseChat Overview and Summary
The court noted that the defendant had carried out works in violation of the Act between 7 November 2002 and 3 December 2002, which included excavating a trench for footings, pouring concrete into the trench, and pouring the concrete slab in the location of approved extensions. Despite the certifier issuing a construction certificate on 3 December 2002, the court found it difficult to accept the defendant's claim that he had a conversation with the certifier prior to carrying out the work. The court also noted that the defendant had previously been issued infringement notices for carrying out unauthorised demolition works and excavation for an in-ground swimming pool without development consent.
In determining the penalty, the court considered the maximum penalty of $1.1 million for a breach of the EP&A Act and the fact that the offence was in the lower range. The court accepted the defendant's contrition and his submission that he was unlikely to re-offend. However, the court also emphasised the importance of general deterrence and the need to make it clear to the public that building or other works subject to the control of the EP&A Act must comply strictly with the provisions of the Act. The court took into account the defendant's early plea of guilty and the efficient conduct of the trial, reducing the penalty to $16,000.
The court ordered that the defendant be convicted of the charge and pay a monetary penalty by way of a fine in the sum of $16,000, as well as the council's costs as agreed or assessed. The exhibits were to be returned.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.