Hornsby Shire Council v Symon

Link copied
Case Copied 7 min read

>

Land and Environment Court


of New South Wales


CITATION: Hornsby Shire Council v Symon [2003] NSWLEC 410
PARTIES:

PROSECUTOR
Hornsby Shire Council

DEFENDANT
George Symon
FILE NUMBER(S): 50038 of 2003
CORAM: Talbot J
KEY ISSUES: Prosecution :- development without construction certificate - plea of guilty - penalty
LEGISLATION CITED: Environmental Planning and Assessment Act 1979 s 81A(2)
CASES CITED:
DATES OF HEARING: 24/11/2003
EX TEMPORE
JUDGMENT DATE :

11/24/2003
LEGAL REPRESENTATIVES:


PROSECUTOR
Mr P R Clay (Barrister)
SOLICITORS
McKees

DEFENDANT
Mr A M Pickles (Barrister)
SOLICITORS
Colin Biggers & Paisley


JUDGMENT:

IN THE LAND AND


ENVIRONMENT COURT


OF NEW SOUTH WALES

                          50038 of 2003

                          Talbot J

                          24 November 2003
Hornsby Shire Council
                                  Prosecutor
      v
George Symon
                                  Defendant
Judgment

      Introduction

1 HIS HONOUR: The defendant, George Symon, is charged that between 7 November 2002 and 3 December 2002 he caused development to be carried out at 8 Roach Avenue, Thornleigh, being his residence, in accordance with a development consent prior to the issue of a construction certificate, a thing forbidden to be done under s 81A(2) of the Environmental Planning and Assessment Act 1979 (“the EP&A Act”).

2 The works complained of were actually carried out between 7 November 2002 and 11 November 2002 and comprised three elements. Firstly, the excavation of a trench for footings, secondly, the pouring of concrete into the trench for the purpose of construction of footings and thirdly, the pouring of the concrete slab in the location of approved extensions.

3 A private certifier had been engaged. The certifier issued a construction certificate on 3 December 2002. On its face the construction certificate appears to deal with the works that already had been carried out.


4 Notwithstanding that the works were by then complete in respect of those three aspects, the certifier nevertheless issued a certificate on 3 December 2002. It is difficult for the Court to speculate as to what really happened, but it is noted that the certifier did not even receive the plans until 28 November 2002. That is apparent from the face of the certificate yet the work was carried out between 7 and 11 November 2002.

5 Mr Pickles, who appears for the defendant, made a submission from the bar table that the defendant had a conversation with the certifier prior to carrying out the work and he then indicated to him that it would be all right to proceed.

6 I find that submission difficult to accept in the circumstances. It certainly is a question of timing, as Mr Pickles submits, but I do not think it is a question of timing in the context that he put it. One would be entitled to infer that the certifier may not have even received instructions, or at least complete instructions, until after the work had been completed.

7 Mr Clay, who appears for Hornsby Shire Council (“the council”), has informed the Court that the council raises no issue as to there being any environmental harm. Furthermore, it is an agreed…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Hornsby Shire Council v Symon and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2003] NSWLEC 410
Decision Date

CaseChat Overview and Summary

In the Land and Environment Court of New South Wales, Hornsby Shire Council brought a prosecution against George Symon for carrying out development at his residence in Thornleigh without obtaining a construction certificate as required by section 81A(2) of the Environmental Planning and Assessment Act 1979. The defendant pleaded guilty to the charge. The court was required to determine the appropriate penalty for the offence, taking into account various factors such as the defendant's contrition, early plea of guilty, and the efficient conduct of the trial.

The court noted that the defendant had carried out works in violation of the Act between 7 November 2002 and 3 December 2002, which included excavating a trench for footings, pouring concrete into the trench, and pouring the concrete slab in the location of approved extensions. Despite the certifier issuing a construction certificate on 3 December 2002, the court found it difficult to accept the defendant's claim that he had a conversation with the certifier prior to carrying out the work. The court also noted that the defendant had previously been issued infringement notices for carrying out unauthorised demolition works and excavation for an in-ground swimming pool without development consent.

In determining the penalty, the court considered the maximum penalty of $1.1 million for a breach of the EP&A Act and the fact that the offence was in the lower range. The court accepted the defendant's contrition and his submission that he was unlikely to re-offend. However, the court also emphasised the importance of general deterrence and the need to make it clear to the public that building or other works subject to the control of the EP&A Act must comply strictly with the provisions of the Act. The court took into account the defendant's early plea of guilty and the efficient conduct of the trial, reducing the penalty to $16,000.

The court ordered that the defendant be convicted of the charge and pay a monetary penalty by way of a fine in the sum of $16,000, as well as the council's costs as agreed or assessed. The exhibits were to be returned.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.