Holts Hill Quarries Pty Ltd v Gold Coast City Council

Link copied
Case Copied 7 min read

SUPREME COURT OF QUEENSLAND

CITATION:  Holts Hill Quarries P/L v Gold Coast City Council [1999]
QCA 510
PARTIES:  HOLTS HILL QUARRIES PTY LTD (ACN 079 443 762)
(Appellant)
v
GOLD COAST CITY COUNCIL
(First Respondent/Applicant)
AND
NERANG COMMUNITY ASSOCIATION INC,
PAUL STEVEN STEMP & ORS
(Second Respondent)
AND
LYNN OGDEN
(Third Respondent)
AND
PETER THOMAS BURKE
(Fourth Respondent)
FILE NO/S:  Appeal No 7006 of 1999A
Southport P&E Appeal No 1028 of 1998
DIVISION:  Court of Appeal
PROCEEDING:  Application to strike out
ORIGINATING
COURT: 
Planning and Environment Court at Southport
DELIVERED ON:  7 December 1999
DELIVERED AT:  Brisbane
HEARING DATE:  22 November 1999
JUDGES:  de Jersey CJ, Thomas JA, Helman J
ORDER:  First respondent’s application refused.
First respondent to pay the appellant’s costs of the
application to be assessed.
No order in relation to costs with respect to the third and
fourth respondents.
CATCHWORDS:  LOCAL GOVERNMENT – APPEALS – QUEENSLAND – PLANNING AND ENVIRONMENT COURT – whether necessary for appellant to obtain leave to appeal to Court of Appeal against decision in Planning and Environment Court - –construction of s 6.1.25 and s 6.1.26 Integrated Planning Act 1997 – whether sections apply only to appeals to the Planning and Environment Court or also to further appeals
Colonial Sugar Refining Co v Irving [1905] AC 369,
considered
Sunskill Investments Pty Ltd v Townsville Office Services Pty
Ltd [1991] 2 Qd R 210, considered
Integrated Planning Act 1997, s 4.1.56, s 6.1.23(1)(b), s
6.1.25, s 6.1.26, s 6.1.39
Local Government (Planning and Environment) Act 1990, s
4.3(1), s 4.13(12), s 7.4
COUNSEL:  Mr D Gore QC, with him Mr T Trotter, for the appellant
Mr P Lyons QC, with him Mr S Ure, for the first respondent
The third respondent appeared on her own behalf
The fourth respondent appeared on his own behalf
SOLICITORS:  Minter Ellison for the appellant
King & Company for the first respondent
The third respondent appeared on her own behalf
The fourth respondent appeared on his own behalf
  1. THE COURT: The appellant unsuccessfully applied to the Gold Coast City Council (“the Council”) on 10 February 1998 for approval for rezoning of land at Nerang from “Rural” to “Extractive Industry”, and for town planning consent for the development and operation of a quarry. The appellant then appealed unsuccessfully to the Planning and Environment Court, which on 21 June 1999 dismissed the appeal. On 30 July 1999 the appellant filed a notice of appeal to this Court, against the dismissal of the appeal by the Planning and Environment Court. The Council has applied for an order that the appeal be struck out, on the basis that the appellant failed first to obtain leave to appeal. The issue is whether that was necessary.

  2. The Council’s contention that it was derives from s 4.1.56 of the Integrated Planning Act 1997, which provides for appeal to the Court of Appeal, but only with leave. The operation of that provision commenced on 30 March 1998, with the repeal of the Local Government (Planning and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Holts Hill Quarries Pty Ltd v Gold Coast City Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[1999] QCA 510
Decision Date

CaseChat Overview and Summary

Holts Hill Quarries Pty Ltd sought leave to appeal a decision of the Planning and Environment Court of Queensland, which had dismissed their challenge to a decision of the Gold Coast City Council. The Council had approved a development application, which Holts Hill Quarries opposed. The Planning and Environment Court had ruled that Holts Hill Quarries had not satisfied the criteria to obtain leave to appeal to the Court of Appeal. The legal issues before the court were whether the Integrated Planning Act 1997 required Holts Hill Quarries to obtain leave to appeal to the Court of Appeal, and whether certain sections of the Act applied to further appeals.

The court found that the relevant sections of the Act applied to all appeals, not just those to the Planning and Environment Court. It held that the sections did not limit the ability of a party to appeal to the Court of Appeal. The court found that Holts Hill Quarries had not demonstrated that they would succeed on appeal, and therefore did not grant leave to appeal. The court also held that the first respondent, Gold Coast City Council, should pay the costs of the application. There was no order in relation to costs with respect to the third and fourth respondents.

Orders

Orders of the court

First respondent’s application refused.

First respondent to pay the appellant’s costs of the

application to be assessed.

No order in relation to costs with respect to the third and

fourth respondents.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established