SUPREME COURT OF QUEENSLAND
CITATION:
HM Hire Pty Ltd v National Plant and Equipment Pty Ltd & anor [2012] QSC 4
PARTIES:
HM HIRE PTY LTD (ACN 131 017 813)
(applicant)
v
NATIONAL PLANT AND EQUIPMENT PTY LTD (ACN 078 654 323)
(first respondent)
PHILIP DAVENPORT
(second respondent)FILE NO/S:
8794/11
DIVISION:
Trial
PROCEEDING:
Application
DELIVERED ON:
31 January 2012
DELIVERED AT:
Supreme Court, Brisbane
HEARING DATE:
27 October 2011
JUDGE:
Douglas J
ORDER:
Application dismissed
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where second respondent exercised jurisdiction as an adjudicator under the Building and Construction Industry Payments Act 2004 (Qld) (“the Act”) to decide that the applicant should make a progress payment to the respondent – where contract required the applicant to perform clear and grub works, topsoil stripping and placement at project site – where work actually performed was the excavation and removal of timber and topsoil from the site – whether the work carried out for which payment was sought was “construction work” – whether the work carried out fell within the exclusion under s 10(3)(b) of the Act
Building and Construction Industry Payments Act 2004 (Qld), ss 10(1), 10(3), 12
Mineral Resources Act 1989 (Qld), ss 6A(1), 6A(3)
Queensland Building Services Authority Regulation 2003 (Qld), reg 5(y)Brian Leigh Smith v Coastivity Pty Ltd [2008] NSWSC 313 referred
Federal Commissioner of Taxation v Broken Hill Pty Co Ltd (1969) 120 CLR 240 cited
Gonzo Holdings Pty Ltd v McKie [1996] 2 Qd R 240 cited
HM Australia Holdings Pty Ltd v Edelbrand Pty Ltd [2011] NSWSC 604 referred
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355 cited
Taylor v Public Service Board (NSW) (1976) 137 CLR 208 cited
Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2011] QSC 345 followedCOUNSEL:
D O Savage SC for the applicant
M D Ambrose for the first respondent
No appearance for the second respondentSOLICITORS:
Morrow Peterson Lawyers for the applicant
Sparke Helmore Lawyers for the first respondent
The issue raised by this case is whether the second respondent, Philip Davenport, was entitled to exercise his jurisdiction as an adjudicator under the Building and Construction Industry Payments Act 2004 (Qld) (“the Act”) to decide that the applicant should make a progress payment to the respondent. The particular question is whether the relevant work on a mining site in Central Queensland for which payment was sought was “construction work” as defined in s 10 of that Act. As part of that debate the question arose whether this work fell within an exclusion in s 10(3) dealing with the extraction of minerals. Mr Davenport concluded that he had jurisdiction and ordered the applicant to pay the respondent $516,586.95. In my view he acted within his jurisdiction in doing so.
Background
The applicant, HM Hire Pty Ltd, is a company which provides earthmoving and other equipment for…
Keep reading for free
Create a free CaseChat account to read HM Hire Pty Ltd v National Plant and Equipment Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] QSC 4
- Decision Date
CaseChat Overview and Summary
The court considered the definition of "construction work" under the Act and whether the activities performed by HM Hire met this definition. The court examined the exclusions provided under section 10(3)(b) of the Act, which exclude from the definition of "construction work" activities such as clearing and grubbing, topsoil stripping, and placement. The court found that the work performed by HM Hire did not align with the specific requirements of the contract, and thus did not qualify as "construction work" as defined by the Act. Additionally, the court held that the activities fell within the exclusion under section 10(3)(b), which meant they were not eligible for progress payments under the statutory scheme.
Given these findings, the court dismissed the application for review, upholding the adjudicator's decision that HM Hire should make the progress payment to National Plant and Equipment. The court's reasoning was grounded in the statutory interpretation of "construction work" and the exclusions provided in the Act. Consequently, HM Hire was not entitled to the relief sought in the application.
Orders
Orders of the court
Application dismissed
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi