SUPREME COURT OF QUEENSLAND
CITATION:
Heritage Properties Pty Ltd & Anor v. Bettson Properties Pty Ltd & Ors [2007] QSC 222
PARTIES:
HERITAGE PROPERTIES PTY LTD ACN 010 754 953
(first applicant)
AND
SOUTH PINE ESTATES PTY LTD ACN 009 861 438
(second applicant)
AND
BETTSON PROPERTIES PTY LTD ACN 009 873 152
(first respondent)
AND
TOBSTA PTY LTD ACN 078 818 014
(second respondent)
AND
PINE RIVERS SHIRE COUNCIL
(third respondent)
FILE NO/S:
BS 2486 of 2003
DIVISION:
Trial
PROCEEDING:
Interlocutory Application
ORIGINATING COURT:
Supreme Court
DELIVERED ON:
24 August 2007
DELIVERED AT:
Brisbane
HEARING DATE:
13 June 2007
JUDGE:
Chesterman J
ORDER:
That the costs of and incidental to the application for summary judgement be reserved to the trial judge
CATCHWORDS:
INTERLOCUTORY APLLICATION - APPLICATION FOR COSTS- where a cross application in the proceeding was brought by the respondents for the proceeding to be dismissed or alternatively for the statement of claim to be struck out – where that application was dismissed by consent – where immediately prior to that application the applicants were granted leave to serve an amended originating application – where it was contested as to the effect of that order on the subsequent dismissal of the application for summary judgement – where the applicants and respondents argued for the costs of the summary judgement application. – whether it was appropriate in an interlocutory application to make orders which were themselves dependent upon making a finding as to a contested construction critical to the outcome of the litigation.
COUNSEL:
Mr S Couper QC with him Mr J Otto for the applicants
Mr W Sofronoff QC with him Mr Franco for the first and second respondents
Mr E Morzone for the third respondentSOLICITORS:
Hopgood Ganim Lawyers for the applicants
Russel & Company for the first and second respondents
On 13 June 2007 I gave the applicant leave to deliver an amended originating application and ordered that South Pine Estates Pty Ltd be joined as the second applicant. The applicants were to pay the costs which the respondents had incurred and which would be wasted by reason of the amendments. A cross application brought by the respondents for orders that the proceeding be dismissed or, alternatively, that the amended statement of claim be struck out, was dismissed by consent. Counsel for the respondents accepted that the amended application and statement of claim, for which I had given leave, raised an arguable entitlement to relief.
Both applicants and respondents asked for the costs of the application for summary judgment. The respondents’ contention was that its application was defeated only by the last minute amendments, and that the application would otherwise have succeeded.
The applicants’ position was that the application for summary judgment was “doomed to fail” without the further amendments, and that the various emanations of the application and statement of claim all raised a trialable case against which an application for summary judgment would have foundered.
The dispute concerns “water rights” as defined by a deed…
Keep reading for free
Create a free CaseChat account to read Heritage Properties Pty Ltd & Anor v. Bettson Properties Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] QSC 222
- Decision Date
CaseChat Overview and Summary
The legal issue before the court was whether it was appropriate to make orders regarding costs in an interlocutory application when those orders depended on determining a contested construction that was crucial to the outcome of the litigation. The court needed to balance the principle of finality in interlocutory decisions with the need for a fair resolution of costs. The applicants argued that the dismissal of their summary judgment application should not automatically result in a costs order, while the respondents contended that the dismissal warranted an order for costs.
In resolving the matter, the court determined that it was not appropriate to make orders that were contingent on a contested construction in an interlocutory application. The court reasoned that such orders could be influenced by a finding that might not be the ultimate conclusion of the litigation. The court therefore held that the costs of and incidental to the application for summary judgment should be reserved for determination by the trial judge, ensuring that the final resolution of costs would be made after the full merits of the case had been adjudicated.
The court's decision underscores the importance of avoiding premature or contingent orders in interlocutory applications that could prejudice the outcome of the litigation. By reserving the costs for the trial judge, the court ensured that the final determination would be made in light of the full context of the case, thereby upholding the principle of finality in interlocutory proceedings.
Orders
Orders of the court
That the costs of and incidental to the application for summary judgement be reserved to the trial judge
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi