HELSBY -v- CONDOR DEVELOPMENTS PTY LTD [2008] WASC 264
| Link to Appeal : |
| SUPREME COURT OF WESTERN AUSTRALIA | Citation No: | [2008] WASC 264 | |
| Case No: | CIV:1666/2008 | 28 OCTOBER 2008 | |
| Coram: | TEMPLEMAN J | 19/11/08 | |
| 20 | Judgment Part: | 1 of 1 | |
| Result: | Defendant's termination without legal effect | ||
| A | |||
| PDF Version |
| Parties: | ALAN BERNARD HELSBY VANESSA ERIN PROSSER CONDOR DEVELOPMENTS PTY LTD (ACN 105 199 880) |
Catchwords: | Contract Sale of strata units off the plan Vendor developer of project Settlement when project completed Various conditions essential to project Agreed time by which all conditions are due Conditions occur according to timetable of events Automatic termination if some conditions not satisfied on time Termination clause for developer if in developer's opinion the project is not viable Developer to consider viability before last condition due to be satisfied Continuation of project and contract of sale after time for automatic termination Other conditions not capable of being satisfied due to effluxion of time Developer purports to terminate on viability grounds Consistent interpretation of terms throughout the contract Whether waiver of exercise of termination clause |
Legislation: | Strata Titles Act 1985 (WA), s 70 |
Case References: | Badat v DTZ Australia (WA) Pty Ltd [2008] WASCA 83 Bellmere Park Pty Ltd v Benson [2007] QCA 102 Commonwealth of Australia v Verwayen (1990) 170 CLR 394 Phillips v Ellinson Brothers Pty Ltd (1941) 65 CLR 221 |
JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
- IN CIVIL
- VANESSA ERIN PROSSER
Plaintiffs
AND
CONDOR DEVELOPMENTS PTY LTD (ACN 105 199 880)
Defendant
Catchwords:
Contract - Sale of strata units off the plan - Vendor developer of project - Settlement when project completed - Various conditions essential to project - Agreed time by which all conditions are due - Conditions occur according to timetable of events - Automatic termination if some conditions not satisfied on time - Termination clause for developer if in developer's opinion the project is not viable - Developer to consider viability before last condition due to be satisfied - Continuation of project and contract of sale after time for automatic termination - Other conditions not capable of being satisfied due to effluxion of time - Developer purports to terminate on viability grounds - Consistent interpretation of terms throughout the contract - Whether waiver of exercise of termination clause
(Page 2)
Legislation:
Strata Titles Act 1985 (WA), s 70
Result:
Defendant's termination without legal effect
Category: A
Representation:
Counsel:
Plaintiffs : Mr P G McGowan
Defendant : Mr S OwenConway QC & Mr D K Barker
Solicitors:
Plaintiffs : Butcher Paull & Calder
Defendant : Chalmers Legal Studio Pty Ltd
Case(s) referred to in judgment(s):
Badat v DTZ Australia (WA) Pty Ltd [2008] WASCA 83
Bellmere Park Pty Ltd v Benson [2007] QCA 102
Continue reading Helsby v Condor Developments Pty Ltd
Sign in free to access the full text
- AGLC
- Helsby v Condor Developments Pty Ltd [2008] WASC 264
- Case
- [2008] WASC 264
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the developer's termination of the contract was valid and, if not, whether Mr. Helsby was entitled to specific performance. The central legal issue was the interpretation and application of the termination clauses in the contract, particularly in light of the developer's decision to terminate on the grounds of project viability. The court considered whether the developer's actions were consistent with the contract's terms and whether the developer had waived its right to terminate under the automatic termination clause.
The court concluded that the developer's termination was without legal effect. It found that the developer had not acted in accordance with the contract's terms and had waived the right to terminate under the automatic termination clause. The court held that the developer's decision to terminate on viability grounds was inconsistent with the contract's conditions, as other conditions remained unsatisfied due to the passage of time rather than any fault of the purchaser. The court also found that the developer's actions were inconsistent with the contract's terms and that the developer had waived its right to terminate under the automatic termination clause.
The court ordered that the developer's termination of the contract was without legal effect. It further ordered that Mr. Helsby was entitled to specific performance, meaning that the developer was required to complete the project and transfer the strata unit to Mr. Helsby as per the original terms of the contract.
Orders
Orders of the court
Defendant's termination without legal effect
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.