Helicopter Aerial Surveys Pty Ltd v Bradford Marine Pty Ltd

Link copied
Case Copied 52 min read

Federal Circuit Court of Australia

Helicopter Aerial Surveys Pty Ltd v Bradford Marine Pty Ltd [2020] FCCA 3238  

File number(s): BRG 71 of 2019
Judgment of: JUDGE VASTA
Date of judgment: 30 November 2020
Catchwords:

Admiralty – jurisdiction law and practice

CONSUMER LAW – consumer protection

Contract – damages – where owner of a vessel sought maintenance/repairs to the vessel – contract partly in writing, partly oral and partly by conduct – where repairs were not completed properly – where the owner paid for remediation works by another contractor – whether respondent had breached contract – whether there was contributory negligence – whether a third party was a concurrent wrongdoer – whether time of repairs was too remote from time of remediation works – causation

Tort – duty of care – negligence – damages for negligence and/or breach of contract – calculation of interest – lump sum awarded pursuant to s.76(3)(d) of the FCCA Act 1999 (Cth)

Legislation:

Civil Liability Act 2003 (QLD) s 30

Federal Circuit Court of Australia Act 1999 (Cth) s 76

Cases cited: Yates v Mobile Marine Repairs Pty Ltd and Anor [2007] NSWSC 1463
Number of paragraphs: 184
Date of last submission/s: 18 November 2020
Date of hearing: 16-18 November 2020
Place: Brisbane
Solicitor for the Applicants: Mr Marinac
Counsel for the Respondent: Mr Tan

ORDERS

BRG 71 of 2019
BETWEEN:

HELICOPTER AERIAL SURVEYS PTY LTD

First Applicant

BARRY EDWARD JONES

Second Applicant

AND:

BRADFORD MARINE PTY LTD

Respondent

order made by:

JUDGE VASTA

DATE OF ORDER:

30 November 2020

THE COURT ORDERS THAT:

1.The Respondent pay to the First Applicant the sum of $260,000.00, with costs to be taxed in accordance with the Federal Circuit Court Rules 2001 (Cth), unless otherwise agreed.

REASONS FOR JUDGMENT

JUDGE VASTA

  1. The Mishima is a 24 m ship. It was built in Japan in 1987 and is constructed from steel.  Because of this, it requires regular painting and maintenance.  Different areas of the vessel need different types of paint.  The vessel has been used primarily as a pleasure craft for a number of years by the Applicants, Helicopter Aerial Surveys Pty Ltd (“HAS”) and Barry Edward Jones (“the Applicant”), the sole director and shareholder of HAS.

  2. In 2009, the Applicants caused the vessel to have maintenance works.  The maintenance works mainly comprise the painting of the hull below the waterline (“HBWL”) and painting of the topside (every area above the waterline that is not the hull).

  3. The Applicant testified that he considered the vessel to be on a four year dry docking cycle; that is, that maintenance would occur on the vessel, especially the HBWL, every 48 months.  Having done maintenance works in 2009, those works were due to be done again in 2013.  For a variety of reasons, the Applicant did not get around to making arrangements for the maintenance works until 2015.

  4. The maintenance works were performed by the Respondent.  The Respondent charged the Applicants over $200,000 for those maintenance works which were concluded in January…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Helicopter Aerial Surveys Pty Ltd v Bradford Marine Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] FCCA 3238
Decision Date

CaseChat Overview and Summary

In *Helicopter Aerial Surveys Pty Ltd v Bradford Marine Pty Ltd*, Vasta J of the Federal Circuit Court of Australia considered a dispute between the owner of a vessel and a marine repair company. The owner sought damages for alleged breaches of contract and negligence arising from repairs carried out on its vessel by the company. The core of the dispute concerned the adequacy of the repairs performed by the respondent, which the applicant claimed necessitated costly remediation works by a third party.

The court was required to determine whether the respondent had breached its contract with the applicant by failing to properly repair the vessel. Additionally, the court had to assess whether the respondent's actions constituted negligence, and if so, whether there was a causal link between the respondent's conduct and the subsequent need for remedial works. The court also considered issues of contributory negligence and the remoteness of the time between the original repairs and the remediation works, although the primary focus remained on breach of contract and negligence.

Vasta J found that the respondent had breached its contract with the applicant and was wholly responsible for the damage to the vessel that necessitated remedial works. The court was satisfied that there was a direct causal link between the respondent's actions in 2015 and the remedial works undertaken in 2019. The judge accepted the applicant's claim for reimbursement of the costs incurred for the remediation works, finding the claim to be modest and the applicant's evidence to be honest. The court also awarded a lump sum in lieu of interest pursuant to s.76(3)(d) of the *Federal Circuit Court of Australia Act 1999* (Cth).

The respondent was ordered to pay the first applicant the sum of $260,000.00, with costs to be taxed in accordance with the Federal Circuit Court Rules 2001 (Cth), unless otherwise agreed.

Orders

Orders of the court

The Respondent pay to the First Applicant the sum of $260,000.00, with costs to be taxed in accordance with the Federal Circuit Court Rules 2001 (Cth), unless otherwise agreed.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

I find that there is a direct causal link between the actions of the Respondent in 2015 and the remedial works conducted in November 2019.Conclusion as to liability I am satisfied that the Respondent is wholly responsible for the state of the vessel that caused the need for remedial works in 2016 and 2019. This means that I accept that the Applicant and the Respondent had a contract for the Respondent to properly repair the vessel of the Applicant. The Respondent breached that contract by failing to properly repair the vessel. I also accept that the damage done to the vessel, that caused the need for GT Mac to conduct two lots of remediation works, was wholly due to the negligence of the Respondent.Quantum This matter comes before this Court pursuant to its Admiralty jurisdiction. The Applicant claimed damages for a breach of contract and/or alternatively, damages in tort, and/or alternatively damages for a breach of the Australian Consumer Protection Law. That last aspect was not pursued during the trial. Because of its accrued jurisdiction, this Court has the power to adjudicate breaches of contract and tortious injuries and I have made the appropriate findings. The claim that is made by the Applicants is a modest claim. It is for reimbursement of the money paid to GT Mac for the two lots of remediation work on the vessel plus interest. I would have been prepared to award damages for other hot works that needed to done on the vessel but the Applicant declined to make that claim. I would also have been prepared to award damages for loss of enjoyment of the vessel whilst it needed to undergo the repairs that would not have been needed if it weren’t for the breach of contract and/or negligence of the Respondent. The Respondent made submissions on many of the line items in the invoice of the second lot of remediation works conducted by GT Mac. The Respondent argued that some of those items could have been ascribed as being “maintenance works” rather than “remediation works”. The Respondent also argued, at one stage, that GT Mac had somehow “double charged” for some items, however that claim was ultimately abandoned. Having regard to the honesty of Mr McIntosh, and to the modest nature of the claim that the Applicant is making, I am not prepared to diminish the amount claimed in any way whatsoever. Section 76 of the Federal Circuit Court of Australia Act 1999 (Cth) (“the FCC Act”) allows a judge to give interest at such a rate as the judge, as the case may be, thinks fit on the whole or any part of the money for the whole or any part of the period between the date on the cause of action arose on the date as of which judgement is entered. In this case, I am satisfied that an interest rate of roughly 5% should be awarded. I will, however, make an order pursuant to s.76(3)(d) and order a lump sum in lieu of such interest. The Applicant paid $50,000 to GT Mac on 16 September 2016. The Applicant would have been awarded interest on that amount from that date until 30 November 2020.

Ratio Decidendi

Legal principle established