Supreme Court
New South Wales
Medium Neutral Citation: Hebbel Constructions Pty Limited v Bitar Pty Limited [2017] NSWSC 917 Hearing dates: 29 May 2017 – 2 June 2017 Date of orders: 04 July 2017 Decision date: 04 July 2017 Jurisdiction: Equity Before: Rein J Decision: See [58] – [59], [66], [71], [73], [79] and [99]
Catchwords: PARTNERSHIPS AND JOINT VENTURES – plaintiff and defendant in partnership to build residential and commercial units – creation of partnership vehicle company to conduct the project development – request for Court dissolution and winding up of partnership – whether construction contract entered into by the parties and whether in force or abandoned – whether plaintiff is the builder of the project, as named in the construction contract, and entitled to recoup monies for construction costs – whether variations were made to the construction contract sum – whether payments claimed were established to have been made by the plaintiff and whether, to the extent so established, loans obtained by the plaintiff for the purpose of meeting construction costs are recoverable from the partnership pursuant to s 24(2) or s 24(3) of the Partnership Act 1892 (NSW) – issue of delay in completion of the project – plaintiff’s lack of building license and impact of Home Building Act 1989 (NSW) raised – whether the joint expert appointed is no longer impartial because he was engaged in communication by the plaintiff’s solicitor without the involvement of the defendant and therefore cannot act as a referee in the proceedings – whether a receiver and manager should be appointed – whether, pursuant to s 35(f) of the Partnership Act 1892 (NSW), the partnership should be dissolved – what questions and matters should the referee and receiver and manager determine Legislation Cited: Home Building Act 1989 (NSW)
Partnership Act 1892 (NSW)Cases Cited: Gerard Cassegrain & Co Pty Ltd v Cassegrain; Cassegrain v Gerard Cassegrain & Co [2010] NSWSC 91
Stanton (WA) P/L v Vasquez Investments [2017] NSWSC 128
DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 CLR 423
Ryder v Frohlich [2004] NSWCA 472
Abignano Nominees Pty Ltd v Sheripeter Pty Ltd [2016] NSWSC 1378
Ebner v Official Trustee in Bankruptcy (2000) 205 CLR 337
Rowlands v MacDonald [2002] NSWSC 282
Tate v Barry (1928) 28 SR (NSW) 380Texts Cited: Ritchie's Uniform Civil Procedure NSW Category: Principal judgment Parties: Hebbel Constructions Pty Limited (Plaintiff and First Cross Defendant)
Bitar Pty Limited (First Defendant and First Cross Claimant)
Hebbel Constructions Pty Ltd & Bitar Pty Limited (Partnership) (Second Defendant)
Joseph Katter (Second Cross Claimant)
Mansour Taouk (Second Cross Defendant)Representation: Counsel:
Solicitors:
F. Assaf (Plaintiff and Cross Defendants)
P.E King & F. Sinclair (First Defendant and Cross Claimant)
Paramonte Legal (Plaintiff and Cross Defendants)
Priest McCarron (First Defendant and Cross Claimant)
File Number(s): 2014/269117 Publication restriction: Nil
Judgment
-
These proceedings relate to a development in Petersham NSW. The site chosen for the development was purchased in December 2001 for $3,120,000 by Hebbel Constructions Pty Ltd (“
Keep reading for free
Create a free CaseChat account to read Hebbel Constructions Pty Limited v Bitar Pty Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWSC 917
- Decision Date
CaseChat Overview and Summary
The court considered the evidence and submissions from both parties regarding the existence and terms of the construction contract. It examined the relationship between the parties, the nature of their dealings, and whether a partnership was formed for the specific purpose of the project. The court also assessed the legitimacy of the claimed payments and the extent to which Hebbel Constructions had met its obligations under the alleged partnership agreement. The court examined the variations made to the construction contract sum and the impact of these changes on the parties' rights and liabilities. Additionally, the court evaluated the role of the joint expert and the impartiality of the expert's report. The court also considered the implications of the delay in project completion, Hebbel Constructions' lack of a building license, and the effect of the Home Building Act 1989 (NSW) on the partnership's obligations.
The court concluded that a partnership existed between Hebbel Constructions and Bitar Pty Limited for the purpose of constructing the residential and commercial units. The court found that the construction contract was in force and that Hebbel Constructions was the builder named in the contract, entitling them to recoup construction costs. The court determined that some of the claimed payments by Hebbel Constructions were legitimate and recoverable from the partnership under the Partnership Act 1892 (NSW). The court also found that the joint expert's report was not compromised by the plaintiff's solicitor's communication with the expert and that the expert could continue to act as a referee. The court decided that a receiver and manager should be appointed to manage the partnership's assets and affairs during the dissolution process. The court ordered that the partnership be dissolved pursuant to section 35(f) of the Partnership Act 1892 (NSW) and specified the questions and matters to be determined by the referee and receiver and manager, including the calculation of each party's share of the partnership's assets and liabilities, the distribution of any surplus assets, and the resolution of any outstanding disputes between the parties.
The court made several orders in relation to the dissolution and winding up of the partnership. The court appointed a receiver and manager to take control of the partnership's assets and to manage the affairs of the partnership during the dissolution process. The court directed the referee to determine the respective shares of the partnership's assets and liabilities, including the calculation of any amounts owed to Hebbel Constructions for construction costs and the distribution of any surplus assets. The court also ordered the referee to determine the validity and enforceability of the construction contract and the legitimacy of the claimed payments by Hebbel Constructions. The court further directed the referee to consider the impact of the delay in project completion and Hebbel Constructions' lack of a building license on the partnership's obligations. Finally, the court ordered the referee and receiver and manager to report back to the court with their findings and recommendations within a specified timeframe.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established