SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY
Case Title: | Heaven Builders Pty Ltd v Moustafa |
Citation: | [2025] ACTSC 466 |
Hearing Date: | 8 May 2025 |
Decision Date: | 16 October 2025 |
Before: | Ainslie-Wallace AJ |
Decision: | See [146] |
Catchwords: | APPEAL – CIVIL LAW – Appeal from ACT Magistrates Court – dispute over payment for painting stage and variations to contract – breach of contract – whether Magistrate erred in finding purported termination of contract by Respondents was valid – whether Respondents had cured earlier breach of contract at time of termination – where Respondents had excluded Appellant from accessing building site – whether subsequent invitation to re-commence work provided uninterrupted possession to builders – appeal allowed |
Legislation Cited: | Court Procedures Rules 2006 (ACT), rr 1619, 1620, Sch 2 item 2.2 |
Cases Cited: | Fox v Percy [2003] HCA 22; 214 CLR 118 |
Parties: | Heaven Builders Pty Ltd (Appellant) Nour Moustafa Abdelhameed Moustafa (First Respondent) Marwa Mohamed Elsaied Hassan Keshk (Second Respondent) |
Representation: | Counsel WDB Buckland ( Appellant) Self-represented ( First and Second Respondents) |
| Solicitors BAL Lawyers ( Appellant) Self-represented ( First and Second Respondents) | |
File Number: | SCA 34 of 2024 |
Decision Under Appeal: | Court/Tribunal: Magistrates Court of the ACT Before: Magistrate Theakston Date of Decision: 26 July 2024 Case Title: Heaven Builders Pty Ltd v Moustafa & Anor (No 2) Citation: [2024] ACTMC 13 Court File Number: CS 182 of 2022 |
AINSLIE-WALLACE AJ:
Introduction
1․On 16 April 2021 Nour Moustafa Abdelhameed Moustafa (the First Respondent) and Marwa Mohamed Elsaied Hassan Keshk (the Second Respondent) entered into a contract with Heaven Builders Pty Ltd (the Appellant) to construct a two storey house on land owned by the Respondents at 1 Trewenack Street, Taylor in the Australian Capital Territory (ACT). An earlier contract with the Appellant was for the construction of a one storey house.
2․In about June 2022 a dispute arose between the Appellant and the Respondents, as a consequence of which the Appellant considered that the Respondents had, by their actions, brought about practical completion of the project and sought the balance of funds owing to them under the contract. The Respondents counter-claimed against the Appellant for the cost of completing the building works.
3․The matter was heard in the ACT Magistrates Court and on 26 July 2024, a Magistrate entered judgment for the Respondents in the sum of $82,038 together with interest and costs.
4․The Appellant appeals that decision.
Background
The Terms of the Building Contract
5․The terms of the contract entered into between the Appellant and the Respondents are, for these purposes, uncontroversial. The controversy here is what effect those terms had in light of the parties’ actions.
6․The contract provided for progress payments to be made to the Appellant at various stages: base, frame, lock-up, fixing, painting and practical completion. It was uncontroversial that the Appellant had delivered invoices to the Respondents for the earlier appointed stages and those invoices…
Keep reading for free
Create a free CaseChat account to read Heaven Builders Pty Ltd v Moustafa and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] ACTSC 466
- Decision Date
CaseChat Overview and Summary
The appeal court found that the Magistrates Court had erred in finding that the purported termination was valid. The court noted that the respondents had breached the contract earlier by excluding the appellant from accessing the building site. The court held that the invitation to re-commence work did not provide uninterrupted possession to the builders as required by the contract. The appeal court concluded that the respondents' actions constituted a breach of contract, and the purported termination was invalid. The appeal was allowed, and the original decision of the Magistrates Court was set aside.
The appeal court's decision provides clarity on the legal issues surrounding the validity of contract termination, the effect of prior breaches, and the requirement for uninterrupted possession in building contracts. The court's findings on these issues will be of significant interest to parties involved in similar disputes. The orders of the appeal court set aside the original decision of the Magistrates Court, and the matter will now proceed as determined by the appeal court.
Orders
Orders of the court
See [146]
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.