Heaven Builders Pty Ltd v Moustafa

Link copied
Case Copied 48 min read

SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY

Case Title:

Heaven Builders Pty Ltd v Moustafa

Citation: 

[2025] ACTSC 466

Hearing Date: 

8 May 2025

Decision Date: 

16 October 2025

Before:

Ainslie-Wallace AJ

Decision: 

See [146]

Catchwords: 

APPEAL – CIVIL LAW – Appeal from ACT Magistrates Court – dispute over payment for painting stage and variations to contract – breach of contract – whether Magistrate erred in finding purported termination of contract by Respondents was valid – whether Respondents had cured earlier breach of contract at time of termination – where Respondents had excluded Appellant from accessing building site – whether subsequent invitation to re-commence work provided uninterrupted possession to builders – appeal allowed

Legislation Cited: 

Court Procedures Rules 2006 (ACT), rr 1619, 1620, Sch 2 item 2.2
Magistrates Court Act 1930
(ACT), s 274

Cases Cited: 

Fox v Percy [2003] HCA 22; 214 CLR 118
Theodorelos v Nexus Projects Pty Ltd [2009] ACTSC 149; 19 ACTLR 1

Parties: 

Heaven Builders Pty Ltd (Appellant)

Nour Moustafa Abdelhameed Moustafa (First Respondent)

Marwa Mohamed Elsaied Hassan Keshk (Second Respondent)

Representation: 

Counsel

WDB Buckland ( Appellant)

Self-represented ( First and Second Respondents)

Solicitors

BAL Lawyers ( Appellant)

Self-represented ( First and Second Respondents)

File Number:

SCA 34 of 2024

Decision Under Appeal: 

Court/Tribunal:             Magistrates Court of the ACT

Before:   Magistrate Theakston

Date of Decision:        26 July 2024

Case Title:  Heaven Builders Pty Ltd v Moustafa   & Anor (No 2)

Citation:  [2024] ACTMC 13

Court File Number:     CS 182 of 2022

AINSLIE-WALLACE AJ:       

Introduction

1․On 16 April 2021 Nour Moustafa Abdelhameed Moustafa (the First Respondent) and Marwa Mohamed Elsaied Hassan Keshk (the Second Respondent) entered into a contract with Heaven Builders Pty Ltd (the Appellant) to construct a two storey house on land owned by the Respondents at 1 Trewenack Street, Taylor in the Australian Capital Territory (ACT).  An earlier contract with the Appellant was for the construction of a one storey house.

2․In about June 2022 a dispute arose between the Appellant and the Respondents, as a consequence of which the Appellant considered that the Respondents had, by their actions, brought about practical completion of the project and sought the balance of funds owing to them under the contract.  The Respondents counter-claimed against the Appellant for the cost of completing the building works.

3․The matter was heard in the ACT Magistrates Court and on 26 July 2024, a Magistrate entered judgment for the Respondents in the sum of $82,038 together with interest and costs.

4․The Appellant appeals that decision.

Background

The Terms of the Building Contract

5․The terms of the contract entered into between the Appellant and the Respondents are, for these purposes, uncontroversial.  The controversy here is what effect those terms had in light of the parties’ actions.

6․The contract provided for progress payments to be made to the Appellant at various stages: base, frame, lock-up, fixing, painting and practical completion. It was uncontroversial that the Appellant had delivered invoices to the Respondents for the earlier appointed stages and those invoices…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Heaven Builders Pty Ltd v Moustafa and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] ACTSC 466
Decision Date

CaseChat Overview and Summary

Heaven Builders Pty Ltd, the appellant, appealed a decision of the ACT Magistrates Court against Moustafa, the respondent, concerning a dispute over payment for painting and variations to a contract. The primary issue was whether the Magistrates Court was correct in ruling that the purported termination of the contract by the respondents was valid. Additionally, the court had to determine whether the respondents had rectified their earlier breach of contract at the time of termination. Another issue was whether the exclusion of the appellant from accessing the building site constituted a breach, and whether the invitation to re-commence work provided uninterrupted possession to the builders.

The appeal court found that the Magistrates Court had erred in finding that the purported termination was valid. The court noted that the respondents had breached the contract earlier by excluding the appellant from accessing the building site. The court held that the invitation to re-commence work did not provide uninterrupted possession to the builders as required by the contract. The appeal court concluded that the respondents' actions constituted a breach of contract, and the purported termination was invalid. The appeal was allowed, and the original decision of the Magistrates Court was set aside.

The appeal court's decision provides clarity on the legal issues surrounding the validity of contract termination, the effect of prior breaches, and the requirement for uninterrupted possession in building contracts. The court's findings on these issues will be of significant interest to parties involved in similar disputes. The orders of the appeal court set aside the original decision of the Magistrates Court, and the matter will now proceed as determined by the appeal court.

Orders

Orders of the court

See [146]

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.