New South Wales
Court of Appeal
CITATION: Hanson Construction Materials Pty Ltd v Siely Pty Ltd [2009] NSWCA 48 HEARING DATE(S): 2 March 2009
JUDGMENT DATE:
16 March 2009JUDGMENT OF: Ipp JA at 1; Macfarlan JA at 67; Sackville AJA at 68 DECISION: (a) The appeal succeeds and the cross appeal succeeds.
(b) The verdict and judgment for the respondent in the sum of $216,156 is set aside.
(c) The respondent to have a verdict and judgment in the sum of $66,000.
(d) The respondent to have interest on the sum of $66,000 at the rate of 10 percent per annum from 7 August 2006 to date of payment.
(e) The respondent to pay the appellant's costs of the appeal and the appellant to pay the respondent's costs of the cross appeal.
(f) Both parties to have certificates under the Suitor's Fund Act 1951 if otherwise entitled.CATCHWORDS: CONTRACTS - general contractual principles - discharge, breach and defences to action for breach - independent contract - whether termination of contract lawful - whether serious misconduct - relevance of terminating party's subjective belief - whether quantum of damages excessive LEGISLATION CITED: Suitor's Fund Act 1951 CATEGORY: Principal judgment CASES CITED: Shepherd v Felt & Textiles of Australia Limited (1931) 45 CLR 359 PARTIES: Hanson Construction Materials Pty Ltd (Appellant)
K H Siely Pty Ltd (Respondent)FILE NUMBER(S): CA 40217/08 COUNSEL: A P Stenmark SC with Y Shariff (Appellant)
JJE Fernon SC with TJ Boyd (Respondent)SOLICITORS: Mark Diamond & Associates (Appellant)
Herbert Weller (Respondent)LOWER COURT JURISDICTION: District Court LOWER COURT FILE NUMBER(S): 2583/07 LOWER COURT JUDICIAL OFFICER: Rolfe DCJ LOWER COURT DATE OF DECISION: 8 July 2008
CA 40217/08
16 March 2009IPP JA
MACFARLAN JA
SACKVILLE AJA
1 IPP JA: On 28 April 2005 the appellant entered into a contract (the “Contract”) with the respondent whereby the respondent, as an independent contractor, agreed to undertake concrete cartage for the appellant. The term of the Contract was from 1 May 2005 until 31 October 2014.
2 On 7 August 2006 the appellant terminated the Contract. The respondent contended that the termination was unlawful and claimed damages calculated on the basis that the Contract had come to an end on that date. The parties conducted the ensuing litigation on the basis that the Contract had indeed so come to an end.
3 The respondent commenced proceedings in the District Court for damages it had suffered by reason of the appellant’s alleged unlawful termination. Rolfe DCJ upheld the respondent’s claim and awarded it $201,076, exclusive of interest.
4 Clauses 3.2(a) and (b) of the Contract governed its termination. These clauses provided as follows:
- “ Termination of Contracts of Carriage
- (a) From 1 November 2004 if the Contractor decides to terminate a contract of carriage for any reason other than serious misconduct the Contractor shall pay to the Carrier an immediate termination payment of $66,000.00 and the…
Keep reading for free
Create a free CaseChat account to read Hanson Construction Materials Pty Ltd v Siely Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] NSWCA 48
- Decision Date
CaseChat Overview and Summary
The Court of Appeal was required to determine whether Siely had engaged in serious misconduct, thereby entitling Hanson to terminate the contract. It also had to consider the relevance of Hanson's subjective belief regarding Siely's conduct in assessing the lawfulness of the termination, and whether the damages awarded by the trial judge were excessive.
The Court of Appeal found that Siely's conduct did not amount to serious misconduct as contemplated by the contract. It held that the contractual right to terminate for serious misconduct required an objective assessment of the conduct itself, rather than being solely dependent on the terminating party's subjective belief. Consequently, Hanson's termination was deemed unlawful. However, the Court also found that the quantum of damages awarded by the trial judge was excessive, and that Siely was only entitled to a lesser amount.
The appeal and cross-appeal were allowed. The original judgment in favour of Siely for $216,156 was set aside. Instead, Siely was awarded judgment for $66,000, with interest. The costs of the appeal were ordered to be paid by Siely to Hanson, while the costs of the cross-appeal were ordered to be paid by Hanson to Siely.
Orders
Orders of the court
(a) The appeal succeeds and the cross appeal succeeds. (b) The verdict and judgment for the respondent in the sum of $216,156 is set aside. (c) The respondent to have a verdict and judgment in the sum of $66,000. (d) The respondent to have interest on the sum of $66,000 at the rate of 10 percent per annum from 7 August 2006 to date of payment. (e) The respondent to pay the appellant's costs of the appeal and the appellant to pay the respondent's costs of the cross appeal. (f) Both parties to have certificates under the Suitor's Fund Act 1951 if otherwise entitled.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi