Hampton Home Builders Pty Ltd v Queensland Building and Construction Commission

Link copied
Case Copied 27 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Hampton Home Builders Pty Ltd v Queensland Building and Construction Commission [2023] QCAT 21

PARTIES:

HAMPTON HOME BUILDERS PTY LTD

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

APPLICATION NO/S:

GAR101-21

MATTER TYPE:

General administrative review matters

DELIVERED ON:

19 January 2023

HEARING DATE:

22 August 2022

HEARD AT:

Brisbane

DECISION OF:

A/Member Katter

ORDERS:

The decision of the Respondent dated 19 January 2021 is confirmed.

CATCHWORDS:

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – General Administrative Review – application by builder to review a decision by the Queensland Building and Construction Commission regarding termination of a building contract - whether the building owner validly terminated a building contract – whether termination notice must specify the breach relied upon for termination

Queensland Building and Construction Commission Act 1991 (Qld) s 86(1)(i), s 86C(3)s 86E(b), s 87

Queensland Building and Construction Commission Regulation 2018 (Qld) Sch 6

Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 20, s 24

Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600

Downer EDI Ltd v Gillies (2012) 229 IR 214
Ericksson v Whalley [1971] 1 NSWLR 397
MacDonald v Australian Wool Innovation Ltd [2005] FCA 105
Matthews v Brodie (unreported, Sup Ct (Vic), 2 April 1980)
Re Stewardson Stubbs & Collett Pty Ltd and Bankstown Municipal Council Arbitration Between [1965]
NSWLR 1671
Parsons v Lloyd (1772) 3 Wils 341
Shepherd v Felt and Textiles of Australia (1931) 45 CLR 359
Wilson v Kirk Contractors Pty Ltd (1990) 7 BCL 284

APPEARANCES & REPRESENTATION:

Applicant:

C. H. Matthews of Counsel instructed by All Building Law

Respondent:

S. E. Seefeld of Counsel for the Queensland Building and Construction Commission

REASONS FOR DECISION

  1. By application filed 12 February 2021, Hampton Home Builders Pty Ltd (“the Applicant”) seeks review of the internal decision of the Queensland Building and Construction Commission (“the Respondent”) dated 19 January 2021 that the domestic building contract between the Applicant and the owners, Andrew and Beata Szczesniak (“the Owners”) for building work at 18 Dubbos Road, Fishermans Pocket (“the Property”) was validly terminated. The Applicant seeks an order from the Tribunal that the decision be set aside and substituted with a decision that the contract was not validly terminated by the Owners.

    Background

  2. On 10 January 2020, a representative of the Applicant met with the Owners at the Property and sent contractual documentation to the Owners along with an invoice for a deposit. That contractual documentation sent on 10 January 2020 was signed by the Applicant but not by the owner. The Owners paid the deposit amount of $59,974.00 on 15 January 2020.[1]

    [1] Statement of Andrew Zbigniew Szczesniak dated 31 May 2022 at paragraphs 5 to 14.

  3. On 17 March 2020, the parties did execute a contract in the form of a HIA Queensland New Homes Construction Contract for the construction of a new low-rise premises at the Property for the agreed price of $330,240.00.[2] It is agreed…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Hampton Home Builders Pty Ltd v Queensland Building and Cons... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QCAT 21
Decision Date

CaseChat Overview and Summary

Hampton Home Builders Pty Ltd sought a review of a decision made by the Queensland Building and Construction Commission that a domestic building contract between the Applicant and the owners for building work at 18 Dubbos Road, Fishermans Pocket was validly terminated. The Applicant argued that the contract was not validly terminated and sought an order from the Tribunal that the decision be set aside and substituted with a decision that the contract was not validly terminated by the Owners. The Tribunal heard the application on 22 August 2022 and considered the evidence and submissions from both parties. The relevant statutory provisions were the Queensland Building and Construction Commission Act 1991 (Qld) and the Queensland Civil and Administrative Tribunal Act 2009 (Qld). The Tribunal was empowered to consider the application for review and produce the correct and preferable decision by way of fresh hearing on the merits. The Tribunal had the power to confirm, amend, set aside, or return the matter for reconsideration to the decision-maker.

The legal issues before the court were whether the contract was validly terminated by the owners and whether the termination was justified. The Applicant argued that the owners did not have the right to terminate the contract as they had not signed the contract and had not provided the required notice of termination. The Respondent argued that the owners had the right to terminate the contract due to the Applicant's failure to complete the work and pay the required deposit. The court had to consider the evidence and determine whether the Respondent's decision was correct and preferable. The court had to consider the statutory provisions and the contractual terms and conditions.

The Tribunal found that the Respondent's decision was correct and preferable. The Tribunal found that the owners had the right to terminate the contract as they had provided the required notice of termination and the Applicant had failed to complete the work and pay the required deposit. The Tribunal found that the Applicant's suspension of works was unjustified and that the Applicant had breached the contract. The Tribunal found that the owners had a valid reason to terminate the contract and that the termination was justified. The Tribunal confirmed the Respondent's decision and set aside the Applicant's application for review.

In conclusion, the Tribunal found that the Respondent's decision was correct and preferable and confirmed the decision. The Applicant's application for review was set aside and the Respondent's decision was upheld. The Tribunal found that the owners had the right to terminate the contract and that the termination was justified. The Applicant's argument that the owners did not have the right to terminate the contract was rejected. The Tribunal's decision is final and binding on both parties.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

By application filed 12 February 2021, Hampton Home Builders Pty Ltd (“the Applicant”) seeks review of the internal decision of the Queensland Building and Construction Commission (“the Respondent”) dated 19 January 2021 that the domestic building contract between the Applicant and the owners, Andrew and Beata Szczesniak (“the Owners”) for building work at 18 Dubbos Road, Fishermans Pocket (“the Property”) was validly terminated. The Applicant seeks an order from the Tribunal that the decision be set aside and substituted with a decision that the contract was not validly terminated by the Owners. Background On 10 January 2020, a representative of the Applicant met with the Owners at the Property and sent contractual documentation to the Owners along with an invoice for a deposit. That contractual documentation sent on 10 January 2020 was signed by the Applicant but not by the owner. The Owners paid the deposit amount of $59,974.00 on 15 January 2020.[1] [1] Statement of Andrew Zbigniew Szczesniak dated 31 May 2022 at paragraphs 5 to 14. On 17 March 2020, the parties did execute a contract in the form of a HIA Queensland New Homes Construction Contract for the construction of a new low-rise premises at the Property for the agreed price of $330,240.00.[2] It is agreed by the parties that the 17 March 2020 contract (“the Contract”) is the relevant contract for consideration by the Tribunal in these proceedings. [2] Statement of Karen Michelle Robinson dated 28 March 2022 at paragraph 14. During January 2020 work commenced at the Property and the Base Stage was completed on or about 1 July 2020.[3] [3] Ibid at paragraphs 17 and 18. On Thursday, 27 August 2020, the Applicant issued the Owners a progress claim for the Frame Stage in the amount of $82,500.00.[4] [4] Ibid at paragraphs 21 to 23. On Monday, 31 August 2020, the Applicant issued a notice to the Owners suspending work from 28 August 2020 pursuant to clause 19.1 of the Contract for failure to pay the progress claim for the Frame Stage.[5] [5] Ibid at paragraph 50 and Attachment J.1. Later in the day on Monday, 31 August 2020, a notice to remedy breach was issued to the Applicant citing the Applicant’s suspension of works, the incomplete work regarding the frame stage and the position of the building. On 15 October 2020, a termination notice was issued to the Applicant.The Evidence The Tribunal heard the application on 22 August 2022. The Applicant called the following witnesses and tendered the following statements:(a)John Paul David. Statement dated 28 March 2022 (including the Statutory Declaration made on 18 December 2020). Mr David is a director of the Applicant. A colour photograph marked as “3 June 2020” identifying pegs marking was tendered. (b)John Berney Middlemiss. Statement dated 23 March 2022. Mr Middlemiss is a licensed building certifier who provided certification in relation to the works.(c)Adrian Victor Da Ros. Statement dated 31 March 2022. Mr Da Ros was previously employed by the Applicant as Site Supervisor. (d)Karen Michelle Robinson. Statement dated 28 March 2022. Ms Robinson has been a director of the Applicant and was a Sales Manager for the Applicant at material times.

Evidence

Evidence Before The Court

On 15 October 2020, a termination notice was issued to the Applicant.The Evidence The Tribunal heard the application on 22 August 2022. The Applicant called the following witnesses and tendered the following statements:(a)John Paul David. Statement dated 28 March 2022 (including the Statutory Declaration made on 18 December 2020). Mr David is a director of the Applicant. A colour photograph marked as “3 June 2020” identifying pegs marking was tendered. (b)John Berney Middlemiss. Statement dated 23 March 2022. Mr Middlemiss is a licensed building certifier who provided certification in relation to the works.(c)Adrian Victor Da Ros. Statement dated 31 March 2022. Mr Da Ros was previously employed by the Applicant as Site Supervisor. (d)Karen Michelle Robinson. Statement dated 28 March 2022. Ms Robinson has been a director of the Applicant and was a Sales Manager for the Applicant at material times. The Commission called and tendered:(a)Andrew Zbigniew Szczesniak. Statement dated 31 May 2022. Mr Szczesniak is an owner of the Property. (b)The Commission’s Statement of Reasons for the Decision dated 22 July 2021.Relevant statutory provisions The Queensland Building and Construction Commission Act 1991 (Qld) (“the QBCC Act”) provides at section 86(1)(i) that a decision that a domestic building contract has been validly terminated (having the consequence of allowing a claim for non-completion under the statutory insurance scheme) is a reviewable decision for the purposes of an internal review. Section 86E(b) sets out that an internal review decision is a reviewable decision for the purposes of an external review by the Tribunal. The QBCC Act at section 87 provides that a person affected by a reviewable decision may apply to the Tribunal to review a decision. The decision of 19 January 2021 was, by operation of section 86C(3) of the QBCC Act, deemed to be an internal review decision in that the Commission did not undertake an internal review within 28 days from the date of receiving the application for internal review. The Tribunal is, therefore, empowered to consider the application for review. In reviewing the decision, the Tribunal is to produce the correct and preferrable decision by way of fresh hearing on the merits pursuant to section 20 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (“the QCAT Act”). Section 24 of the QCAT Act sets out that the Tribunal may:(a)Confirm or amend the decision; or(b)Set aside the decision and substitute its own decision; or(c)Set aside the decision and return the matter for reconsideration to the decision-maker for the decision, with the directions the tribunal considers appropriate. Relevant provisions are set out in Schedule 6 of the Queensland Building and Construction Commission Regulation 2018 (Qld) (“the QBCC Regulation”) regarding when a fixed price residential contract ends. Section 4(1)(a) of the Schedule sets out that a fixed price residential contract ends if “the contract is validly terminated on the default of the licenced contractor”.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.