LAND COURT OF QUEENSLAND
CITATION: Hail Creek Coal Holdings Pty Ltd & Ors v O’Loughlin & Ors [2023] QLC 22 PARTIES: Hail Creek Coal Holdings Pty Limited,
Marubeni Resources Development Pty Ltd, and
Sumisho Coal Development Queensland Pty Ltd(applicants) v Michael Thomas O'Loughlin Junior, Clayton Douglas O'Loughlin, Tarquin Michael O'Loughlin, and Jarrod Patrick O'Loughlin
(respondents)FILE NO: MER065-23 DIVISION: General PROCEEDING: Application to decide compensation and conduct DELIVERED ON: 8 December 2023 DELIVERED AT: Brisbane HEARD ON: 18, 19 and 20 October 2023 HEARD AT: Brisbane MEMBER: JR McNamara ORDERS: I determine for MDL 442:
1. Ten Thousand, Three Hundred and Fifty-four dollars and Fifty cents ($10,354.50) be paid pursuant to and in satisfaction of the general liability to compensate under s 81 of the Mineral and Energy Resources (Common Provisions) Act 2014;
1. Twenty-five Thousand, Nine Hundred and Forty-seven dollars and Thirty-three cents ($25,947.33) representing negotiation and preparation costs be paid pursuant to and in satisfaction of any liability under s 91 of the Mineral and Energy Resources (Common Provisions) Act 2014.
1. That the disputed terms of the Conduct and Compensation Agreement are decided in accordance with the Schedule attached to these orders.
1. Any submission as to costs must be filed and served within 28 days of the publication of these reasons.
CATCHWORDS: ENERGY AND RESOURCES – MINERALS – MINING FOR MINERALS – COMPENSATION – where the Applicants hold a Mining Development Licence (MDL442) located within the Respondents’ land – where the Applicants propose to conduct advanced exploration activity on the Respondents’ land – where the Respondents are a family enterprise operating Exevale station – whether the impacts of exploration activity cause claimed effects on cattle – whether such effects are compensatable effects pursuant to s 81 of the Mineral and Energy Resources (Common Provisions) Act 2014 (MERCPA) – whether proposed exploration activity and associated noise and disturbance cause ‘mismothering’ of calves – where the court heard such evidence for the first time – where the Respondents claim compensation for loss of opportunity for a time beyond the duration of the proposed exploration activity – where the Respondents claim reduced income as a result of the reduction of calves caused by proposed exploration activity – where the Respondents claim reduced value of meat sold due to reduction of weight gain caused by proposed exploration activity – where the Respondents claim compensation for additional management time under s 81(4)(b) MERCPA – where the parties agree on compensation under s 91 MERCPA – where the Court determines compensation under s 81 MERCPA
ENERGY AND RESOURCES – MINERALS – MINING FOR MINERALS – CONDUCT OF MINING OPERATIONS – where the Applicants propose drilling and exploration activity on the Respondents’ land – where draft conduct and compensation agreement provides for conditions of rehabilitation – where Respondents’ seek inclusion of ‘dust and soil’ under biosecurity clauses – where conduct clauses are presented in a draft conduct and compensation agreement – where the Court determines disputed conduct conditions under s…
Keep reading for free
Create a free CaseChat account to read Hail Creek Coal Holdings Pty Ltd v O'Loughlin and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2023] QLC 22
- Decision Date
CaseChat Overview and Summary
The legal issues included whether the proposed exploration activities would cause compensatable effects under s 81 of the MERCPA, and if so, the extent of the compensation. The court also had to decide on the appropriate conditions for the conduct of the mining operations under s 96 of the MERCPA, particularly regarding biosecurity measures and weed monitoring.
The court reasoned that the proposed exploration activities would indeed cause compensatable effects, but not to the extent claimed by the respondents. The court found that the respondents were entitled to compensation for the deprivation of possession of the land’s surface and for the diminution of the use of the land for the 180-day period required to complete the activities, including rehabilitation. However, the court disallowed the claim for additional and ongoing compensation beyond the 180-day period. Regarding the conduct conditions, the court decided that the Applicants' proposed conditions for vehicle washdown and weed monitoring were appropriate, rejecting the respondents' suggested amendments.
The final orders required Hail Creek Coal Holdings Pty Ltd to pay a total of $10,354.50 for compensation under s 81 of the MERCPA and $25,947.33 for negotiation and preparation costs under s 91 of the MERCPA. The court also decided the disputed terms of the Conduct and Compensation Agreement in accordance with the attached schedule. Any submissions regarding costs were to be filed within 28 days of the publication of the reasons.
Orders
Orders of the court
I determine for MDL 442:
1. Ten Thousand, Three Hundred and Fifty-four dollars and Fifty cents ($10,354.50) be paid pursuant to and in satisfaction of the general liability to compensate under s 81 of the Mineral and Energy Resources (Common Provisions) Act 2014;
1. Twenty-five Thousand, Nine Hundred and Forty-seven dollars and Thirty-three cents ($25,947.33) representing negotiation and preparation costs be paid pursuant to and in satisfaction of any liability under s 91 of the Mineral and Energy Resources (Common Provisions) Act 2014.
1. That the disputed terms of the Conduct and Compensation Agreement are decided in accordance with the Schedule attached to these orders.
1. Any submission as to costs must be filed and served within 28 days of the publication of these reasons.
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
In their compensation statement, the Applicants say that they have allowed for a ‘180-day window’ within which their exploration activities, including post-disturbance rehabilitation activities, will be undertaken. That includes the time for cultural heritage and environmental inspections, the creation of new access tracks and drill pads, undertaking the drilling activities, undertaking sampling and logging of the drill holes, and rehabilitating the drill sites and new access tracks. They say they will not be on the land at all times during the 180-day period.Preparation and location During opening submissions, Senior Counsel for the Applicants presented Queensland Globe imagery comprising four plans: the first showing the cadastral boundaries of Exevale and the road reserve; the second included the proposed drill sites and access tracks; the third included affected Exevale paddock boundaries; and the fourth included an overlay of a Powerlink (transmission line) easement (below). The imagery confirms that three Exevale paddocks will be impacted by the proposed advanced activities: the Front Paddock, the Bullock Paddock, and the Three Springs Paddock. Dr Stephens was engaged by the Respondents to provide an opinion on the economic impacts and/or loss of profits that the Respondents might suffer having regard to the activities of the Applicants. Usefully included in Dr Stephens’ report, is the following table: A more detailed plan showing the location of the proposed advanced activities (below) was attached to the 10 July 2023 Affidavit of Exploration Superintendent Bradley Pearson. The plan shows the location of the road reserve (shaded) and the actual physical location of Turrawulla Road (mostly off alignment just to the east of the road reserve). The road reserve and the physical road are in a NNW/SSE alignment. The outline of MDL 442 can be seen, as can the location of 15 proposed drill holes and the existing drill hole to be rehabilitated. Three of the drill hole sites are on the road reserve. The remaining 12 sites are in relatively close proximity to either the road reserve and/or the physical road. The plan shows (in yellow) 1.5 km of existing access tracks intended to be used, and (in green) 6.75 km of new tracks proposed for access to drill sites. In the hearing, it was accepted that the distance between the most northern drill site and the most southern was approximately 7 kilometres.Disturbance Each drill site will consist of a drill pad – an area of 30 metres x 33 metres, or 0.1 hectare. The dimensions of the disturbance area at any one location are limited by the EA to a maximum 1000m2. There will be only one drill hole per drill pad unless a ‘re-drill’ is required, in which case the second hole will be in close proximity to the first. Mr Pearson, in his affidavit, says that when the sites were inspected it did not appear that any of the sites required any slashing, nor did it appear that any levelling was required. In evidence, Mr Pearson noted that during an inspection tour with the O’Loughlins, he was unable to identify any access to one site, R008, and it was uncertain if that site would be drilled.