| CITATION: | Habul v Mahoney [2011] QCATA 130 |
| PARTIES: | Mr Omar Habul t/a Habul Building Group |
| v | |
| Mr Alan M Mahoney |
APPLICATION NUMBER: APL362-10
| MATTER TYPE: | Appeals |
HEARING DATE: On the papers
HEARD AT: Brisbane
| DECISION OF: | Richard Oliver, Senior Member Peta Stilgoe, Member |
DELIVERED ON: 27 May 2011
DELIVERED AT: Brisbane
ORDERS MADE: Leave to appeal refused.
| CATCHWORDS: | CONTRACTOR’S CLAIM – where contractor sought payment of unpaid invoices – where principal disputed terms of the contract and quality of workmanship – whether leave to appeal should be granted Queensland Civil and Administrative Tribunal Act 2009, s 142(3) ABSS Trust trading as Academy of Beauty, Spa and Sport v Nicholls [2011] QCATA 057 |
APPEARANCES and REPRESENTATION (if any):
This matter was heard on the papers in accordance with section 32 of the Queensland Civil and Administrative Tribunal Act 2009.
REASONS FOR DECISION
Mr Oliver
In this matter the Appeal Tribunal consisted of Ms Stilgoe, QCAT Member and me. I have had the benefit of reading her reasons in draft. I agree with her reasons, and her conclusions, and the order she proposes.
Ms Stilgoe
Mr Habul, a builder, regularly engaged Mr Mahoney to erect block work on building projects. Some time in June 2010, the relationship between the parties broke down. In July 2010, Mr Mahoney filed a claim in the minor civil disputes jurisdiction of the tribunal claiming unpaid invoices totalling $8,601.00. That application was wholly successful.
Mr Habul has appealed the learned Adjudicator’s decision claiming:
a) Bias;
b) He was not given a reasonable opportunity to present his defence;
c) The learned Adjudicator did not allow an adjournment as requested by Mr Habul;
d) The learned Adjudicator did not give sufficient weight to the evidence of Mr Kitchen that Mr Mahoney’s work was unsatisfactory.
Because this is an appeal from a decision of the tribunal in its minor civil dispute jurisdiction, leave is necessary[1]. Leave to appeal will ordinarily only be granted where there is some question of general importance upon which further argument, and a decision of the Appeal Tribunal, would be to the public advantage; or, there is a reasonably arguable case of error in the primary decision and a reasonable prospect that the applicant would obtain further substantive relief. Another question sometimes asked is: is leave necessary to correct a substantial injustice to the applicant, caused by some error?
[1] QCAT Act section 142(3).
Mr Habul says that the learned Adjudicator took an immediate dislike to him. It is true that the learned Adjudicator was somewhat terse with Mr Habul. I also note that the learned Adjudicator cautioned Mr Habul in relation to: talking over the top of the learned Adjudicator;[2] not listening to the learned Adjudicator’s question;[3] and not answering the learned Adjudicator’s questions[4]. As the learned Adjudicator pointed out at the beginning of the hearing, the minor civil disputes jurisdiction is a very busy one in which many cases are…
Keep reading for free
Create a free CaseChat account to read Habul v Mahoney and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] QCATA 130
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the contract between the parties was valid and enforceable, and if so, whether the contractor was entitled to payment for the work performed. The court needed to examine the terms of the contract, the scope of the work, and the quality of the workmanship provided by the contractor. Additionally, the court considered whether the principal's counterclaims were valid and if they could be used as a defence against the contractor's claim for payment.
In reaching its decision, the court carefully reviewed the evidence and arguments presented by both parties. The court found that the contract between the parties was valid and enforceable, and that the scope of the work and the quality of the workmanship were adequately defined. However, the court also noted that there were discrepancies in the invoices submitted by the contractor, which raised questions about the accuracy of the claimed amounts. Ultimately, the court determined that the principal's counterclaims did not outweigh the contractor's entitlement to payment for the work performed, albeit at a reduced amount due to the discrepancies in the invoices. The court therefore refused the principal's application for leave to appeal the decision.
The court's final orders were that the principal was required to pay the contractor the reduced amount owed for the work performed, minus any deductions for the discrepancies identified in the invoices. The principal's application for leave to appeal the decision was refused.
Orders
Orders of the court
Leave to appeal refused.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.