H and M Constructions (NSW) Pty Ltd v Golden Rain Development Pty Ltd

Link copied
Case Copied 5 min read

Supreme Court


New South Wales

Medium Neutral Citation: H & M Constructions (NSW) Pty Ltd v Golden Rain Development Pty Ltd [2021] NSWSC 708
Hearing dates: On the papers
Decision date: 16 June 2021
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Security for costs ordered up to time of proposed mediation

Catchwords:

COSTS – security for costs – where no dispute that Court’s jurisdiction to order security enlivened – whether plaintiff’s claim should be seen as defensive – where defendant foreshadowed possible cross-claim but eschews current intention to bring a cross-claim

Legislation Cited:

Australian Consumer Law

Corporations Act 2001 (Cth)

Uniform Civil Procedure Rules 2005 (NSW)

Category:Procedural rulings
Parties: H & M Constructions (NSW) Pty Ltd (Plaintiff/Respondent)
Golden Rain Development Pty Ltd (Defendant/Applicant)
Representation:

Counsel:
D J Batt QC with F Cameron (Plaintiff/Respondent)

Solicitors:
Pinsent Masons (Plaintiff/Respondent)
Allens (Defendant/Applicant)
File Number(s): SC 2021/115569

Judgment

  1. The Plaintiff, H & M Constructions (NSW) Pty Ltd, is a construction contractor. The Defendant, Golden Rain Development Pty Ltd, is a developer. H & M and Golden Rain are parties to a construction contract.

  2. H & M commenced these proceedings in the Supreme Court of Victoria on 5 March 2021 seeking ex parte relief to restrain Golden Rain from calling on a bank guarantee under the contract.

  3. The security had already been converted into cash but a continuing restraint on recourse to that cash was ordered by consent and remains in place.

  4. H & M filed a Statement of Claim in the Supreme Court of Victoria which pleads breach of the contract, unconscionable conduct under the Australian ConsumerLaw and seeks the return of security and damages.

  5. On 9 April 2021 the proceedings were transferred to this Court.

  6. By Notice of Motion dated 27 April 2021 Golden Rain seeks security for costs.

  7. There has been no relevant delay in the bringing of the application, as was foreshadowed as early as 30 March 2021 when the proceedings were still in the Supreme Court of Victoria.

  8. H & M does not dispute that the Court’s jurisdiction to order security is enlivened.

  9. However, H & M contends that its proceedings are “defensive” and that H & M is, in effect, a defendant in these proceedings, which have been triggered by Golden Rain taking “self-help” procedures by seeking to have recourse to the bank guarantees provided by H & M under the construction contract.

  10. However, H & M seeks substantive relief in the proceedings. It pleads breaches of the construction contract and unconscionable conduct under the Australian Consumer Law.

  11. I do not see that H & M, in substance, should be seen as a defendant in the proceedings.

  12. H & M Constructions that:

“The defensive nature of H & M’s claim is further highlighted by the fact that Golden Rain has foreshadowed making a claim (which it refuses to bring forward as a cross-claim) on the basis that it asserts it ‘has other claims against the Contractor, including for damages, which may exceed…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read H and M Constructions (NSW) Pty Ltd v Golden Rain Developmen... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] NSWSC 708
Decision Date

CaseChat Overview and Summary

In the case of H and M Constructions (NSW) Pty Ltd v Golden Rain Development Pty Ltd, the dispute arose between the plaintiff, H and M Constructions, and the defendant, Golden Rain Development. The plaintiff sought an order for security for costs from the defendant. The case was heard in the Supreme Court of New South Wales. The primary issue before the court was whether the plaintiff's claim should be viewed as defensive, particularly given that the defendant had foreshadowed a possible cross-claim but had no current intention to bring one. The court needed to determine the appropriate application of the security for costs provisions.

The court examined the circumstances under which the plaintiff's claim was made and the defendant's potential for bringing a cross-claim. It was established that the jurisdiction to order security for costs was indeed enlivened. However, the court had to consider whether the plaintiff's claim could be classified as defensive based on the defendant's actions and intentions. The court found that the plaintiff's claim was not inherently defensive, despite the defendant's potential to bring a cross-claim in the future. The court reasoned that the plaintiff's claim was primarily for compensation for breach of contract and did not serve to counter or respond to any existing claims from the defendant.

The court concluded that the plaintiff's claim was not defensive in nature and that the defendant's potential for bringing a cross-claim did not alter this assessment. The order for security for costs was granted in favour of the plaintiff, reflecting the court's determination that the plaintiff's claim was not defensive. This decision ensured that the plaintiff could proceed with the litigation without undue financial burden, while still allowing for the possibility of the defendant initiating a cross-claim in the future. The court's judgment balanced the interests of both parties, providing clarity on the application of security for costs in this particular context.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.