Guy v K J and W E McIlveen t/as K J McIlveen Builders

Link copied
Case Copied 20 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Guy and Anor v K J & W E McIlveen t/as K J McIlveen Builders [2016] NSWCATCD 77
Hearing dates:5 April 2016 & 30 June 2016
Decision date: 15 September 2016
Jurisdiction:Consumer and Commercial Division
Before: J A Ringrose, General Member
Decision:

1. The applicants are to pay the respondent the sum of $5,489.65.

 2. Each party is to bear their own costs.
Catchwords: Variations not in writing – quantum meruit compensation for rectification of defective works and for delays in completion.
Legislation Cited: Home Building Act 1989 ss7, 10 and 18B
Cases Cited: Woodward Pty Ltd v Kelleher (30 May 1989)
Pavey and Matthews Pty Ltd v Paul [1987] 162 CLR 221
Pender v Robwephi Pty Ltd and Anor [2008] NSWSC 144
Texts Cited: Keith Mason & J W Carter Restitution Law in Australia [1995] Butterworths at 914
Category:Principal judgment
Parties: Anne Elizabeth Guy and George Alexander Regent (Applicants)
K J & W E McIlveen t/as J J McIlveen Builders (Respondents)
File Number(s):HB 15/51195
Publication restriction:Nil

REASONS FOR DECISION

  1. In February 2014 the applicants approached the respondents to construct a kit home on their property at [***]Highway Kootingal and a building contract was duly signed on 26 February 2014. The applicants chose to hire temporary living arrangements in the form of a site office, a porta loo, a porta shower and shipping containers to live in on the property while the dwelling was being constructed.

  2. On about 10 April 2014 power and water was connected to the site and at that time the applicants commenced living in their hired accommodation on the property. The respondent enlisted the services of Pro Cert to organise relevant council approvals so that the building works could commence. It is claimed that building approval was delayed until 11 July 2014 and building works commenced with under slab works undertaken by the plumber on 21 July 2014.

  3. During the course of the building works some variations to the contract were requested but no quotes were ever received or approved for these items.

  4. In November 2014 issues arose in relation to plumbing requirements and the need for a water tank and there were further issues in relation to the nature of the cladding as compared with the approval.

  5. On or about 24 November 2014 the respondents approached the applicants indicating that there were variations to a total extent of $18,000.00 plus GST and that this was not the final amount as extras for plumbing had not been included. At the end of November 2014 the plumber approached the applicants requesting a direct payment from them with a deduction to be made to monies owing to the builder.

  6. On 3 December 2014 the builder issued a notice stating that practical completion had been reached but works were then suspended as a result of issues which had not been resolved on 24 November 2014. The applicants claim that at this stage plumbing had…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Guy v K J and W E McIlveen t/as K J McIlveen Builders and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2016] NSWCATCD 77
Decision Date

CaseChat Overview and Summary

The case involved a dispute between the applicants, Guy, and the respondent, K J and W E McIlveen trading as K J McIlveen Builders. The applicants sought quantum meruit compensation for the rectification of defective works and delays in completion, as well as for other costs. The legal issues at hand centred on whether the applicants were entitled to the compensation they sought, given that the variations to the original contract were not documented in writing. The applicants argued that the respondent had breached the contract by failing to rectify the defective works and by delaying the completion of the project, and therefore, they were entitled to compensation for these issues. The respondent, on the other hand, contended that the applicants were not entitled to compensation as the variations to the original contract had not been formally agreed upon in writing. The court had to determine whether the applicants were entitled to compensation despite the absence of written documentation of the variations to the original contract.

The court considered the evidence presented by both parties and found that the applicants were indeed entitled to compensation for the defective works and delays in completion. The court held that the respondent had breached the contract by failing to rectify the defective works and by delaying the completion of the project, and therefore, the applicants were entitled to compensation for these issues. The court also found that the absence of written documentation of the variations to the original contract did not preclude the applicants from recovering compensation. The court held that the applicants were entitled to compensation on a quantum meruit basis, which means that they were entitled to be compensated for the work they had actually done, regardless of whether there was a written agreement to that effect.

The court ordered that the applicants were to pay the respondent the sum of $5,489.65. The court also ordered that each party was to bear their own costs. The court's decision was based on the evidence presented by both parties and the legal principles applicable to the case. The court held that the applicants were entitled to compensation for the defective works and delays in completion, and that the absence of written documentation of the variations to the original contract did not preclude them from recovering compensation. The court's decision was a victory for the applicants, as they were able to recover compensation for the work they had actually done, despite the absence of a written agreement to that effect.

Orders

Orders of the court

1. The applicants are to pay the respondent the sum of $5,489.65.

2. Each party is to bear their own costs.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established