Gutteridge Haskins & Davey Pty Ltd v McCutcheon
[1993] HCATrans 65
IN THE HIGH COURT OF AUSTRALIA
Office of the Registry
Melbourne No M30 of 1992 B e t w e e n -
GUTTERIDGE HASKINS & DAVEY PTY
LTD
Applicant
and
ANDREW McCUTCHEON and THE STATE
OF VICTORIA
Respondents
Office of the Registry
Melbourne No M31 of 1992 B e t w e e n -
GUTTERIDGE HASKINS & DAVEY PTY
LTD
| Gutteridge(2) | 1 | 12/3/93 |
| MASON CJ BRENNAN J GAUDRON J |
Applicant
and
ANDREW MCCUTCHEON and THE STATE
OF VICTORIA
Respondents
Applications for special leave
to appeal
TRANSCRIPT OF PROCEEDINGS
AT MELBOURNE ON FRIDAY, 12 MARCH 1993, AT 10.10 AM
Copyright in the High Court of Australia
MR J.L. DWYER, QC: If the Court pleases, I appear with my
learned friend, MR R.J. MANLY, for the applicant in
each matter. (instructed by Minter Ellison Morris Fletcher)
MR A.G. UREN, QC: If the Court pleases, I appear with my
learned friend, MR R.E. COOK, for the respondent in
each case. (instructed by J. Gregory)
MASON CJ: Yes, Mr Dwyer.
| MR DWYER: | The outline of argument that has been filed |
MASON CJ: Yes, we have had the opportunity of reading those
outlines.
MR DWYER: It identifies what are really four separate
questions, although the first two are closely
related. The submission is that both the onus point and the question of when damage is first
sustained in relation to the limitation of actionsdefence are both important questions, and questions
on which special leave should be granted.
It is submitted that in each case the decision of the Full Court is a decision which is not in
accord with well established authority, and it is
submitted that in each case it is important for the
operation of the law of tort in Australia that the
issue be determined and be determined by this
Court.
| MASON CJ: | Did the decision turn on the onus point? |
| Gutteridge(2) | 12/3/93 |
| MR DWYER: | It is submitted that it did because the Full |
Court expressly referred to the fact when it was analysing the evidence in relation to whether or not damage had occurred prior to 6 April 1981, that
we carried the onus, and it is submitted that had
the onus been the other way, that body of evidence
would not have been able to be disposed of in the
way that the Full Court disposed of it, that is, if
the Full Court had been saying, "Having regard to
this evidence can the plaintiff establish that
damage had not been suffered before 8 April 1981?"
the answer would have been different, in our
submission. In that way, the onus question was at
the heart of the Full Court's decision on the
limitation of actions defence.
We have set out in the outline the very
considerable body of authority which supports the
proposition for which we argue that the onus lay on
the plaintiffs, and it is submitted that the
Full Court ought to have applied that body of
authority and ought not to have departed from it in
the way that it did. As the outline acknowledges, there have been suggestions in some cases that
perhaps a different rule might be contemplated, but
that did not provide a basis for the Full Court to
depart from that authority. We do rely on the proposition that in this area of the law, the
proposition that is contained in paragraph 5 on
page 3 of the outline, that in this area of the law
the rules established by precedent are what count;that the incidence of the legal burden of proof as
is said in Cross on Evidence can only be ·determined
by consulting the precedents and not by considering
a priori from the nature of pleading and such like,
where the incidence of the burden of proof should
lie on a particular question.
| BRENNAN J: | Mr Dwyer, could you direct me to the page of the |
appeal book in which the Full Court reversed the
onus?
| MR DWYER: | The discussion on the issue starts at page 288, |
but the particular passage that I have in mind is
in relation to the analysis that the Full Court
does which begins at page 304 of the appeal book,
where the Full Court goes back referring witness by
witness to what their analysis of the evidence was.
It is in the course of that that the Full Court
makes express reference to the fact that we carried
the onus. I am sorry, just for the moment I am unable to put my finger on the particular passage,
but it is in that part of the judgment. I will
have my junior have a more careful look while I
continue with other matters if I may. It is at
page 303 and at line 9 the court says:
| Gutteridge(2) | 3 | 12/3/93 |
His client bears the onus here and "defects"
means, not some physical damage to the
structure occasioned by the inadequacy of the
footings, but that inadequacy itself.
If I could pass to the question,of when was damage
first sustained, the law which we say should have
been applied is the law as contained in
Cartledge v Jopling and in Pirelli, because we say
that damage in the form of cracking and settlements
had occurred between the opening of the pool in
September 1980 and March 1981 at any rate; and the
six years before the date of commencement of the
action takes us to April 1981.
So it is submitted that the facts of the case
directly raise the question whether the test in
Pirelli should be applied. The Full Court did not
apply the test in Pirelli, but rather applied what
it understood to be the effect of what
Mr Justice Deane had said in Hawkins v Clayton.
But it is our submission that the Full Court
misunderstood what Mr Justice Deane said, and that
Mr Justice Deane was not intending to lay down a
different rule from the rule in Pirelli. That
really turns on an understanding of what
Mr Justice Deane said and intended to say in the
passages which are quoted extensively by the Full
Court.
It is our submission that what
Mr Justice Deane did in those passages was draw a
distinction between two cases. On the one hand you have the case where due to a latent defect in a
building, on the discovery of that defect the
economic value of the building is affected. This
is a case where the building has not itself
suffered any physical damage, but it becomes known,
for example, that the foundations of the footing
are defective. Once that is known, the value ofthe building is reduced and so it is the coming to
case as the occurrence of damage. light of that fact which can be regarded in such a That cannot be the case, we submit, where what happens is not simply the finding out of the
existence of defective footings, but what happens is that the building suffers physical damage itself, which was the case in Pirelli and which is
the case here. Where the building itself starts to crack, where parts of the building start to settle
and to twist, the plaintiff, as the owner of thebuilding, plainly suffers real damage when that
starts to happen. Mr Justice Deane in the passages
quoted made allowance for that. He accepted from what he was saying about the pure loss in value cases, he accepted from that analysis the cases
| Gutteridge(2) | 4 | 12/3/93 |
where there is physical damage to the building.
But the Full Court overlooked that distinction that
Mr Justice Deane had drawn.
The error that the Full Court fell into could
be put this way: they proceeded by establishing a
conceptual category by pushing the case into that
category and by then saying that certain
consequences follow. The category they established was the category of economic loss. The first move they make is to say, "We should regard this as an
economic loss case"; and the next move is to say, "Because we regard this as an economic loss case we
therefore apply observations that have been made
about when damage is incurred in economic losscases." But to do so is to ignore the actual
facts. It is to prefer the category or the concept to what really happened. We would submit it is plain beyond argument that damage was suffered when
the building started to crack and when the building
started to settle, and it is in that way that the
Full Court applied, in our submission, an incorrect
analysis. We say it is a matter of the utmost importance to the operation of the law of tort in
Australia that that matter be corrected, that it be
understood clearly by litigants and by courts that
where physical damage is sustained, the cause of
action is complete from the time that that physical
damage is sustained. So we submit that on that issue leave ought to be granted.
The third issue was the question of the
finding of negligence which the Full Court made
against our client overturning the decision of the
trial judge that our client had not been negligent.
The trial judge's finding, we say, was based on the
judge's assessment of a considerable body of
evidence and the witnesses who appeared before him,
including a number of experts who were called, and
who said that what our client had done was in
conformity with good engineering practice and had been properly carried out. The trial judge accepted that analysis of what our client had done,
and so the Full Court, in making its finding that
despite that evidence and those findings by the
trial judge, we had been negligent, the Full Court
focused on two particular matters.
The first of them was the Full Court's own
interpretation of Exhibit Cl. Exhibit Cl is
contained in the appeal book at page 384, and I
invite the Court to look at the drawing.
GAUDRON J: It is hard to see that this raises any question
of principle, is it not?
| Gutteridge(2) | 5 | 12/3/93 |
| MR DWYER: | The question of principle that it raises is this: |
the Full Court, as it were, departed from the trial judge's assessment on the question of negligence by
its own interpretation of this document. It is one
thing to do that in cases where the interpretation
of the document is incontrovertible. It is one
thing to do that in cases where the inferences to
be drawn from the document are plain and
inexorable. But this is not such a document. This
is a document which, in our submission, is highly
ambiguous as to its interpretation; and it is a
document, the interpretation of which by engineers,
had not-been the subject of evidence at the trial.
The trial evidence had not got beyond the plaintiff
who had tendered the document in opening putting it
to one engineering witness and getting statements
from that witness which, in our submission, are
highly equivocal, and which do not bear the
interpretation the Full Court put on them.
The question is not simply: what does the
document mean? The question is: was it negligent
of engineers dealing with the document at the time
to interpret it in a particular way? As to that, what the Full Court has done is.simply say, "It is
negligent because we interpret it this way and we
regard that as the interpretation which any
competent engineer should have put on the
document." The matter just was not open to be dealt with in the Full Court in that way, we
submit. The important question of law that that raises is whether what the Full Court did is within
what is permissible under, for example, Dawson's
case, where the High Court dealt with the drawing
of inferences from documents where that inference is inescapable. But here, the inference, we say,
is not only not inescapable, we say the inference
is wrong, and we say there is simply nothing in the
document to entitle the Full Court to do what they
did.
| MASON CJ: | How does that become a special leave point? |
| MR DWYER: | It becomes a special leave point because the Full |
Court ought to have been confined in its approach
to this document. The Full Court has gone beyond
what was said in Dawson's case to be appropriateto, if you like, an extended question. Dawson's
case says that an intermediate court of appeal may
draw an inference from the face of a document if
that inference is inescapable. The Full Court has gone beyond that. The Full Court has said, "We draw this inference from the face of this document
because that is our interpretation of thedocument." It is not, as it were, a legal document
or a letter which a court may be able to interpret
for itself. It is a drawing containing
| Gutteridge(2) | 6 | 12/3/93 |
information, the issue being: how was it appropriate for an engineer to deal with that
information? We say that in approaching the matter
in that way, the Full Court simply went beyond what
it is permissible for an intermediate court of
appeal to do, and we say that is a special leave
point.
The submission at pages 8 and 9 sets out in
detail what we say about that document and why we
say what the Full Court did was wrong. The Court
has the document. The inference that the Full Court drew was that the measurements as to sinking
that are recorded on Exhibit Cl are to be
interpreted as being measurements relative to
something which was itself sinking and not absolute
measurements, that is, measurements by reference to
some fixed datum. But the problem with Exhibit Cl is that it just does not tell one which of those
interpretations of the document is correct, and as
we say, it was not appropriately canvassed at the
trial.
The second matter that the Full Court relied
on was what is dealt with in the outline of
submission on page 10 as being the South Melbourne
experience. The Full Court took a view as to the implications which an engineer ought to have taken
from the South Melbourne experience, and took a
different approach on this question to the trial
judge, that is, the Full Court did not accept the
conclusion which the trial judge made that there
were reasons for differentiating between the site
of these works and the South Melbourne site.
Our submission is that it was not open to the Full Court to deal with this question in the way
that they did - - -
| BRENNAN J: | Mr Dwyer, would it be necessary if an appeal |
were allowed on this basis for the appellate court to form its own view about the conclusion reached
by the Full Court?
| MR DWYER: | In our submission, it would be that the appellate |
court would not need to go beyond the question
whether the Full Court was right or wrong to
approach the matter as the Full Court did.
| BRENNAN J: | Why not? |
| MR DWYER: | Because it would be appropriate, in our |
submission, rather than the appellate court
involving itself in determining this question on the material, to remit the matter for retrial on the issue.
| Gutteridge(2) | 12/3/93 |
BRENNAN J: Retrial by a single judge?
| MR DWYER: | Yes. |
BRENNAN J: But it has been tried by a single judge, and
there is an appeal. If you set aside the judgment
of a Full Court you would have to remit it to the
Full Court to rehear, would you not?
| MR DWYER: | Unless the Court were persuaded that the points |
raised by the Full Court were points which had not
been appropriately canvassed at the trial
itself - - -
| BRENNAN J: | It seems to me that before you could make any of these points run you would have to take us through |
| MR DWYER: | We would be confident that it would not be |
necessary to do that because - - -
| MASON CJ: | You might not do that, but your opponent almost |
certainly would be forced into a situation where
that would require us to look at all the evidence.
| MR DWYER: | On particular issues it may be necessary to look |
at all the evidence.
| MASON CJ: | How long did this case last in the Full Court? |
MR DWYER: Before the Full Court?
MASON CJ: Yes.
MR DWYER: It was, I think, 12 days from memory.
BRENNAN J: That is a very substantial concession you have
just made, Mr Dwyer.
| MASON CJ: | Some might think it is fatal. | |
| MR DWYER: | Could I say this: | that at least some of the time |
before the Full Court was taken up with issues
which the Full Court said it was not necessary to
determine and did not determine. They are issues
which are referred to in the judgment, for example,
as to what the future holds for this pool, whether
the design of it is such that it will withstand
future settlements or whether it will not. There was a considerable analysis of matters of that
kind, and time was spent on other issues in what the trial judge had done which do not find their
way into the decision of the Full Court.
| MASON CJ: | Mr Dwyer, it really does emerge, does it not, |
that if the case came to the Court on this footing
| Gutteridge(2) | 8 | 12/3/93 |
it would require a great deal of expenditure of the Court's time investigating a matter that really is,
in substance, an issue of fact.
| MR DWYER: | On the question of negligence |
MASON CJ: Yes.
| MR DWYER: | - - - it is difficult to controvert that, |
Your Honour. But from the point of view of my client who - - -
| MASON CJ: | I follow that, but that is one of the reasons why |
the Court rarely grants special leave where the
substantial issue is an issue of fact.
| MR DWYER: | We are conscious of that, Your Honour, but all |
that we can say is that the Full Court confined
themselves to particular matters in deciding that
our client was negligent, and the examination of
where the Full Court went wrong, as we say, on
conveniently and quickly dealt with, and we have outlined in the outline of argument how those points arise and how they could be disposed of.
those particular matters is in much smaller compass
than the examination of the whole of the evidence.From the litigant's point of view the question
of whether the outcome in the Full Court is a
proper one is a matter of the utmost importance,
and this is a case where the professional
reputation of a firm of engineers is very much at
the front line of the decision. They are not just a local firm, they are a firm that practises
Australia wide, and it is, from their point of
view, very much to be regretted if they cannot have
their contentions dealt with simply because the
issues involved are too extensive.
The fourth point fortunately is one in very
small compass indeed, and that is the Rodger v The
Comptoir D'Escompte de Paris point as to whether or
not it was proper for the Full Court to award
interest on the costs which were ordered to be
repaid. Our point there simply is that the Privy Council said all those years ago that it could not
be done on the ordering of costs to be repaid that you add interest to them, because it was said then that it has never been known to be done before and
"We can't and won't do it". And there is no decision since then which says that it can be done.
So the Full Court has simply taken a new approach based on their own view of - - -
| GAUDRON J: | Do you say it is outside their rules? | Do the |
rules provide with respect to interest at all?
| Gutteridge(2) | 9 | 12/3/93 |
| MR DWYER: | We understand that the respondents seek to rely |
on section 58 of the Supreme Court Act, but that
does not apply to the award of interest on ordering
costs to be repaid. We say it is plain, if you look at the section, that it does not provide for
it and the rules do not in terms provide for it
either. So it is just a new thing that the Full Court has done in the face of authority and without
having any authority at all to support what they
have done, in our submission.
| GAUDRON J: | And was the matter argued in the Full Court? |
| MR DWYER: | Very briefly. | The matter was only raised at the |
time of handing down judgment, that is, when
judgment was taken the Full Court indicated what
they intended to do subject to what counsel might
argue. We submitted to them that they could not
and should not, but they did not depart from the
view that they already formed that that was the
extent of the argument.
The other matter that I should remind the
Court of is the fact that there is, of course, to
be a retrial in any event on the question of
damages because the Full Court has ordered that,
and it was our contention before the Full Court,
and it remains our position, that if there is to bea retrial it ought to be a retrial on all issues
rather than simply on the question of damages. The Full Court dismissed that contention in a sentence,
simply saying that they felt that that would be
unjust to the plaintiff, but they did not explain
at all or give any reasons for that contention.
It is our submission that if regard is had to
the way in which the issues on which we are said to
have been negligent have been dealt with in this
litigation, there is a a lot to be said for the
contention that justice to the defendants in the
case, justice to the engineers, requires, if there is to be a retrial, that it be on all issues and
not simply on the question of the assessment of
damages. They are the submissions, if the Court pleases.
| MASON CJ: | What about the second action? | ||
| MR DWYER: |
|
the strongest reason for submitting that leave
ought to be granted in that matter, is that it
ought go together with the first action, that is,
if leave is granted in the first action - - -
| GAUDRON J: | Does it not go rather the other way around? |
Unless you succeed with respect to the second
| Gutteridge(2) | 10 | 12/3/93 |
action everything you have put with respect to the
first is entirely academic.
| MR DWYER: | Yes, that outcome does follow. Turning then to |
the second action which has been dealt with very
shortly both at trial and in the Full Court - both
at trial and in the Full Court all the attention
was on the first action and very little attention
was given to the second action. But our submissions are that there are important questions
that arise in the second action.
The first of them is as to whether the
applicant owed a duty of care in relation to the
question of the respondent's first action becoming
statute barred. The submission there is that an engineer giving advice as to what is to be done
about faults in a building may be, if he is
negligent in that advice, liable in respect of
damage to the structure that follows from hisadvice, or damage which follows from defects in the
advice regarding the engineering matters, but that
the damage of the plaintiff getting out of time in the plaintiff's action is quite a different matter
and is entirely outside the risk, if one can put it
that way, of the advice that the engineer is
giving.
| MASON CJ: | Why is that? |
MR DWYER: | Because it is not a foreseeable consequence of the engineer giving advice about faults in the |
| building that the plaintiff will allow its action to get out of time. | |
| BRENNAN J: | What is the purpose of the report? |
| MR DWYER: | The purpose of the report was to deal with |
specific matters that had been raised, that is, the
building owner put together a detailed thing which
was called a "faults statement", and the engineer went through the faults statement dealing with each
of the matters and saying what was appropriate to
do with that matter that had been raised in the
faults statement.
| BRENNAN J: | I suppose one of the things that would be |
appropriate to do would be to sue the person
responsible for causing the fault.
| MR DWYER: | But engineers do not give advice about matters of |
that kind. That is a legal matter. If the advice
had been obtained from a lawyer - - -
| BRENNAN J: | It is not unforeseeable by an engineer that that |
might happen:
| Gutteridge(2) | 11 | 12/3/93 |
| MR DWYER: | It is not the subject on which the engineer is |
giving advice. That is really the point. The
engineer is giving advice about the faults in the
structure.
GAUDRON J: Is he giving advice about the cause of the
faults, the source of the faults?
| MASON CJ: | He must be, surely. |
| MR DWYER: | The contention is that the engineer's advice covers the source of the faults if that is what he |
GAUDRON J: Well, does that not go the whole distance for
the cause of action?
| MR DWYER: | It is submitted not, because the question of |
commencing an action is simply outside the
engineer's sphere of competence. He is not giving advice about the question of when an action must be
commenced.
GAUDRON J: Let us assume that the engineer advises that the
source of the problem is the builder's poor
workmanship, and an action is commenced against the
builder, and at the end of the day it turns out
that the source of the defect is the engineer's own
design fault and the action against him has been
lost, statute barred. It must be within thegeneral risk involved.
| MR DWYER: | It is submitted not because the engineer is not in the business of giving advice about taking legal |
| begins to run and when an action will be statute | |
| barred. That is all entirely outside the engineer's sphere of competence and the matters on which the engineer is giving advice. |
But that is only part of what we say. We say
also that it was necessary for the respondents to
prove that they relied on the engineer's advice in
waiting until. the time that they did to commence
their action. The submission is that simply no evidence at all was called that the engineer's
advice was relied on in delaying until April 1987
to commence the action. They just did not call any evidence at all on that issue.
The third principal matter is
| MASON CJ: | Did they have any other advice apart from the |
engineer's advice as to source of fault?
| Gutteridge(2) | 12 | 12/3/93 |
| MR DWYER: | Yes, they did. | They started to engage |
independent advice during 1985, but they did not
commence their proceedings until April 1987. In
the appeal book there is a document of May 1987
which demonstrates that the question of proceedings
against the engineers were being contemplated at
that time. It is at page 507 of the appeal book.
The document is briefing notes for the Minister for
Public Works. The document is undated, but it is in response to the Minister's request for briefing
notes dated 8 May 1985, so it can be accepted that
it is going to be very soon after that date. The second last paragraph on that page says: In addition, further investigations are
proceeding to ascertain liability, if any, on
the part of the Consultants responsible for
the design and structure.
So the plaintiff was actively investigating that
matter at that stage, but did not commence
proceedings until nearly two years later in
April 1987.
| MASON CJ: | What was the date of your client's report? |
| MR DWYER: | The first report is in August 1982, and the last |
report was in 1983. There were four reports
altogether.
The Full Court by a matter of analysis
identified seven months as being the critical
period because they said the action could not have
been statute barred at the earliest until six years
after the building achieved practical completion in
September 1980. So they said, "Well, the earliest
date when an action could have been statute barred
was September 1986." So they say between that date and when the action was commenced there are seven
months, and so they said that is the critical
period. And they say that they find it inconceivable that if advice had been given during
1982 and 1983 and by 1984 at the latest, that that
seven month delay still would have been incurred.
That was all supposition because no evidence had been called about the matter. The plaintiff did
not explain what factors had led to its delaying
until April 1987 in order to commence the action,
called no evidence about the matter at all, and in
those circumstances the court ought not to make an
inference favourable to the plaintiff.
| MASON CJ: | But did the plaintiff have evidence or advice |
which established a cause of action against your
clients in that relevant period of time?
| Gutteridge(2) | 13 | 12/3/93 |
| MR DWYER: | We do not know fully what advice the plaintiff |
had, but the Full Court was satisfied that by
November 1985 at the latest the plaintiff had
independent engineering advice. But the matter was not addressed at trial by the plaintiff bringing
forward the evidence which it had as to exactly
when it was advised that our client was negligent.
| GAUDRON J: | What submissions were made on behalf of your |
client in the light of that absence of evidence?
| MR DWYER: | Certainly in the Full Court we submitted that the matter should have been attended to. | I am not |
certain as to what submissions were made at trial. But certainly, in the Full Court we submitted that
the plaintiff simply had not called any evidence
about these matters, and so had not established
that it relied on our advice in waiting until
April 1987 and that was a critical part of its
action.
The other way in which it could be put is in
terms of causation and whether it can be said that
the advice that we gave in 1982 and 1983 caused the
plaintiff to delay until 1987 in commencing its
action, that is, caused the plaintiff to get out of
time.
BRENNAN J: Well, the question would be whether, if you had
discharged your duty in 1982 and 1983 and revealed
your own negligence, it is more likely than not
that an action against you would have been
commenced within time.
| MR DWYER: | Even if that is the question, Your Honour, it is |
still up to the plaintiff to call evidence in
support of the presentation of its case on that
issue, and they simply did not. They called no
evidence at all on this issue.
BRENNAN J: | The question is whether or not one inference or another can be drawn, or whether it is a case where |
| there was simply no evidence. | |
| MR DWYER: | Yes, and we say that there is no reason to draw |
the inference that the Full Court chose to draw
that it is inconceivable that they would not have
issued. We say it is as open on consideration ofall of the facts to conclude that it was a
government department that was not particularly
interested in getting galvanized into action and
meandered along without any sense of urgency until
it eventually chose in 1987 to issue.
The fact of delay is, of course, something
that bears very hardly on the engineers and which
affected, it may be thought, the conduct of the
| Gutteridge(2) | 14 | 12/3/93 |
case. Our records had been destroyed in a fire early in 1982 so our computations, for example,
were not available to us when we came to reconsider
the matter in these reports.
The plaintiff had a copy of our computations
but did not make them available to us, then or at
any time until during the trial when they were
discovered to have been locked away in a drawer.
But the result has been that it is now some
12 years since practical completion was achieved on
this building, and we are still in the position
where we are endeavouring to cope with the claim
that is made against us.
| MASON CJ: | Now, Mr Dwyer, did not an issue of this kind |
arise in Bennett's case, and was it not resolved in
accordance with a view just put to you by
Justice Brennan, ie, if correct advice had been
given, a correct report had been made, then the
inference to be drawn is that the plaintiff would
have brought an action within time?
| MR DWYER: | But in Bennett's case the advice was of a very |
different kind. In Bennett's case it is advice
from the person who had charge of the relevant
person's affairs.
MASON CJ: It was advice of a very different kind, but did
it not raise the same question of inference in
terms of causation and statute of limitations?
| MR DWYER: | A similar question of inference, but the |
inference is different, in our submission, where,
on the one hand you have a person whose affairs are
being looked after by the person who is to give the
advice and who, if he had given the correct advicein Bennett, must have had proceedings instituted.
Whereas here the question is: "What did this government department do?" One just cannot draw an inference of a similar kind, in our submission. There is just no basis to say that an inference of
the same kind as in Bennett's case could be drawn
in this case. Certainly the Full Court did notpurport to do so.
GAUDRON J: That is because, is it, the different status of
the people who should have been advised, the
different nature of the advice that was in
contemplation as well?
| MR DWYER: | Yes. |
| GAUDRON J: | And anything else? |
MR DWYER: Certainly if one compares the two persons being
advised, they stand very differently. Perhaps the
| Gutteridge(2) | 15 | 12/3/93 |
third factor is that nothing should have been
easier than for the government department to give
evidence of the matter. That is, for the
government department to not have the matter dealt
with by inference but to actually inform the court
as to what the true facts were -
| GAUDRON J: | But I suppose the difference, if there is one, |
is that in Bennett's case you knew why he had taken
no action. He had been given false and wrong advice which he would not have received if the duty
had been carried out. You say in this case, we donot know what it was that caused the delay and how
that can be related back to the advice.
| MR DWYER: | Yes, that is entirely a matter for speculation |
because the department chose never to give evidence
about the matter. We do know from this memo, for example, that the matter was being actively
considered as early as about May 1985, and in thelight of that how it could be said that our advice,
back in 1982 and 1983 was causing them not to
commence an action against us, we say, is just not
apparent at all. So we would say that that is another reason why an inference of the Bennett type
cannot be drawn, because in the face of something
like this memorandum, that at least is revealed as
to how the government department was approaching
the matter, and at that stage, in May 1985, plainly
they have ceased to be relying on our reports in1982 and 1983 as to the faults and the nature of
them and what should be done about them.
As my learned junior points out we have here
the Public Works Department with its own engineers, some of whom gave evidence in the case. We are not dealing with a lay client who does not understand
how buildings work. We are dealing with the department of State that, in fact, looks after the construction of buildings in the State of Victoria
and has its own expert staff. Again that is a circumstance which would mean that an inference of
the Bennett type should not be drawn.
So the submission is that in the second
action, the plaintiff just did not, on the
evidence, make out the action, and so the second
action is bound to fail, in our submission, on the
evidence. And if the second action is bound to
fail then the consequences to the issues in the
first action are not those which were put to me at
the outset of what was submitted about the second
action, that is, if the second action must failthen the issues in the first action are entirely
live and should be dealt with.
| Gutteridge(2) | 16 | 12/3/93 |
| MASON CJ: | I did not quite follow that. | Would you repeat |
that again, Mr Dwyer?
| MR DWYER: | If the second action must fail, then we go back |
to the first action - - -
MASON CJ: Yes, I follow.
| MR DWYER: | - - - and then the question whether the first |
action is statute barred, for example, is of the
utmost importance.
| MASON CJ: Yes. | But if, on the other hand, you do not get |
special leave in the second action, and the Court
is not willing to grant special leave to take on
the substantial issue of merit in the first action,
then the first two points you raise in the first
action, that is, onus of proof and the Pirelli
point, are academic points.
| MR DWYER: | If we do not get leave in the second action? |
MASON CJ: Yes.
| MR DWYER: | Yes, but, we would submit that we ought get leave |
in the second action as a matter of -
| MASON CJ: | I appreciate the arguments you have put, but again you see, on this question of breach of duty |
| runs over into the two, it is essentially an issue | |
| of fact. | |
| MR DWYER: | But the facts are in very short compass as can be |
seen from what is said - - -
| MASON CJ: | Not within 12-day compass. |
MR DWYER: Half a day at the outside, it is submitted. It
is really a very small point, largely because so
little attention was given to the second action at trial as can be seen from the trial judge's
judgment, and very little more was given in the
Full Court as can be seen from the Full Court's
judgment. The Full Court judgment reveals, it might be said, the paucity of evidence so that if
one then considers, "Well, what happened at the
trial will need to be brought to the attention of
the High Court to determine the outcome of the
second action", that is in very small compass
indeed.
BRENNAN J: | What would you say about the inference to be drawn from a hypothesis that the defendant had in |
| 1982 and 1983 admitted its liability for the | |
| defects in the building? |
| Gutteridge(2) | 17 | 12/3/93 |
MR DWYER: If the defendant had done that?
BRENNAN J: Yes.
| MR DWYER: | It is by no means inevitable that the department |
would have chosen to sue, the department may well
have preferred to set in course a process of
endeavouring to remedy defects very much, in a
sense, of what was done.
Could I just perhaps make this point: The
advice that was given in 1982 when the settlements
were beginning to be noticed and a measurement
programme had been instituted by the plaintiff inJune 1982, was that that monitoring programme should be continued. So a question then arises as
to when the monitoring had gone on for long enough
for definite conclusions to be drawn as to what the
monitoring of settlements revealed. There is a
document in the appeal book which indicates that from the point of view of the department, it was
only in October 1983 that one was able to draw
meaningful conclusions from the measurements. That
appears in the document that is at page 505 of the
appeal book, where in the second paragraph on thatpage it said:
After analysis of several readings taken over
a period of fifteen months a pattern starts to
appear. Only now can any conclusions be made
with any certainty.
Now, that is the department's analysis of how the
reading stood as at October 1983. That is after
the last of the reports.
So, if the advice had been in 1982 and 1983
that we may have been at fault in - - -
| BRENNAN J: | Not "may be", "we were at fault". |
| MR DWYER: | Yes. | If the advice had been "we were at fault", |
at that stage the consequences of the fault could not have been, perhaps, assessed in the same way, but the consequences are assessed at a later date.
That letter really shows that even if the first
line on that letter had said, "The engineer has
admitted that it was at fault in the design of this
structure, and that that fault has contributed to
some of the matters that have been complained of",
and it had then gone on, it was still only in
October 1983 that in that way the seriousness of
the fault could have been appreciated, and perhaps
even at a much later date.
The other matter of fact that I should draw to
the Court's attention is that the builder was still
| Gutteridge(2) | 18 | 12/3/93 |
on the job. That is, although practical completion
was achieved in September 1980 and the pool was
open to the public in September 1980 and events
started to be held there from then on, the builder
was still there engaged in rectifying matters as
late as 1985. There was an ongoing process of
matters being complained of; matters being
rectified; further matters being complained of;
further matters being rectified and so on, until in
1985 there was the attempt to resolve matters by
the issue of a final certificate.The final certificate was in contention in the Full Court in relation to whether or not there was
a defence under the contract, and the Full Court
judgment deals with that, but no appeal is sought
in relation to that particular matter. That is, we
do not seek to upset the Full Court's decision in
relation to that certificate or the defence underwere the inferences to be drawn in 1982 and 1983,
the contract which was sought to be based on it.
that this process was going on until 1985. Unless there is anything else that I can assist the Court
with I think that is all that is desired to put.
MASON CJ: Yes, thank you, Mr Dwyer. The Court need not
trouble you, Mr Uren. In the view of the Court the
proposed appeal in the second action turns on an
issue of fact and raises no question of general
principle and is therefore not appropriate for the
grant of special leave. Likewise, in the view of
the Court, the issue of breach of duty in the firstaction is one of fact raising no important point of
principle and is also inappropriate for the grant
of special leave.
In these circumstances the onus question and
the Pirelli point in the first action are of
academic interest only. The interest on costs question is not one of sufficient importance to justify the grant of special leave to appeal.
Accordingly, the two applications for special leave
to appeal are refused.
| MR UREN: | Would the Court make an order for the costs of the |
respondent?
| MASON CJ: | You do not oppose that, Mr Dwyer? |
| MR DWYER: | No. |
| MASON CJ: | The applications are refused with costs. |
AT 11.12 AM THE MATTER WAS ADJOURNED SINE DIE
| Gutteridge(2) | 19 | 12/3/93 |
Key Legal Topics
Areas of Law
-
Negligence & Tort
-
Civil Procedure
Legal Concepts
-
Limitation Periods
-
Appeal
-
Causation
-
Damages
0
0
0