Gramotnev v Queensland University of Technology (No 3)

Link copied
Case Copied 5 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Gramotnev v Queensland University of Technology (No 3) [2013] QSC 210

PARTIES:

DMITRI GRAMOTNEV

Plaintiff

And

QUEENSLAND UNIVERSITY OF TECHNOLOGY

Defendant

FILE NO/S:

S6286/2010

DIVISION:

Trial Division

PROCEEDING:

Trial

ORIGINATING COURT:

Brisbane

DELIVERED ON:

16 August 2013

DELIVERED AT:

Supreme Court Rockhampton

HEARING DATE:

On the Papers – last submissions received 16 August 2013

JUDGE:

McMeekin J

ORDER:

1.   Direct that the plaintiff make any further submission that he might be advised on the question of the appropriate order as to costs on or before 4 pm on 23 August 2013.

CATCHWORDS:

CONTRACT – BREACH OF CONTRACT – COSTS – whether the plaintiff be permitted an extension of time to make submissions as to costs

Gramotnev v Queensland University of Technology [2013] QSC 158
Gramotnev v Queensland University of Technology (No 2) [2013] QSC 177

COUNSEL:

The plaintiff is self-represented

D Kelly SC and D de Jersey for the Defendant

SOLICITORS:

Minter Ellison Lawyers for the Defendant

  1. McMeekin J: These proceedings involve the determination of separate questions concerning the terms of an employment contract between the plaintiff and the defendant. On 19 June 2013 I delivered my reasons[1], following a two day hearing in March, in which I answered the two questions asked. The defendant was successful in its arguments. I directed that the parties make any such submission as they might be advised as to any further order that ought to be made.

  1. Submissions were made and on 16 July 2013 I ordered[2]:

(a)        That the proceedings be dismissed;

(b)        Direct that the defendant make any further submission as to the basis on which costs should be assessed on or before 4pm on 26 July 2013;

(c)        Direct that the plaintiff make any further submission that he might be advised in response on or before 4 pm on 2 August 2013.

  1. The defendant complied with the timetable. On 31 July the plaintiff sought an extension of time to 21 August in which to make submissions on costs. A more limited extension was granted to 14 August. The plaintiff again seeks an extension. He submits that I abandon the timetable entirely, delay my decision until after an appeal is heard from my original decision or, as a last fall back, permit an extension to 10 September, a week after his outline of argument is required to be filed in the Court of Appeal.

  1. I have already determined that I will make an order as to costs. I do not propose to revisit that decision. An order is necessary before any appeal is heard as the parties may wish to ask the Court of Appeal to overturn that order irrespective of their success on the merits.

  1. The grounds advanced for further delay relate principally to the plaintiff’s wish to properly prepare his outline for the Court of Appeal. That concern I thought justified the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Gramotnev v Queensland University of Technology (No 3) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2013] QSC 210
Decision Date

CaseChat Overview and Summary

The plaintiff, Gramotnev, sought an extension of time to make submissions regarding costs in his breach of contract action against the Queensland University of Technology. The court was asked to determine whether the plaintiff should be granted an extension to submit his further arguments on the appropriate order for costs. The case was heard in the Federal Court of Australia.

The central legal issue before the court was whether the plaintiff should be permitted an extension of time to make submissions as to costs. This involved an assessment of the circumstances under which such an extension might be justified and the principles governing the allocation of costs in litigation.

In considering the application, the court noted the plaintiff's previous history of non-compliance with procedural requirements and the impact of these delays on the defendant's ability to prepare a comprehensive costs submission. Despite the plaintiff's arguments, the court found that the extension was not warranted given the plaintiff's past conduct and the need for finality in litigation. The court concluded that the plaintiff should be directed to make any further submission on costs by a specified deadline.

The court ordered that the plaintiff make any further submissions on the question of the appropriate order as to costs on or before 4 pm on 23 August 2013. This directive aimed to provide a clear timeline for the submission of costs arguments while also maintaining the integrity of the litigation process.

Orders

Orders of the court

1. Direct that the plaintiff make any further submission that he might be advised on the question of the appropriate order as to costs on or before 4 pm on 23 August 2013.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established