Goodacre v Romtra Pty Ltd
[1999] QCA 264
•16/07/1999
IN THE COURT OF APPEAL 99.264 SUPREME COURT OF QUEENSLAND
Appeal No. 3503 of 1998
Brisbane
[Romtra P/L v Goodacre & Maroochy SC]
BETWEEN:
ROMTRA PTY LTD (ACN 007 155 571)
(RECEIVER AND MANAGER APPOINTED)
(First Defendant) Appellant
AND:
ALLEN GOODACRE and SUSAN GOODACRE
(Plaintiffs) First Respondents
AND:
COUNCIL OF THE SHIRE OF MAROOCHY
(Second Defendant) Second Respondent de Jersey CJ
Pincus JA
Thomas JA
Judgment delivered 16 July 1999.
Separate reasons for judgment of each member of the Court, each concurring as to the order made.
APPEAL DISMISSED WITH COSTS.
section 11 of the Subcontractors' Charges Act 1974 considered - whether payment into court by employer is irrevocable admission that such money is payable to contractor - whether contractor had present entitlement to balance of fund after satisfaction of charge - possibility of different entitlements emerging as between the parties at different times.
Counsel: Mr S J Keim for the appellant.
No appearance on behalf of the first respondents.
Mr A Looney for the second respondent.Solicitors: Macrossans Lawyers for the appellant.
No appearance on behalf of the first respondents.
Mr JD Hall, Maroochy Shire Council for the second respondent.Hearing Date: 9 June 1999
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No. 3503 of 1998
Brisbane
Before de Jersey CJ
Pincus JA
Thomas JA[Romtra P/L v. Goodacre & Maroochy SC]
BETWEEN:
ROMTRA PTY LTD (ACN 007 155 571)
(RECEIVER AND MANAGER APPOINTED)
(First Defendant) Appellant
AND:
ALLEN GOODACRE and SUSAN GOODACRE
(Plaintiffs) First Respondents
AND:
COUNCIL OF THE SHIRE OF MAROOCHY
(Second Defendant) Second Respondent
REASONS FOR JUDGMENT - de JERSEY CJ
Judgment delivered 16 July 1999
I have had the advantage of reading the reasons for judgment of Thomas JA, with which I
substantially agree.
As Thomas JA points out, the intended beneficiaries of the operation of the Subcontractors’ Charges Act 1974 are primarily subcontractors, not employers: that is a consideration important to the resolution of this appeal.
The Act establishes a mechanism for the diversion to subcontractors, in order to satisfy their
claims against head contractors, of monies which would otherwise be paid directly by employers to
head contractors. It is convenient to note what may seem trite, that s.11 is not intended to facilitate the
payment of whatever claim a subcontractor may make, however excessive in amount. It is intended,
obviously enough, to secure the payment of whatever is truly due to the subcontractor from the head
contractor.
Here only $109,000.00 was due to the subcontractor, although by its notice of claim of charge,
the subcontractor had claimed the larger amount, $179,197.19. Under s.11(1) of the Act, the employer
was obliged to retain the amount necessary “to satisfy the claim”. In my view, that amount was not
$179,197.19, but $109,000.00. That sum of $109,000.00 was, as it turned out, the amount the
employer was entitled to pay into court under s.11(5), and it was to that amount that the discharge
under s.11(6) related - that is, the amount “paid” to satisfy the claim. I agree with Pincus JA that
s.11(6) operates to discharge an employer from all further liability in respect of the amount paid, both
to the subcontractor and the head contractor. I would for my part identify the amount subject to that
discharge in this case as limited to the amount of $109,000.00 in fact due.
That leaves the fate of the balance of some $70,000.00 still to be determined. Read in the way
I have indicated, s.11 could not operate to elevate the employer’s initial concession, when making
payment into court of the amount of $179,197.19 that that sum was or would become payable to the
head contractor, into an irrevocable concession to that effect still binding in the current situation of claim
and allegedly greater cross-claim.6 I agree that the appeal should be dismissed with costs.
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No. 3503 of 1998
Brisbane
Before de Jersey CJ
Pincus JA
Thomas JA[Romtra P/L v. Goodacre & Maroochy SC]
BETWEEN:
ROMTRA PTY LTD (ACN 007 155 571)
(Receiver and Manager Appointed)
(First Defendant) Appellant
AND:
ALLEN GOODACRE and SUSAN GOODACRE
(Plaintiffs) First Respondents
AND:
COUNCIL OF THE SHIRE OF MAROOCHY
(Second Defendant) Second Respondent
REASONS FOR JUDGMENT - PINCUS JA
Judgment delivered 16 July 1999
1 I have read the reasons of Thomas JA in which the character of this dispute is explained.
The essential question is whether the payment-in provisions contained in s 11 of the
Subcontractors' Charges Act 1974, correctly construed, mean that the contractor is entitled to
the surplus of money paid in, after the subcontractor's claim is satisfied. The Act does not expressly
say so. But in a helpful argument Mr Keim gave two principal reasons for concluding that the
surplus must go to the appellant.
2 The first reason given was that if the Court holds that a payment in under s 11 is revocable,
where the payer alleges that it was not truly liable in the sum paid in, an important purpose of the
statute is defeated. It was pointed out that the subcontractor's charge attaches to the money in
court, which charge should not be held defeasible by a change in the state of accounts between the
principal and head contractor. The second reason was that under s 11(6) the payment discharges
the payer in respect of liability to the head contractor under the general law.
3 For the sake of simplicity, I shall discuss the questions raised on the basis that the parties
involved are the principal, the head contractor and a subcontractor; the Act deals with other
relationships as well. As to the first reason, I agree that it would seem inconsistent with the tenor
and purpose of the Act to hold that money paid in under s 11 may, as against the claimant
subcontractor, be withdrawn on account of supervening circumstances. The proper construction
of s 11(6) is that, to the extent of the money paid in by the principal, the liability which might
otherwise attach to it under s 11(2) is negatived. One would expect that the circumstances in which
the money paid in could be ordered to be paid out in such a way as to defeat a subcontractor's
claim would be extremely limited and would not include the occurrence of circumstances after the
making of the payment in, giving rise to a new claim by the principal against the head contractor.
But it does not follow that the court would be similarly hampered, in ordering payment out to the
principal, where (as here) there is no question of defeating the subcontractor's charge.
4 As to the second reason, I agree with Mr Keim's contention that s 11(6) gives the principal
a discharge, to the extent of the amount paid in, of its liability to the head contractor. This must be
so because, if there were no such discharge, then the payment in would be no answer to an action
by the head contractor against the employer to recover an amount equal to the sum paid in. The use of the word "discharge" does not encourage the thought that Parliament intended a mere
suspension of the principal's liability to the head contractor; it suggests finality. Although a statutory
reference to discharging a liability is not necessarily "limited to absolute and permanent discharges
of liability" (Hamilton v Commonwealth Bank of Australia (1992) 9 ACSR 90 at 123), one
would not ordinarily read a statute which has the effect of making a payment, made by a debtor to
a person other than the creditor, a discharge of liability as intending that the discharge could be
undone at the instance of the payer. But there are countervailing considerations.
5 A purpose of s 11 is to give the principal a choice, where notice of claim of charge is given.
It can either retain or pay in. An advantage of the latter course is that, at least if the payment in is
held to be of the proper amount, the payer is protected against costs. When referring to the "proper
amount" I have in mind the amount due to the head contractor from time to time; I do not read the
words "or is to become" in s 11(1) as requiring a principal to anticipate the extent of future liability
to the head contractor. That is, the obligation to retain applies to sums due by the principal as and
when they become due. If a sum is retained under s 11(1) then under that provision the court may
direct "to whom and in what manner" it is to be paid; this entitles the court to dispose of the notional
or actual fund retained. There is nothing in that language to suggest that the court's power to direct
is so limited that it must order any surplus (in excess of the amount necessary to satisfy the
subcontractor's claim) to be paid to the head contractor; the natural interpretation of s 11(1) is that
the surplus is to be paid in accordance with the then legal entitlement of the head contractor,
whatever may have been its entitlement at the time of the retention. Acceptance of that view
supports the giving of a similar interpretation to s 11(7), one entitling the court to order payment out
in accordance with the true state of accounts between the parties at the time of the order. And
looking at the matter more broadly, it would be surprising if the statute required the court to order
payment out to a party who is not, at the time of the order, entitled to that sum; on Mr Keim's
argument, the court would be obliged to order payment out to the head contractor even if it were
clear beyond doubt that to do so would be inconsistent with the then rights of the parties, under the
general law.
6 Here it is impossible for the court to tell what is the true state of the accounts between the parties. This is so because of the employer's large claim for damages (not argued to be made in bad faith) which it asserts can be set off against the head contractor's entitlement. In my opinion to
decline to order payment out of a sum which the court could not presently be satisfied was properly
due to the head contractor was not a wrong exercise of discretion. This is so, in summary, because
the court is entitled to give consideration, in exercising its power to order payment to the head
contractor, to events occurring after the payment-in which are alleged to have reduced or eliminated
the debt due by the payer.
7 For these reasons, I agree that the appeal should be dismissed with costs.
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No. 3503 of 1998
Brisbane
Before de Jersey CJ
Pincus JA
Thomas JA[Romtra P/L v Goodacre & Maroochy SC]
BETWEEN:
ROMTRA PTY LTD (ACN 007 155 571)
(RECEIVER AND MANAGER APPOINTED)
(First Defendant) Appellant
AND:
ALLEN GOODACRE and SUSAN GOODACRE
(Plaintiffs) First Respondents
AND:
COUNCIL OF THE SHIRE OF MAROOCHY
(Second Defendant) Second Respondent
REASONS FOR JUDGMENT - THOMAS JA
Judgment delivered 16 July 1999
1 This case concerns the disposition of monies paid into the District Court pursuant to a notice
of claim of charge given by a subcontractor. The relevant persons involved are the employer, the
contractor and the subcontractor. There was no intermediate contract or interest. After receiving
the notice of claim of charge from the subcontractor the employer paid $179,197.19 into court. The subcontractor obtained a court order for payment out of that sum of $109,000.00 which it
accepted as its full entitlement. There remains a dispute between the contractor (the appellant) and
the employer (the second respondent), each claiming to be entitled to money from the other. The
contractor unsuccessfully applied to a District Court judge for an order that the balance of the
monies paid into court be paid out to it. It now appeals against the refusal of that application.
2 By 6 September 1996 the subcontractor had given notices of claims of charge to the
employer totalling $179,197.19. The employer paid that sum into court soon after the
commencement of the subcontractor's action against the contractor and the employer claiming that
amount. The employer admitted in its defence that certificates had issued in favour of the contractor
for sums in excess of the amount in issue and that at the time of the giving of the notices such monies
had been payable to the contractor, but claimed that such entitlement was only provisional, and, in
the light of subsequent events including termination of the contract by the employer for breaches by
the contractor, that such provisional entitlements had been nullified. The defence alleged that the
employer on a balance of account was now entitled to money from the contractor. It accordingly
opposed the contractor's application for payment to it of the monies in court.
3 The statutory provisions most relevant to the present matter are contained in s11 of the
Subcontractors' Charges Act 1974, and in particular the following subparagraphs:
"(1)
Where a notice of claim of charge is given pursuant to section 10, the person to whom it is given shall retain, until the court in which the claim is heard directs to whom and in what manner the same is to be paid, a sufficient part of the money that is or is to become payable by the person under the contract to satisfy the claim.
(2)
A person who fails to retain the amount that the person is required to retain shall be personally liable to pay to the subcontractor the amount of the claim not exceeding the amount that the person is required by this section to retain.
... (5)
An employer or superior contractor may, at any time after notice of claim of charge has been given to the employer or superior contractor, pay into court the amount that the employer or superior contractor is required to retain under this section.
(6)
A payment made pursuant to this section shall discharge the employer or superior contractor, as the case may be, of all further liability in respect of the amount paid and of the costs of any proceeding.
(7) Money paid into court under this section shall not be paid out save under
an order of the court ...".
4 Mr Keim, counsel for the contractor, submitted that by paying the money into court the
employer acknowledged that that money was payable to the contractor. He pointed out that if the
notice of claim of charge had not been delivered, the money would have been paid to the contractor
and would have been available to it to use in its ordinary business activities. In his submission the
balance of the money paid into court over and above that to which the subcontractor was actually
entitled now belongs to the contractor and should be paid to it. The employer's payment into court,
on Mr Keim's submission, was a relinquishment of interest in those monies in exchange for the
discharge conferred by s11(5).
5 It is common ground that the subcontractor's charge has been satisfied or discharged, and
that the appeal concerns competing rights between an employer and a contractor. That is not a
subject about which the Act is primarily concerned, but ss11(5), 11(6) and 11(7) give the court a
power to determine when and to whom money that has been paid into court should be paid. The
proper basis for exercise of that power will be considered in due course.
6 The contractor's submission is that the contractor has an entitlement to receive the balance of the money paid into court. It further submitted that from the moment when the employer paid the money into court, the contractor was entitled to it subject only to the charge in favour of the
subcontractor. It contended that the act of paying the money into court was a concession by the
employer that the money was so payable, arguing that if it were otherwise no charge could have
arisen in favour of the subcontractor (s11(1)). The contractor also submitted that its rights remained
unaffected by the occurrence of later events. In short the suggestion is that there is an irrevocable
admission made in favour of the contractor when an employer pays money into court, and that in
view of the advantage obtained by the party paying money into court (see s11(6)), the admission
ought not to be able to be retracted.
7 Payment into court in these circumstances is certainly an admission by conduct that such
money is "money that is or is to become payable by the person under the contract"[1] and by
[1] Section 11(1).
necessary implication, payable to the contractor. The question is whether this is merely an
evidentiary concession which, like all other admissions, is capable of being shown to be incorrect.
8 The general rule is that an admission against interest may be contradicted or explained away by its maker, as it is for the tribunal of fact to determine the question of its truth and the weight to be attached to it[2]. Formal admissions in the course of court process are not so easily retracted, but
[2] Hoad v Swan (1920) 28 CLR 258, 264-265.
even here a formal admission may in a proper case with leave of the court be withdrawn[3].
[3] Hollis v Burton [1892] 3 Ch 226.
9 The money here in court is a surplus fund not subject to any charge. It is difficult to identify
any particular character or purpose in this money once the primary statutory object of the exercise
has been achieved, namely satisfaction of the subcontractor's charge. If it is to be seen as an
overpayment by the employer prima facie it might ask for the return of its own money, and in that
event it would not have to stand in line with other creditors of the contractor if in due course it is
established that the contractor owes money to it. Conversely, if the contractor is entitled to the
money at this stage, it should be paid to it now, and later disputes between the parties will proceed
as they would have proceeded if the money had been paid to it when it was admittedly due. The
fact that the employer might subsequently suffer rateably with other creditors of the contractor in
the event of the contractor's insolvency is not to the point. If the contractor shows a present
entitlement vis a vis the employer, the employer is not to be given an advantage in relation to other
unsecured creditors through the indulgence of the court in preserving a fund for its benefit.
10 In short if either party could show a present entitlement to that fund then it should be given
to that party now. Conversely if neither party can show such an entitlement, it would be a proper
exercise of discretion to keep the money in court, on the footing that it is not yet known which of
these parties will be owed money by the other, and therefore it is convenient to keep the money in
court until the outcome is known. The primary question is one of entitlement[4].
[4] cf Caboolture Park Shopping Centre Pty Ltd v White Industries (Qld) Pty Ltd (1989) 90 ALR 589, 592-593; Hydronic Industries Pty Ltd (In Liq) v Taylor [1992] 2 Qd R 116, (1991) 5 ACSR 202.
11 The difficulty in the present case arises from the possibility of different entitlements emerging
as between these parties at different times. The contract is a lump sum building contract with
provision for progress payments, and, prior to the time of payment of money into court by the
employer, the contractor was entitled through the issuance of appropriate certificates to payment
of a greater amount than the sums in respect of which the subcontractor had given notices of claims
of charge. Indeed amounts were specifically kept back by the employer for this purpose after the
employer received the subcontractor's notices. After the payment of these amounts into court,
claims have been made by the employer of damages of approximately $200,000.00 by reason of
breaches of contract and the termination by the employer of the contract on 2 May 1997 for the
contractor's breach. The employer has purported to set off such damages against any entitlement
under the progress certificates and further contends that in the light of subsequent events the provisional entitlement to payment has disappeared by reason of the non-completion of the lump
sum contract.
12 It can thus be seen that arguable issues exist between these two parties and that it is
impossible at this stage to tell what the ultimate entitlements may be. At the same time, on the
undisputed evidence the contractor was entitled to receive the money at the time when it was paid
into court.
13 It becomes necessary then to examine these facts in the light of the Subcontractors'
Charges Act.
14 Upon receipt of a notice of claim of charge from the subcontractor, an employer may have
to make a difficult judgment not only with respect to what is then payable to the contractor but what
will become payable to a contractor. That is not a promising start for a submission that the act of
payment of money into court amounts to an irrevocable concession that money is or will become
payable to the contractor. Further, the employer will usually have no real knowledge whether the
subcontractor's claim against the contractor is overstated or even viable. The obvious intent of the
legislation is to require that money be retained by the employer or superior contractor so that it does
not reach the hands of the contractor by whom the money is payable to the subcontractor. This is
the initial means of securing of the subcontractor's position while entitlements are determined. The
Act is drawn to impose strict time limits to the end that quick determination of claims will occur so
that claimants will not be held out of their entitlements for an undue period. However the intended
beneficiaries of the legislation are subcontractors, the object being that they will not be hurt by
insolvency further up the line.
15 The primary position, protection of the subcontractor, has been achieved in the present case
and there remains a dispute between the employer and the contractor as to the balance of apayment that, in hindsight, can be seen to have been excessive. It is true that to the extent of the
excess such monies should have been paid to the contractor by that time anyway, but the fact is that
they were not. I can find nothing directly or indirectly in the Act which gives to the contractor in this
situation an entitlement to the balance, or which deprives an over-paying employer from reasserting
a claim to excess monies of which the court has become the custodian.
16 In my view the position of the contractor can only be maintained if the initial payment is
regarded as an irrevocable concession that those monies belong to the contractor subject only to
the charge in favour of the subcontractor. Some support might be found for that submission if
s11(6) is regarded as conferring a total discharge in favour of the employer in respect of claims
against it by the contractor or the subcontractor. However that subsection does not say so
expressly. It is limited to a discharge "of all further liability in respect of the amount paid and the
costs of any proceeding". While a different view is open, I would interpret the "liability in respect
of the amount paid" to be a reference back to s11(2) which provides that upon failure to retain the
appropriate amount the recipient of the notice "shall be personally liable to pay to the subcontractor
the amount of the claim."
17 In the end, despite the able argument of Mr Keim, I am unable to conclude that the payment
into court was a relinquishment of future rights in relation to that money on the part of the employer.
The initial obligation created by the giving of a notice of claim of charge was an obligation to retain
money, and the act of payment into court was an authorised means of discharging that obligation.
When this is considered along with the fact that a retained fund (and in turn money in court) is provided for the benefit of the subcontractor giving the notice[5], it is difficult to find any particular
[5] Re Radair Pty Ltd [1998] 2 Qd R 539, 540-541, 547.
interest conferred upon the contractor that could be regarded as an entitlement in specie to such
money. In the circumstances I conclude that neither party has a present entitlement to receive this
particular money. The contractor's argument that "if the notice of charge had not been delivered,
the money would have been paid to the contractor and available to it to use in its ordinary business
activities" is not persuasive, because a notice of charge was given, and the money was lawfully
diverted from that consequence.
18 As earlier indicated, in the absence of any sufficient indication of entitlement to the monies
in court, discretionary considerations favour its retention until the final rights of these two parties are
established.
19 The appeal should be dismissed with costs.
0