QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Gollan v Queensland Building and Construction Commission [2022] QCAT 85
PARTIES:
WILLIAM GOLLAN
(applicant)
V
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (respondent)
APPLICATION NO/S:
GAR331-20
MATTER TYPE:
General administrative review matters
DELIVERED ON:
10 March 2022
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member Cranwell
ORDERS:
The application for review filed on 9 September 2020 is dismissed.
CATCHWORDS: PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – whether statutory time limit expired
Queensland Building and Construction Commission Act 1991 (Qld), s 72A
Orlanski v Queensland Building Services Authority [2011] QCAT 35
REPRESENTATION:
Applicant:
Self-represented
Respondent:
C Low
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Chronology
On 30 March 1998, Mr Gollan entered into a contract with Derek Geoffrey Veitch for the construction of a new dwelling.
On 1 September 2003, Mr Gollan noticed defects and made a complaint to the Queensland Building and Construction Commission (‘QBCC’).
On 15 December 2003, the QBCC gave a direction to rectify to Mr Veitch.
On 16 July 2004, the QBCC approved a claim against the statutory insurance scheme. Mr Gollan engaged R A Dibbs & Sons Pty Ltd to complete the rectification work.
On 22 December 2004, Mr Veitch agreed to rectify some of the items.
On 15 December 2006, R A Dibbs & Sons Pty Ltd completed rectification of the remaining defects.
On 20 May 2008, Mr Gollan made a second complaint with the QBCC, claiming that the rectification work carried out by Mr Veitch had failed.
On 10 June 2008, the QBCC gave a second direction to rectify to Mr Veitch.
On 11 October 2008, the QBCC approved a second claim against the statutory insurance scheme. Mr Gollan engaged Stargaze Pty Ltd to complete the rectification work.
On 4 February 2019, Mr Gollan contacted the QBCC call centre about rust and water leaks noticed to the deck.
On 15 June 2020, Mr Gollan sent an email to the QBCC, which was taken to be a third complaint.
On 29 June 2020, the QBCC made a decision not to give a direction to rectify, and further decided that the statutory insurance scheme was unable to provide assistance for any of the complaint items.
On 3 August 2020, the QBCC confirmed its decisions upon internal review.
On 9 September 2020, Mr Gollan purported to seek review of both decision with the Tribunal.
On 2 March 2021, the QBCC lodged applications for miscellaneous matters seeking to have the application for review struck out.
Direction to rectify
Sub-section 72A(4) of the Queensland Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’) provides:
A direction to rectify or remedy cannot be given more than 6 years and 6 months after the building work to which the direction relates was completed or left in an incomplete state unless the tribunal is…
Keep reading for free
Create a free CaseChat account to read Gollan v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QCAT 85
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the three-month period for making a claim could be extended beyond the statutory timeframe and whether the QBCC's decision to reject the claim was justified. Additionally, the court needed to consider whether the statutory insurance scheme could be invoked in light of the significant delay in reporting the defects. The court had to interpret and apply relevant statutory provisions and policies regarding the timeliness of claims and the operation of the statutory insurance scheme.
The court found that the statutory time limit for making a claim could not be extended and had expired well before Mr Gollan made his complaint. Consequently, the QBCC's decision not to approve the claim was upheld. The court emphasised that the statutory insurance scheme provides a limited period for claims, and any delays in reporting defects could not be accommodated. Therefore, the application for review was dismissed. The court also clarified that the issues raised under the Australian Consumer Law were irrelevant to the application for review under the QBCC Act.
The final orders of the court were that the application for review was dismissed, and no direction to rectify or approve a claim under the statutory insurance scheme would be issued. The court did not find it necessary to address the QBCC’s contentions about the review of two decisions in a single application, as it was not pertinent to the outcome of the case.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.