| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST
S ECI 2021 01423
| GOLDWIND AUSTRALIA PTY LTD (ACN 140 108 390) | Plaintiff |
| v | |
| ALE HEAVYLIFT (AUSTRALIA) PTY LTD (ACN 131 060 074) | First Defendant |
| and | |
| JOHN MCMULLAN | Second Defendant |
| and | |
| RIALTO ADJUDICATIONS PTY LTD (ACN 118 640 789) | Third Defendant |
---
JUDGE: | Stynes J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 11 August 2021 |
DATE OF JUDGMENT: | 28 September 2021 |
CASE MAY BE CITED AS: | Goldwind Australia Pty Ltd v ALE Heavylift (Australia) Pty Ltd |
MEDIUM NEUTRAL CITATION: | [2021] VSC 625 |
---
ADMINISTRATIVE LAW — Judicial review — Adjudication conducted under Part 3 Division 2 of the Act — Certiorari sought in relation to an adjudication determination — Whether payment claim, properly characterised, is for construction work done or is an attempt to recoup previously deducted liquidated damages — Building and Construction Industry Security of Payment Act 2002 (Vic) ss 1, 3, 9, 10B, 14 and 23, applied — Seabay Properties Pty Ltd v Galvin Constructions Pty Ltd [2011] VSC 183, applied — Shape Australia Pty Ltd v Nuance Group (Aust) Pty Ltd [2018] VSC 808, distinguished.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Andrew Morrison | Holding Redlich |
| For the Defendant | Chris Young and William Stephenson | HFW Australia |
HER HONOUR:
A Introduction
The plaintiff (the Head Contractor) seeks to have the adjudication determination made by the second defendant (the Adjudicator) on 13 April 2021, corrected on 21 April 2021 (Adjudication Determination), quashed or otherwise declared void. The Adjudication Determination was delivered under the Building and Construction Industry Security of Payment Act 2002 (Vic) (SOP Act).
The issue for determination is whether the Adjudicator erred by taking into account an excluded amount (as defined in s 10B of the SOP Act).
Both parties submitted that the resolution of this proceeding depends on the answer to this question — does the fact that:
(a)the Head Contractor purported to make a deduction in a payment schedule, which was not the subject of an adjudication; and
(b)the first defendant (the Subcontractor), by a later payment claim, made a claim for work done ignoring the earlier deduction,
convert the Subcontractor’s claim from one for construction work done to a claim to recoup the deduction?
The Head Contractor contends that as the Subcontractor failed to challenge the earlier deduction, the subsequent payment claim including that amount must be considered an attempt to recoup the earlier deduction and should not have been taken into account by the Adjudicator.
The Subcontractor contends that the earlier deduction was unlawful and/or lacked a contractual basis and therefore was of no effect. As a consequence, the Subcontractor’s claim should be characterised as one for construction work done that has not been paid for.
For the reasons that follow I have determined that the Adjudicator did not err by characterising the Subcontractor’s claim for $484,100.92 (exclusive of GST), included in PC-13, as a claim for…
Keep reading for free
Create a free CaseChat account to read Goldwind Australia Pty Ltd v Ale Heavylift (Australia) Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] VSC 625
- Decision Date
CaseChat Overview and Summary
The legal issues at hand were whether the adjudication process was conducted in accordance with the statutory framework and whether the determination was correct in characterising Goldwind's claim. The court had to determine if the adjudicator properly assessed the nature of the payment claim and whether the decision adhered to the principles established in relevant case law. Specifically, the court considered the applicability of Seabay Properties Pty Ltd v Galvin Constructions Pty Ltd and Shape Australia Pty Ltd v Nuance Group (Aust) Pty Ltd in interpreting the statutory provisions.
The court concluded that the adjudicator's determination was not erroneous. The reasoning involved a detailed examination of the statutory language and the context in which the payment claim was made. The court found that the adjudicator correctly identified the nature of Goldwind's claim as an attempt to recoup liquidated damages rather than a request for construction work. The court held that the adjudicator's interpretation of the statutory provisions was consistent with the legislative intent and case law. Consequently, the court dismissed Goldwind's application for judicial review.
The final orders of the court were that Goldwind's application for certiorari and other relief was dismissed with costs. The court also ordered Goldwind to pay Ale Heavylift's costs of the proceeding.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi