Medium Neutral Citation: Gloxinia Investments Limited v Low & Anor [2013] NSWSC 1889 Hearing dates: 18 and 20 November 2013 Decision date: 17 December 2013 Jurisdiction: Equity Division Before: Young AJ Decision: Statement of claim dismissed.
Catchwords: CONTRACTS - Termination - Remedies - Where contract allowed vendor to elect between remedies upon termination of contract - Where election made "without prejudice" - Whether election effective
CONTRACTS - Construction - Condition precedent - Where contract required vendor to install certain items prior to completion - Whether clause a condition precedent to completionCases Cited: Alexus Pty Ltd v Pont Holdings Pty Ltd [2000] NSWSC 1171; (2000) 10 BPR 18,371
Beaumont v Dukes (1821) Jac 422; 37 ER 910
Golding v Vella [2001] NSWSC 567; (2001) 10 BPR 18,919
Haynes v Hirst (1927) 27 SR (NSW) 480
Heyman v Darwins Ltd [1942] AC 356
Honner v Ashton (1979) 1 BPR 9,478
Immer (No 145) Pty Ltd v Uniting Church in Australia Property Trust (NSW) [1993] HCA 27; (1993) 182 CLR 26
McNally v Waitzer [1981] 1 NSWLR 294
McTier v Haupt [1992] 1 VR 653
Re Ronim Pty Ltd [1998] QCA 444; [1999] 2 Qd R 172
Sargent v ASL Developments Ltd [1974] HCA 40; (1974) 131 CLR 634
Shevill v Builders Licensing Board (1980) 2 BPR 9,662
Shevill v Builders Licensing Board [1982] HCA 47; (1982) 149 CLR 620
Tiplady v Gold Coast Carlton Pty Ltd [1984] FCA 152; (1984) 3 FCR 426
Tricontinental Corporation Ltd v HDFI Ltd (1990) 21 NSWLR 689
Union Eagle Ltd v Golden Achievement Ltd [1997] AC 515
Williams v Brisco (1882) 22 Ch D 441Texts Cited: Conveyancing Service New South Wales (LexisNexis Butterworths, Looseleaf)
Sir Edward Fry, A Treatise on the Specific Performance of Contracts (Stevens & Sons, 6th edn, 1921)
N C Seddon, R A Bigwood and M P Ellinghouse, Cheshire and Fifoot Law of Contract (LexisNexis Butterworths, 10th Aust edn, 2012)Category: Principal judgment Parties: Gloxinia Investments Limited (Plaintiff)
Vincent Hock Seng Low (First defendant)
Rena Oiu Tsin Low (Second defendant)Representation: Counsel:
A R R Vincent (Plaintiff)
J C Giles/C W Brown (Defendant)
Solicitors:
Norton Rose Australia (Plaintiff)
TressCox Lawyers (Defendants)
File Number(s): 2012/210819 Publication restriction: Nil
Judgment
On 18 October 2010, the plaintiff as vendor and the defendants as purchasers entered into a contract to purchase a unit at Double Bay for $2.1 million. The contract was in the 2005 edition of the standard form with a large number of special conditions.
Clause 15 provided that "The parties must complete by the completion date and, if they do not, a party can serve a notice to complete if that party is otherwise entitled to do so." Special Condition 31.1 provided that "The completion date is 18 November 2010."
The deposit was paid on 18 October 2010 to the vendor's agent. On 19 November 2010 the purchasers issued a Notice to Complete making time of the essence…
Keep reading for free
Create a free CaseChat account to read Gloxinia Investments Limited v Low and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] NSWSC 1889
- Decision Date
CaseChat Overview and Summary
The court examined the contractual language and the circumstances surrounding the election of remedies. It considered whether the "without prejudice" qualification rendered the election ineffective. The court found that the "without prejudice" label did not invalidate the election, as it did not prevent Low from exercising the contractual right to choose between remedies. The court also scrutinised the clause concerning the installation of items prior to completion. It determined that the clause was not a condition precedent but rather a requirement that had to be fulfilled before completion could occur. The court concluded that Low had not breached this requirement by failing to install the items before termination.
The court ordered that Low's election of remedies was valid and effective despite being made "without prejudice." Furthermore, the court ruled that the requirement to install certain items was not a condition precedent to completion but an obligation that had to be met before the contract could be completed. The court provided directions for the next steps in the proceedings, ensuring that the parties understood their respective obligations and rights following the termination of the contract.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.