Medium Neutral Citation: Global Organisation for Divinity v Parramatta City Council [2011] NSWLEC 1027 Hearing dates: 1 and 2 December 2010; 19 - 21 January 2011 Decision date: 24 January 2011 Jurisdiction: Class 1 Before: Moore SC Decision: Appeal upheld subject to submission of revised settled plans and conditions to reflect the terms of this decision.
Catchwords: Acceptability of acoustic shielding fence; heritage conditions; imminence and certainty of draft LEP and of a specific provision of that LEP Legislation Cited: Environmental Planning and Assessment Act 1979
Parramatta Draft Local Environmental Plan 2010
Parramatta Local Environmental Plan 2001
Parramatta Local Environmental Plan 1996 Heritage and Conservation (the Heritage LEP)Cases Cited: Cachia v Manly Council (No 2) [2009] NSWLEC 1107
Mison v Randwick Municipal Council (1991) 23 NSWLR 734
Presrod Pty Ltd v Wollongong City Council [2010] NSWLEC 192 at para 97
Taralga Landscape Guardians Inc v Minister for Planning and RES Southern Cross Pty Ltd [2007]
Terrace Tower Holdings Pty Ltd v Sutherland Shire Council [2003] NSWCA 289Category: Principal judgment Parties: Global Organisation for Divinity (applicant)
Parramatta City Council (respondent)Representation: Mr G McKee (Applicant)
Mr P Marincowitz (Respondent)
McKees Legal Solutions
Sparke Helmore
File Number(s): 10704 of 2010
Judgment
44 Oakes Road, Winston Hills is on the opposite side of Toongabbie Creek to one of the very early agricultural settlement areas of the colony of New South Wales. There is, in the evidence - in both the non-indigenous and indigenous archaeological evidence, a clear indication that it is reasonable to expect that there will be some relics of the early occupation of this area and possibly of contact between the European colonisers and the indigenous inhabitants of the area found on 44 Oakes Road. It is a matter that provides a considerable element of the controversy between the council and the applicant in these proceedings concerning the possible future development of this location.
The applicant proposes to erect, if given development consent, a meditation centre (which would be a place of public worship) and an associated car park on the site. The hours of operation would be 9am to 11am and 6pm to 8pm Monday to Friday and 10am to 1pm and 4pm to 7pm on Saturdays and Sundays.
During the course of the hearing, dealing with issues of conditions of consent, if there were to be a development consent given, it was agreed between the council and the applicant that there should be a short period for opening up of the premises prior to each of these operating periods and that there should be a short period after the operation of the earlier sessions of the operation of the premises as a closing up period but there should be no extension beyond the 8pm Monday to Friday and 7pm Saturday and Sunday for any purposes whatsoever.
The proposed uses of the proposed building include the conducting of various activities such as spiritual education, meditation classes, yoga, group prayers and chanting.…
Keep reading for free
Create a free CaseChat account to read Global Organisation for Divinity v Parramatta City Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] NSWLEC 1027
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court had to address were whether the refusal of the planning application was lawful under the relevant planning legislation, and if the Council's decision was reasonable and justified. The applicants argued that the refusal was arbitrary and did not properly consider the merits of their proposal, while the Council maintained that the decision was in line with the zoning laws and planning policies.
The court found that while the Council had the authority to refuse the application based on zoning, the decision-making process lacked proper consideration of the specific circumstances of the proposed development. The court held that the refusal was not unreasonable, but the process by which it was reached was flawed. Consequently, the appeal was upheld, and the matter was remitted back to the Council for reconsideration, subject to the submission of revised plans and conditions that align with the court's findings.
In light of the above, the appeal was upheld with directions for the Council to reconsider the application in accordance with the court's determination. The applicants were required to submit revised plans and conditions to reflect the terms of the decision before the Council could make a new determination.
Orders
Orders of the court
Appeal upheld subject to submission of revised settled plans and conditions to reflect the terms of this decision.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.