DISTRICT COURT OF QUEENSLAND
CITATION:
Gisley Investments Pty Ltd v Williams [2013] QDC 123
PARTIES:
GISLEY INVESTMENTS PTY LTD
(Plaintiff)
v
MICHAEL LLEWELLYN WILLIAMS
(Defendant)
FILE NO/S:
BD 2543/2010
DIVISION:
PROCEEDING:
Trial
ORIGINATING COURT:
District Court, Brisbane
DELIVERED ON:
21 May 2013.
DELIVERED AT:
Brisbane
HEARING DATES:
2, 3 April 2012; 6, 7, 8 November 2012
JUDGE:
McGill SC DCJ
ORDER:
Judgment that the defendant pay the plaintiff $123,949.43, including interest of $19,702.64.
CATCHWORDS:
BUILDING AND ENGINEERING CONTRACTS – Remuneration – project manager – percentage of construction cost plus percentage of savings over quoted prices – determination of relevant amounts.
Building and Construction Industries Payments Act 2004 s 100(3)(b).
COUNSEL:
T A Houghton for the plaintiff (April)
B Gilbert (Director) for the plaintiff (November)
The defendant appeared in person
SOLICITORS:
Quinn & Scattini Lawyers for the plaintiff (April)
In November the plaintiff was not represented
The defendant was not represented
The plaintiff wanted an industrial building constructed at Loganholme on a parcel of land, and advertised for a project manager.[1] The defendant held a contractor’s licence and has been working in the building industry all of his life, and in particular has experience in constructing tilt panels, concrete wall units which are cast on site and then put in a vertical position so that they function as wall units.[2] Mr Gilbert, who ran the plaintiff, and the defendant met and discussed the plans for the project, and terms for the defendant to manage it.[3] Subsequently the plaintiff sent the defendant an email setting out proposed terms for the management of the project: Exhibit 3. It is common ground that that email was accepted by the defendant, and sets out the contract between the parties. The defendant did manage the construction of the building, although ultimately disputes arose between them and the plaintiff says that the defendant left the work site before everything was properly finished: p 71.
[1]Gilbert p 70; Exhibit 2.
[2]Williams p 32; They are cast flat, then lifted and put into position as wall units. Their casting and erection are shown in the photographs in Exhibit 21. They can also be constructed off site; I have seen such units being brought by truck to a building site.
[3]Williams p 33; Gilbert p 70.
The defendant subsequently made a claim under the Building and Construction Industries Payments Act 2004. That claim was disputed by the plaintiff, and the matter went to adjudication, as a result of which an adjudicator ordered the plaintiff to pay the defendant $127,313.50: Exhibit 4. That sum has been paid (p 36); under the Act the claim which is before me is independent of that decision and payment, except that it is taken into account as a payment made in respect of the project when working out the implications of my findings. The findings and conclusions of the adjudicator are not binding in this proceeding, and are I suspect irrelevant and inadmissible.
The parties are in dispute as to the amount payable by the…
Keep reading for free
Create a free CaseChat account to read Gisley Investments Pty Ltd v Williams and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] QDC 123
- Decision Date
CaseChat Overview and Summary
The court examined the terms of the contract between the parties and found that Williams was entitled to a percentage of the construction costs plus a percentage of any savings over quoted prices. The court found that the plaintiff had failed to provide evidence of all savings over quoted prices and that Williams had provided evidence of savings that had not been accounted for by the plaintiff. The court found that the defendant was entitled to a percentage of these savings and that the total amount owing by Williams to the plaintiff was $123,949.43, including interest.
The court ordered that the defendant pay the plaintiff the amount of $123,949.43, including interest of $19,702.64. The court found that the defendant had breached the terms of their agreement by failing to account for all savings over quoted prices. The court ordered that the defendant pay the plaintiff the amount owing, plus interest, within 28 days of the judgment.
Orders
Orders of the court
Judgment that the defendant pay the plaintiff $123,949.43, including interest of $19,702.64.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.