| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
No. 9132 of 2005
| GEVAH CONSTRUCTIONS PTY LTD (ACN 005 974 596) | Appellant |
| V | |
| GRN AUSTRALIA PTY LTD (ACN 108 435 927) | Respondent |
---
JUDGE: | HARGRAVE J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 25 July 2006 | |
DATE OF JUDGMENT: | 31 July 2006 | |
CASE MAY BE CITED AS: | Gevah Constructions Pty Ltd v GRN Australia Pty Ltd | |
MEDIUM NEUTRAL CITATION: | [2006] VSC 266 | |
---
Appeal – discretionary decision of Victorian Civil and Administrative Tribunal under s. 78 of Victorian Civil and Administrative Tribunal Act 1998 (Vic) – whether pre-conditions for exercise of discretion existed – whether exercise of discretion involved an error of law justiciable on appeal under s. 148(1) of Victorian Civil and Administrative Tribunal Act 1998 (Vic).
---
APPEARANCES: | Counsel | Solicitors |
| For the Appellant | Mr V Ruta | Jack Bock Lawyers |
| For the Respondent | Mr J Brett | Deacons |
HIS HONOUR:
Factual Background to Appeal
The appellant (“Gevah”) is a property developer. The respondent (“GRN”) is a distributor of polystyrene products. In November 2004, GRN agreed to supply, install and render polystyrene sheets on the exterior of 15 home units being constructed by Gevah (“the contract”).
The contract price was calculated by reference to calculations of the total area to be covered by the polystyrene sheets and rendered, including an allowance for wastage. The calculations upon which the contract price was based were made by Gevah. In these circumstances, the contract contained a provision to protect GRN in the event that more polystyrene sheets were required than those specified in the contract. In this respect, the contract provides:
“Variations:
As per Gevah Constructions calculations, the area calculated for the works involved (allowing for waste) is 1150 sqm. Since each 40 mm “M” Grade Polystyrene sheet is 3 m this area is equivalent to 384 sheets.
GRN Wallboards and Gevah Constructions P/L agree that, should extra polystyrene be needed to complete the project, Gevah Constructions to pay $215.70 for each extra sheet (Excluding GST) for the supply and render. This is equivalent to $71.90 per square metre. (Excluding GST).
Additional cartage will be charged at $120.00 per delivery (Excluding GST).”
The 15 units were to be constructed in three stages of five units each. After completion by GRN of its part of stage 2 of the works, it became apparent to GRN that extra polystyrene sheets would be required to complete stage 3. By letter dated 10 March 2005, GRN informed Gevah that it had already used 343 polystyrene sheets in the completion of stages 1 and 2. Accordingly, the 384 polystyrene sheets referred to in the contract would be insufficient to complete stage 3. Gevah was put on notice that extra charges would be made for additional sheets in order to complete stage 3. Specific reference was made in this letter to the term of the contract to which I have referred above.
It appears that there was no response to this letter from GRN to Gevah.…
Keep reading for free
Create a free CaseChat account to read Gevah Constructions Pty Ltd v GRN Australia Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] VSC 266
- Decision Date
CaseChat Overview and Summary
The court considered whether the Tribunal had correctly identified the pre-conditions for exercising its discretion to dismiss the claim and whether the exercise of that discretion involved an error of law. It was necessary to determine if the Tribunal's decision could be subject to judicial review under s. 148(1) of the Act. The court found that the Tribunal had indeed exercised a discretionary power but did not find that any error of law was made in the exercise of that discretion. The Tribunal’s findings were based on a proper application of the relevant legal principles to the evidence presented.
In conclusion, the court upheld the Tribunal’s decision, dismissing Gevah's appeal. The Tribunal was found to have correctly exercised its discretion and no error of law was identified that warranted setting aside the decision. The orders of the Tribunal remained in place, with Gevah's claim for damages against GRN being dismissed.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.