Georges River Council v Stojanovski (No 3)

Case

[2019] NSWLEC 139

30 September 2019

No judgment structure available for this case.

Land and Environment Court


New South Wales

Medium Neutral Citation: Georges River Council v Stojanovski (No 3) [2019] NSWLEC 139
Hearing dates: 6, 22 and 30 August, 2 and 20 September 2019
Date of orders: 30 September 2019
Decision date: 30 September 2019
Jurisdiction:Class 4
Before: Moore J
Decision:

(1) Pursuant to s 98(4)(c) of the Civil Procedure Act 2005, Mr Steven Stojanovski (the First Respondent) is ordered to pay the Applicant’s costs in the gross sum of $23,083.80; and
(2)   The Applicant’s motion that the First Respondent be punished for contempt is otherwise dismissed.

Catchwords: CONTEMPT - carry out development without consent - Class 4 proceedings leading to orders to demolish and remove unauthorised development - orders not complied with - contempt proceedings commenced - First Respondent found guilty of contempt - further compliance orders made requiring First Respondent to demolish and remove material within further period of time - sentencing hearing deferred to permit First Respondent to comply with further order - substituted performance order made in favour of the Applicant - substituted performance order mandated the Applicant to demolish and remove if First Respondent did not do so - First Respondent failed to comply within further period of time - Applicant failed to carry out mandated substituted performance requirement - First Respondent and Applicant both in breach of court orders - sentencing hearing for First Respondent - Applicant seeks order to extend the time for mandated substituted performance - extension granted - no participation by First Respondent in sentencing hearing - First Respondent completes demolition and removal of unauthorised structures - Applicant no longer presses that the First Respondent be punished for contempt - Applicant proposes that, other than as to costs, the Applicant’s contempt motion be dismissed
COSTS - appropriate to order that the First Respondent pay the Applicant’s costs on the ordinary basis up to and including the sentencing hearing together with those of the finalisation hearing - not appropriate to require the First Respondent to pay the costs of the two hearings required to address the failure of the Applicant to carry out the mandated substituted performance order - appropriateness of a gross sum costs order to finalise the proceedings - the First Respondent ordered to pay the Applicant’s costs in the gross sum of $23,083.80.
Legislation Cited: Civil Procedure Act 2005, s 98(4)(c)
Environmental Planning and Assessment Act 1979
Uniform Civil Procedure Rules 2005, r 40.8
Cases Cited: Georges River Council v Stojanovski [2018] NSWLEC 125
Georges River Council v Stojanovski (No 2) [2019] NSWLEC 53
Lismore City Council v Vivian [2016] NSWLEC 108
Category:Principal judgment
Parties: Georges River Council (Applicant)
Steven Stojanovski (First Respondent)
Robert Stojanovski (Second Respondent)
Representation:

Counsel:
Mr N Eastman, barrister (Applicant)
No appearance (First or Second Respondent)

  Solicitors:
Lindsay Taylor Lawyers (Applicant)
File Number(s): 99739 of 2018
Publication restriction: No

TABLE OF CONTENTS

Introduction

The proceedings before Pepper J

The contempt proceedings before Sheahan J

The sentencing proceedings

Introduction

Partial performance by the First Respondent

The Applicant’s failure to fulfil order (4) made by Sheahan J

Rectifying the Applicant’s position

The hearing on 6 August 2019

The hearing on 22 August 2019

The hearing on 30 August 2019

Finalising the proceedings

Introduction

The hearing on 20 September 2019

Costs

Orders

JUDGMENT

Introduction

  1. On 24 March 2018, Georges River Council (the Applicant) commenced Class 4 civil enforcement proceedings against Mr Steven Stojanovski (the First Respondent) and Mr Robert Stojanovski (the Second Respondent) concerning development at a property at Part Lot 68 DP2997, 47 Jersey Avenue, Mortdale and Lot 68 DP 2997, 34 Milsop Place, Mortdale (the site), where development had been undertaken without development consent and where development consent, pursuant to the Environmental Planning and Assessment Act 1979, was required.

The proceedings before Pepper J

  1. Those proceedings were dealt with by Pepper J on 21 August 2018 (Georges River Council v Stojanovski [2018] NSWLEC 125). Although the First and Second Respondents were not present during the course of the hearing before her Honour, they were legally represented. On that occasion, her Honour was satisfied that the Applicant had established an appropriate case for relief and made the following declaration and orders:

(1) a declaration that the First Respondent has carried out or permitted the carrying out of development on Part Lot 68 DP2997, 47 Jersey Avenue, Mortdale and Lot 68 DP 2997, 34 Milsop Place, Mortdale (“the property”) being the excavation of the Property, construction of a concrete slab, and construction of two sheds (“sheds”) being used for the purpose of a habitable dwelling, on land zoned R2 - Low Density Residential, without the requisite development consent as required by Hurstville Local Environmental Plan 2012, such development being contrary to s 4.2 of the Environmental Planning and Assessment Act 1979 (“EPAA”);

(2) an order, pursuant to s 9.46 of the EPAA, that the First Respondent, by himself, his servants or agents, be restrained from using the sheds on the property for the purpose of a habitable dwelling unless and until development consent has been obtained for that use;

(3) an order, pursuant to s 9.46 of the EPAA, that within 28 days of the making of this order, the First Respondent must demolish all unlawfully erected structures, including the sheds and the concrete slab on the property;

(4)   that the First Respondent pay the Applicant’s costs of these proceedings; and

(5)   all exhibits in this matter are to be returned to the parties.

  1. As can be seen, these orders imposed obligations on only the First Respondent (but not the Second Respondent) to demolish the illegal works and to remove the demolished materials from the site. The orders established the time within which this was to have occurred.

  2. The First Respondent did not meet the obligations that were imposed by her Honour’s orders to demolish the works and remove the material from the site within the required time.

The contempt proceedings before Sheahan J

  1. On 30 October 2018, the Applicant commenced contempt proceedings against the First Respondent. These proceedings were heard by Sheahan J on 15 April 2019. His Honour was satisfied that the First Respondent was guilty of contempt. His Honour made a series of orders, in the terms sought by the Applicant (a matter to which it will be necessary to return), and published short reasons for doing so (Georges River Council v Stojanovski (No 2) [2019] NSWLEC 53).

  2. His Honour’s orders were in the following terms:

1   The First Respondent having continued to use the two sheds (Sheds), which were erected on the land described as Part Lot 68 DP 2997 known as 47 Jersey Avenue, Mortdale (Property) without development consent, for the purpose of a habitable dwelling, in contravention of Order 2 as made by this Court in proceedings 2018/99739 on 21 August 2018, is guilty of contempt of Court.

2   The First Respondent having failed to demolish all unlawfully erected structures on the Property (including the concrete slab and the Sheds) within 28 days of the making of Order 3 as made by this Court in proceedings 2018/99739 on 21 August 2018, is guilty of contempt of Court.

3   That the First Respondent, within 28 days of the making of this order, must demolish all unlawfully erected structures on the Property including the Sheds and the concrete slab.

4   If all unlawfully erected structures on the Property have not been demolished by the end of the period specified in Order (3) above, the Applicant is directed, within 21 days of the end of that period, to enter the Property and, carry out the demolition of all unlawfully erected structures on the Property including the sheds and the concrete slabs and remove and lawfully dispose of the unlawfully erected structures.

5   The First Respondent is to pay the Applicant's costs incurred in complying with Order (4).

6   The First Respondent is to pay the Applicant's costs of this Notice of Motion on an indemnity basis.

7   The sentencing hearing in respect of the 1st Respondent is stood over to the List Judge list on Friday 10 May 2019 for directions.

  1. It is to be noted that, as his Honour recorded in [14] to [17], the First Respondent was not present during the contempt hearing nor was he legally represented. However, his Honour was satisfied that the Applicant's legal representatives had taken appropriate and effective steps to ensure that that hearing had been brought to the First Respondent's attention.

  2. In the orders made by Sheahan J (as can be seen from their terms set out above), his Honour provided further time for the First Respondent to satisfy the requirement to demolish the works and remove the materials from the site and deferred, to a further hearing, sentencing of the First Respondent for the contempt for which is Honour had made the necessary finding of guilt.

The sentencing proceedings

Introduction

  1. The contempt sentencing hearing was subsequently set down for 6 August 2019 and the matter was allocated to me for hearing.

Partial performance by the First Respondent

  1. Affidavit evidence on behalf of the Applicant at the commencement of the sentencing hearing showed that the First Respondent had significantly (but not completely) complied with the demolition and removal order made by Sheahan J.

The Applicant’s failure to fulfil order (4) made by Sheahan J

  1. In Sheahan J's reasons for decision in agreeing to make the orders noted above, his Honour commented that he was making a substituted performance order pursuant to r 40.8 of the Uniform Civil Procedure Rules 2005. His Honour noted that doing so was consistent with past practice of the Court in such circumstances. He noted, as an example, the relevant order of Pain J in Lismore City Council v Vivian [2016] NSWLEC 108.

  2. However, in my pre-trial preparation for the hearing on 6 August 2019, it seemed to me that there was one anomalous and distinctly different element of the substituted performance order made by Sheahan J on 15 April 2019 when compared with other substituted performance orders that have been made by this Court (including the one in Lismore to which his Honour referred).

  3. Each of the other substituted performance orders, of which I am aware, gave the relevant authority the option of entering into the relevant site and carrying out the works that were the subject of the Court's orders in each instance where the person burdened with responsibility for the carrying out of those requirements had failed to do so. In each and every instance, however, exercising the right for substituted performance was at the discretion of the relevant authority.

  4. In these proceedings, for the purposes of understanding the following discussion, it is appropriate to repeat, with emphasis added, the terms of Sheahan J’s order (4) made on 15 April 2019:

4   If all unlawfully erected structures on the Property have not been demolished by the end of the period specified in Order (3) above, the Applicant is directed, within 21 days of the end of that period, to enter the Property and, carry out the demolition of all unlawfully erected structures on the Property including the sheds and the concrete slabs and remove and lawfully dispose of the unlawfully erected structures.

  1. As can be seen from the terms of this order, the Applicant was not given the option of electing to carry out substituted performance if the First Respondent did not carry out the mandated demolition and removal of the demolished material within 28 days of the date of his Honour's orders, but order (4) mandated that the Applicant carry out substituted performance and gave a further period of 21 days within which the Applicant was required to comply with that order.

  2. The Applicant, itself, did not do so and had not done so when the matter came before me on 6 August 2019. It seems to me that, as a consequence, the Applicant itself was also in contempt by this failure.

  3. At this point, I should repeat that I have carefully checked the terms of the orders sought by the Applicant in the Notice of Motion that initiated the contempt proceedings before Sheahan J. The orders made by his Honour faithfully replicated the orders that had been sought by the Applicant. The consequence of this is that the Applicant had no excuse for failing to undertake substituted performance, triggered by the First Respondent's failure, by 14 May 2019, to demolish all the works and remove the material. The Applicant was required to carry out the substituted performance by 5 June 2019 and did not do so.

Rectifying the Applicant’s position

The hearing on 6 August 2019

  1. At the hearing before me on 6 August 2019, I raised the position of the Applicant's breach of Sheahan J's orders with Mr Eastman, counsel appearing for the Applicant.

  2. I here interpolate that the First Respondent was not present at this hearing, but that I am satisfied, on the basis of the affidavit evidence before me on that occasion, that that hearing had been drawn to his attention. I had had the matter called outside the Court, with no appearance by the First Respondent or any legal representative on his behalf.

  3. Mr Eastman sought an adjournment to enable the Applicant to consider how it might wish to respond to its own breach of Sheahan J's orders. I indicated, on that occasion, that I felt that the position that now arose, where the First Respondent and the Applicant were both in breach of Sheahan J's orders, that this would necessarily act to moderate any penalty which might be imposed on the First Respondent for his failure to demolish and remove materials by the expiry of the 28th day after the making of Sheahan J's orders.

  4. I granted the Applicant an adjournment until 22 August 2019 to consider the position that now applied as a consequence of the unusual and mandatory nature contained in order (4) of the orders made by Sheahan J. I directed that the adjourned proceedings also be drawn to the attention of the First Respondent (including the date of the proposed resumed hearing).

The hearing on 22 August 2019

  1. On 22 August 2019, Mr Eastman advised me that the Applicant proposed to seek that I make an amendment to order (4) made by Sheahan J to extend the time by which the Applicant was obliged to comply with its obligations. That extension was to be sought until 30 November 2019.

  2. Affidavit evidence on behalf of the Applicant at this hearing established that the First Respondent had had appropriate information provided to him about the ongoing nature of the proceedings and of the date of this adjourned hearing.

  3. At Mr Eastman's request, I adjourned the hearing for a further period of time to enable the filing and serving of the Notice of Motion seeking the extension of time for the Applicant for compliance. I directed that service be effected on the First Respondent in the fashion which had been the methods of communication with him in the past.

The hearing on 30 August 2019

  1. When the further hearing took place on 30 August 2019, the First Respondent did not appear and was not legally represented. The matter was called outside the courtroom. Affidavit evidence on behalf of the Applicant established that all relevant documents, including the Notice of Motion and notice of this resumed hearing, had been served on the First Respondent.

  2. It is to be observed that, although the First Respondent had (as earlier noted) partially performed what was required of him as a consequence of Sheahan J's order (3), no further progress appeared to have been made since the earlier observations of the state of the site set out in earlier affidavits on behalf the Applicant. This was established on this occasion by further affidavit evidence on behalf of the Applicant.

  3. I was satisfied, under the circumstances, that it was appropriate to grant the Applicant the extension of time which it now sought for it to comply with order (4) made by Sheahan J.

Finalising the proceedings

Introduction

  1. The granting of the extension to the Applicant did not have the effect of altering the fact that, between 6 June and the date of the making, on 30 August 2019, of the order for extension of time, the Applicant was, itself, in breach of order (4) made by Sheahan J.

  2. It is to be observed that, although the position of the Applicant being in contempt by its breach of order (4) of Sheahan J's orders still remained to be addressed, it was appropriate that I reserved my decision on sentencing of the First Respondent for his contempt but that I not make any determination on what penalty (if any) might be appropriate to be imposed until after the Applicant’s breaching position had been addressed. On 30 August 2019, I therefore stood the matter over for a further short hearing on 20 September 2019.

The hearing on 20 September 2019

  1. When the matter came before me on 20 September 2019, Mr Eastman read an affidavit from his instructing solicitor that deposed as to the present state of the site. In short, the works which had been mandated by the orders made by Pepper and Sheahan JJ have now been completed. As a result, the First Respondent’s obligations had been fulfilled, as all the unpermitted development had been removed from the site. This had the effect of the First Respondent having purged his contempt.

  2. This outcome also had the effect of extinguishing the continuing obligation which had fallen on the Applicant as a consequence of order (4) of the orders made by Sheahan J in May 2019 and as extended by me.

  3. On this occasion, Mr Eastman advised me that the Applicant no longer sought that the First Respondent be punished for his failure to meet the first timetable for removal of the unapproved structures, as had been imposed by Pepper J, nor for the First Respondent’s failure to meet the further and extended timetable, which had been imposed by Sheahan J in May of this year.

  4. As a consequence, the element of the Applicant’s contempt motion seeking to have the First Respondent punished for contempt is appropriate to be dismissed.

Costs

  1. Although not pursuing the question of punishment for the First Respondent for his contempt, Mr Eastman did indicate that the Applicant sought its costs of the proceedings, but that those costs were only sought on the ordinary basis.

  2. Although the Applicant did seek the entirety its costs since the hearing before Sheahan J (as Sheahan J had made a costs order addressing the Applicant’s costs up to and including the hearing before him, those earlier costs had been dealt with), Mr Eastman acknowledged that I might consider that some of the costs during the intervening period might not be appropriate to be ordered against the First Respondent because of the unusual nature of order (4) made by Sheahan J, at the Applicant's request, and the Applicant's subsequent failure to give effect to its mandated obligation arising under that order.

  3. I indicated to Mr Eastman that I considered that it would be desirable to finalise the matter by making a gross sum costs order as is permitted by s 98(4)(c) of the Civil Procedure Act 2005, rather than making an as “agreed or assessed” order because an order in that form risked further prolonging disputation between the Applicant and the First Respondent.

  4. I requested Mr Eastman to have instructions sought on this with a view to providing to me, if such a process was accepted by the Applicant as appropriate, gross sum alternatives. Both were to be provided on a conventionally discounted basis (with me indicating that 70% of actual costs would be acceptable as a basis to calculate any gross sum to be ordered).

  5. The first gross sum amount was to encompass the entirety of the proceedings after the hearing before, and orders of, Sheahan J, whilst the second was to exclude those elements of subsequent hearings necessary to address and rectify the Applicant’s own breach of order (4) made by Sheahan J.

  1. I indicated that, once I had the indication as to whether or not the Applicant would agree to a gross sum order basis to dispose of the costs issue, I would deal with the question of quantum in this decision.

  2. If the Applicant did not agree to a gross sum order, I would simply make an as agreed or assessed costs order after determining what should be the scope covered by such an order.

  3. On 26 September 2019, the Applicant’s solicitor advised my Associate that a gross sum costs order was acceptable to the Applicant and provided details of the alternative sums (discounted to 70% of the actual costs) that I had requested.

  4. I am satisfied that it is appropriate to make a gross sum order for the lower amount - that being the amount which excludes those subsequent hearings necessary to address and rectify the Applicant’s own breach of order (4) made by Sheahan J. The costs order will therefore be in the gross sum of $23,083.80.

Orders

  1. The orders of the Court are:

  1. Pursuant to s 98(4)(c) of the Civil Procedure Act 2005, Mr Steven Stojanovski (the First Respondent) is ordered to pay the Applicant’s costs in the gross sum of $23,083.80; and

  2. The Applicant’s motion that the First Respondent be punished for contempt is otherwise dismissed.

**********

Decision last updated: 01 October 2019

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

3

Statutory Material Cited

3

Lismore City Council v Vivian [2016] NSWLEC 108