Gedoun Constructions Pty Ltd v Queensland Building and Construction Commission

Link copied
Case Copied 9 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Gedoun Constructions Pty Ltd v Queensland Building and Construction Commission & Anor [2021] QCAT 142

PARTIES: GEDOUN CONSTRUCTIONS PTY LTD

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

MARK ELLIOT AGIUS

(respondents)

APPLICATION NO/S:

GAR194-20

MATTER TYPE:

General administrative review matters

DELIVERED ON:

11 May 2021

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Member Paratz AM

ORDERS:

1.   Gedoun Constructions Pty Ltd atf Gedoun Development Unit Trust is removed as the applicant in the proceeding.

2.   Gedoun Constructions Pty Ltd is joined as the applicant in the proceeding.

3.   The Application for miscellaneous matters filed on 24 February 2021 by Mark Elliot Agius, to dismiss the Application to review a decision filed by Gedoun Constructions Pty Ltd atf  Gedoun Development Unit Trust on 8 June 2020, is dismissed.

4.   The matter is to be set for a Directions Hearing at 11:30am on 3 June 2021 together with GAR140-20, GAR193-20, GAR373-20 and GAR392-20.

CATCHWORDS:

PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - JOINDER OF CAUSES OF ACTION AND OF PARTIES - PARTIES - GENERALLY -  where a company as trustee was named as the applicant to a review proceeding – where the trust did not hold a Queensland builder’s licence – whether the trust should be removed as the applicant – whether the company holding a Queensland builder’s licence should be joined as the applicant - whether an applicant can be effectively substituted under the Queensland Civil and Administrative Tribunal Act 2009 (Qld) – whether the proceeding should be dismissed

Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 28(1), s 42(1)(a), s 42(2)(b), s 42(3), s 47(1)

Uniform Civil Procedure Rules 1999 (Qld) r 69

Ward & Anor v Williams [2019] QCAT 136

APPEARANCES & REPRESENTATION:

Applicant:

Connolly Suthers, Lawyers

Respondent:

QBCC: Norton Rose Fulbright

Mr Agius: Self-represented

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)

REASONS FOR DECISION

  1. Gedoun Constructions Pty Ltd (‘the builder’) contracted to build a residential home for Mark Elliot Agius (‘the owner’) in Townsville, Queensland.

  2. The Queensland Building and Construction Commission (‘the QBCC’) made a decision on 26 May 2020 that the builder was responsible for work at the property and issued a Direction to Rectify and/or Complete no. 0106161 to the builder on 28 May 2020.

  3. Gedoun Constructions Pty Ltd atf Gedoun Development Unit Trust (‘the Trust’) filed an Application to Review a Decision in relation to the matter on 8 June 2020.

  4. The owner filed an Application for Miscellaneous Matters on 3 November 2020 (‘the application to dismiss’) applying to dismiss the application to review a decision filed by the builder.

  5. I gave directions on 8 February 2021 that the application to dismiss would be determined on the papers, after receipt of submissions. This is the decision in relation to that application.

Submissions of the owner

  1. The owner filed submissions attached as Appendix 1 to his application to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Gedoun Constructions Pty Ltd v Queensland Building and Const... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QCAT 142
Decision Date

CaseChat Overview and Summary

The Queensland Civil and Administrative Tribunal was asked to decide whether Gedoun Constructions Pty Ltd atf Gedoun Development Unit Trust should be removed as the applicant in an application to review a decision of the Queensland Building and Construction Commission, and whether Gedoun Constructions Pty Ltd should be joined as the applicant. The Tribunal was also asked to determine whether an application to dismiss the application to review should be granted. The matter was determined on the papers. The court found that Gedoun Constructions Pty Ltd atf Gedoun Development Unit Trust should be removed as the applicant in the proceeding, and that Gedoun Constructions Pty Ltd should be joined as the applicant in the proceeding. The court also found that the application to dismiss the application to review should be dismissed. The court found that the identity of the applicant could be remedied by the tribunal making orders effectively substituting the company ‘Gedoun Constructions Pty Ltd’ as the applicant. The effect of substitution could be achieved by removing the existing applicant and joining the company as the applicant. The court found that substitution of the applicant would not cause any delay to the proceeding, but would remove the question of identity as an issue and enable the proceeding to concentrate on the merits of the review itself. The court also found that a party should not be summarily deprived of its right to review a decision simply because of a procedural error, if none of the elements required to justify dismissing an application are substantiated. The court found that whilst the owner alleged that the bringing of the review application by the builder was an abuse of process, and designed to delay rectification of defects to his home, it was not established that this was the intent or effect of the review application. The court found that there was no suggestion that the company in its own right would be prejudiced by being named as an applicant in the proceeding. The court found that the tribunal has discretion as to the procedure for a proceeding, and may make an order joining a person as a party to a proceeding if it considers that the person should be bound by or have the benefit of a decision of the tribunal in the proceeding; and may order that a party be removed from a proceeding if it considers that the party is not a proper or necessary party to the proceeding, whether or not the party was one originally. Such an order may be made by the tribunal on its own initiative. The court found that the tribunal may dismiss an application if it considers that it is frivolous, vexatious or misconceived; or lacking in substance; or otherwise an abuse of process. The court found that a party should not be summarily deprived of its right to review a decision simply because of a procedural error, if none of the elements required to justify dismissing an application are substantiated. The court found that whilst the owner alleged that the bringing of the review application by the builder was an abuse of process, and designed to delay rectification of defects to his home, it was not established that this was the intent or effect of the review application. The court found that there was no suggestion that the company in its own right would be prejudiced by being named as an applicant in the proceeding. The court found that the tribunal has discretion as to the procedure for a proceeding, and may make an order joining a person as a party to a proceeding if it considers that the person should be bound by or have the benefit of a decision of the tribunal in the proceeding; and may order that a party be removed from a proceeding if it considers that the party is not a proper or necessary party to the proceeding, whether or not the party was one originally. Such an order may be made by the tribunal on its own initiative. The court found that the tribunal may dismiss an application if it considers that it is frivolous, vexatious or misconceived; or lacking in substance; or otherwise an abuse of process. The court found that a party should not be summarily deprived of its right to review a decision simply because of a procedural error, if none of the elements required to justify dismissing an application are substantiated. The court found that whilst the owner alleged that the bringing of the review application by the builder was an abuse of process, and designed to delay rectification of defects to his home, it was not established that this was the intent or effect of the review application. The court found that there was no suggestion that the company in its own right would be prejudiced by being named as an applicant in the proceeding.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.