QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Gebremariam & Anor v Queensland Building and Construction Commission [2024] QCAT 411
PARTIES:
SOFIA HAILE GEBREMARIAM (applicant)
YISHAK ABRAHAM (applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (respondent)
APPLICATION NO/S:
GAR685-23
MATTER TYPE:
General administrative review matters
DELIVERED ON:
16 September 2024
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member Lumb
ORDERS:
1. The Application to dismiss or strike out a proceeding filed by the respondent is granted.
2. The Application to review a decision filed on 22 September 2023 is dismissed pursuant to s 47 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
CATCHWORDS:
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – ENDING PROCEEDINGS EARLY – SUMMARY DISPOSAL – general administrative review – where applicants entered into a contract with a builder for the construction of a dwelling – where builder went into liquidation during the course of the building work – where applicants submitted a claim for assistance under the Queensland Home Warranty Scheme for non-completion of work – where the respondent notified applicants that the contract had been validly terminated – where scope of works approved – where respondent engaged external claims consultant to produce a cost assessment – where applicants engaged third-party builder to perform completion work without prior written approval of the respondent – whether applicants lost their right to recover under the scheme by virtue of s 64 of Schedule 6 of the Queensland Building and Construction Commission Regulation 2018 (Qld) – whether application to review should be dismissed or struck out under s 47 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
Queensland Building and Construction Commission Act 1991 (Qld), s 67Y, s 72
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 20, s 47
Queensland Building and Construction Commission Regulation 2018 (Qld), Schedule 6, s 1, s 30, s 31, s 64Cronin v Queensland Building and Construction Commission [2019] QCAT 14
Perry v Queensland Building and Construction Commission (no. 2) [2023] QCAT 286University of the Sunshine Coast v Hickson-Jamieson [2022] QCATA 54
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Introduction
On 15 December 2021, the Applicants entered into a contract with PDH QLD Pty Ltd (‘the Builder’) for the construction of a dwelling in Brisbane in the State of Queensland (‘the property’).
On 30 March 2023, the Builder wrote to the Applicants asserting that the works were complete up to and including the ‘Fixing Stage’.
On 31 March 2023, Grant Thornton Australia Limited informed the Applicants that the Builder had entered into liquidation.
On 10 April 2023, the Applicants submitted a Non-Completion Claim Form (‘the Claim’) with the Queensland Building and Construction Commission (‘the QBCC’) seeking assistance under the Queensland Home Warranty Scheme (‘the Scheme’).
On 2 June 2023, the QBCC notified the Applicants that the contract had been validly terminated and that…
Keep reading for free
Create a free CaseChat account to read Gebremariam v Queensland Building and Construction Commissio... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] QCAT 411
- Decision Date
CaseChat Overview and Summary
The legal issues that the court was required to decide were whether the applicants rectified the work within the meaning of section 64(1) of Schedule 6 and, if so, whether they did so without the prior written approval of the QBCC. The court found that the applicants did indeed rectify the work within the meaning of section 64(1) and that they did so without the prior written approval of the QBCC. The QBCC’s notification clearly stated that any work done without written approval could result in the loss of the right to claim under the scheme. Despite this, the applicants proceeded with the completion work through another builder due to extensive delays and financial constraints. The applicants argued that the QBCC had already approved the scope of works and had commissioned reports documenting the remaining works, which provided expert cost estimates.
The court granted the respondent's application to dismiss or strike out the proceeding filed by the applicants. The application to review a decision filed on 22 September 2023 was dismissed pursuant to section 47 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld). The court found that the applicants had lost their right to recover under the scheme by virtue of section 64 of Schedule 6 of the Queensland Building and Construction Commission Regulation 2018 (Qld), as they had not obtained the required prior written approval from the QBCC before engaging another builder to complete the work.
Orders
Orders of the court
1. The Application to dismiss or strike out a proceeding filed by the respondent is granted.
2. The Application to review a decision filed on 22 September 2023 is dismissed pursuant to s 47 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Further, as submitted by the QBCC, the terms of s 64 do not provide any discretion to allow a claim for assistance if work described in the section has been done without prior written approval of the QBCC.[11][11]Cronin v Queensland Building and Construction Commission [2019] QCAT 14, [54]-[55] (Member Gordon); Perry v Queensland Building and Construction Commission (no. 2) [2023] QCAT 286, [52]-[53] (Member McVeigh).Consideration In the present case, the operation of s 64 raises the following issues: (a)whether the Applicants rectified the work within the meaning of s 64(1) of Schedule 6;(b)if so, whether they did so without the prior written approval of the QBCC. In addressing these issues, I consider that it is necessary to commence with the content of the Notification. The QBCC’s written submissions state that the Applicants were notified ‘that the Claim had been accepted, and the [QBCC] would quantify the cost of completing the works under the Contract’.[12] [12]At [5](e), (f). I consider that the submission does not fully capture the terms of the Notification. The Notification stated the following: (a)‘OUTCOME: Your contract has been validly terminated and your claim under the Queensland Home Warranty Scheme has progressed.(b)‘THE NEXT STEP: Option 3 – you have elected to quantify the cost to complete the works through a Quantity Surveyor and cash settle your claim.’(c)Under the heading ‘SCOPE OF WORKS’:(i) ‘a Scope of Works is a description of the building work that has been accepted. This refers to our assessment of work included in your original contract with [the Builder].’(ii) ‘The QBCC has approved the attached Scope of Works and this document is used by the Quantity Surveyor to quantify the cost to complete the incomplete residential construction work.’(d)‘Sedgwick will assess the fair market value of the incomplete building work by engaging a Quantity Surveyor using the QBCC approved Scope of Works.’(e)under the heading ‘CLAIM APPROVAL’: ‘Once the loss to complete the work has been quantified, QBCC will resolve your claim by way of cash settlement in the amount of the fair market value as confirmed by Sedgwick.’(f)In a highlighted portion near the end of the Notification:‘IMPORTANT – please remember:1. …2. QBCC approval It is important that you do not make any arrangements to have work finished or fixed without prior written approval from the QBCC. If you do go ahead with work without written approval you may lose your right to claim under the Scheme.’ The Notification advised the Applicants that:(a)the QBCC accepted that the contract had been validly terminated; (b)the Claim had progressed;(c)a scope of works had been approved; and(d)the loss to complete the work was still to be quantified (by a Quantity Surveyor). In relation to the work performed by ALP Building, the Applicants subsequently stated:(a)‘We simply could not wait around for Sedgwick and QBCC to finish their long processes prior to recommencing the build as our lease is running out.’[13](b)‘We could not delay a build which we started using hard earnt life savings.[14](c)‘Due to extensive delays, we had no choice but to continue our build through another builder whilst the QBCC’s lengthy cash settlement process took place. Irrespective of whether the works were continued or not, the QBCC had three reports mentioned above which clearly and thoroughly documented the remaining works. In addition to that, two of the three reports provide expert cost estimates showing the remaining value of the works at that point in time.The build was partially completed in November 2023, enabling us to move in to save on rental and mortgage costs. As discussed in QCAT Tribunal dated 1 February 2024, there remain uncompleted works on the property, for example the exterior paint which was only half done due to high cost to paint first floor using a scaffolding system, we could not afford. Photos have been provided in Attachment 6. This is one of the outstanding work items we need to have rectified using the cash settlement.…’[15][13]Letter from Yishak Abraham to the QBCC dated 5 September 2023 forming part of the material attached to the Review Application.[14]Ibid. [15]Witness Statements of Yishak Abraham and Sofia Haile Gebremariam filed on 18 March 2024 at page 2.