Geary v QBCC

Link copied
Case Copied 20 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Geary v QBCC & Anor [2023] QCAT 179

PARTIES:

JOHN FRANCIS GEARY

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(first respondent)

ANTHONY JOHN MURRAY

(second respondent)

APPLICATION NO/S:

GAR449-20

MATTER TYPE:

General administrative review matters

DELIVERED ON:

24 May 2023

HEARING DATE:

24 January 2023

HEARD AT:

Brisbane

DECISION OF:

Member Howe

ORDERS:

1        The decision of Queensland Building and Construction Commission dated 13 October 2020 is confirmed.

2        The miscellaneous applications for adjournment and non-publication order are refused.

CATCHWORDS:

PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – where the Queensland Building and Construction Commission refused to issue directions to rectify defective building work in respect of 16 items of complaint – where only 6 of the complaints were pursued at hearing - where there was no written building contract – where a quotation issued by the builder was accepted by the parties as evidencing the scope of work of the contract save only in one respect – where the complaints made by the owner concerned matters outside the agreed scope of work – where one item of complaint correctly identified defective building work – where the item of defective building work was trivial – where it was unfair to require the builder to rectify

Queensland Building and Construction Commission Act 1991 (Qld) s 72(5)

Wright and Anor v Duke Building Pty Ltd and Anor [2017] QCATA 35

APPEARANCES & REPRESENTATION:

Applicant:

Self represented

First Respondent:

Self represented by S Tabuwalo

Second Respondent:

[eg. Self-represented]

Self represented

REASONS FOR DECISION

  1. Mr Geary has applied to the Tribunal for review of a decision made on 13 October 2020 by the Queensland Building and Construction Commission (“QBCC”) not to issue certain requested directions to rectify defective building work claimed to be performed by Mr Murray at Mr Geary’s property in 2019.

  2. Mr Geary made 20 complaints about the work done by Mr Murray. QBCC directed Mr Murray to rectify six, but not the remainder. Mr Geary apply to the tribunal to review the decision not to direct rectification of the other 14 items of complaint.

  3. Mr Geary resiled from his application seeking review of complaint items 3, 7, 8, 14, 17, 18, 19 and 20 at a compulsory conference held on 13 October 2021. The review application continued but limited to complaint items 2, 4, 5, 6, 11 and 16. At the compulsory conference the Tribunal directed that evidence be confined to addressing only complaint items 2, 4, 5, 6, 11 and 16.

  4. The parties appeared before the Tribunal at hearing on 24 January 2023.

The complaints

  1. The relevant complaints according to Mr Geary:

  2. Complaint 2 – timber floors have not been levelled as requested and expected, as per verbal contract.

  3. Complaint 4 – three 100 mm square holes left in timber floor (after three 100 mm  supporting posts to ceiling were removed) have been filled with cheap particle board and left uneven. Four boards could…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Geary v QBCC and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QCAT 179
Decision Date

CaseChat Overview and Summary

The applicant, Mr Geary, applied for review of a decision of the Queensland Building and Construction Commission (QBCC) not to issue directions to rectify defective building work performed by Mr Murray, the builder, at Mr Geary's property in 2019. Mr Geary made 20 complaints about the work done by Mr Murray. QBCC directed Mr Murray to rectify six, but not the remainder. Mr Geary applied to the tribunal to review the decision not to direct rectification of the other 14 items of complaint. Mr Geary resiled from his application seeking review of complaint items 3, 7, 8, 14, 17, 18, 19 and 20 at a compulsory conference held on 13 October 2021. The review application continued but limited to complaint items 2, 4, 5, 6, 11 and 16. The Tribunal found the complaints about Mr Murray’s work being defective or incomplete were not established. The only item of complaint correctly identifying defective building work was trivial. It was unfair to require the builder to rectify the defect. The QBCC decision was confirmed and the applications for adjournment and non-publication order were refused.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.