Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Gassman v Peck [2017] NSWCATCD 90 Hearing dates: 17 February 20179 June 2017 (final submissions received 17 July 2017) Decision date: 13 October 2017 Jurisdiction: Consumer and Commercial Division Before: T Simon, Senior Member Decision: The Tribunal makes the following orders:
1. The builder is to pay the homeowners the amount of $17,475.22 immediately.
2. In the event that either party intends to make submissions in relation to costs, the party making the costs application is to give to the other party and the Tribunal, either in person or by post, any documents and submissions they intend to rely on in relation to the costs application by 27 October 2017.
3. The parties are to provide to the other party and the Tribunal, either in person or by post, any documents and submissions in response to a costs application by 10 November 2017.
4. The issue of costs will be decided on the papers. In the event that the parties wish to be heard in person they must advise the Tribunal on or before 15 November 2017. If no further submissions are received the Tribunal will proceed to make a decision on the papers.Catchwords: Home Building – preferred outcome – s48MA – Breach of Statutory Warranty. Legislation Cited: Civil and Administrative Tribunal Act 2013
Home Building Act 1989 (NSW)
Home Building Amendment Act 2014Cases Cited: Brooks v Gannon Constructions Pty Limited [2017] NSWCATCD 12
Galdona v Peacock [2017] NSWCATAP 64
John Peter Maiolo v Frank Chiarelli and Anor [2016) NSWCATAP 81
3D Design & Build Pty Ltd v Lynch [2016] NSWCATAP 229Category: Principal judgment Parties: Peter Gassman and Beth Roddy (applicants)
Nathan Peck (respondent)Representation: Counsel
Solicitors:
D A Moujalli (for the applicants)
Macguire & McInerney for the applicants’
RMB Lawyers for the respondent
File Number(s): HB 16/21767 Publication restriction: Nil
Reasons for the Decision
The Application
-
For ease of reference in these reasons the applicants shall be referred to as homeowners and the respondent as builder.
-
On 9 May 2016, the homeowners made an application to renew proceedings HB 14/17549 in which orders had been made by consent on 11 December 2015. The orders required the builder to undertake and complete agreed works in a proper and workmanlike manner on or before 24 March 2016. The Tribunal has decided in this matter to make an order for money for rectification of the defective works.
Background
-
The homeowners made application HB 14/17549 on 1 April 2014. The application related to defective works which the homeowners allege the builder was liable for. The respondent had initially been named as ‘Impeckable Constructions Pty Limited’ in that application. That was the name of the builder as it appeared on the contract. The respondents name has subsequently been amended to Nathan Peck. Both parties have proceeded on the basis that was the builder with whom the homeowners contracted.
-
Both parties engaged experts. Mr Connor provided a report and gave evidence for…
Continue reading Gassman v Peck
Sign in free to access the full text
- AGLC
- Gassman v Peck [2017] NSWCATCD 90
- Case
- [2017] NSWCATCD 90
- Decision Date
CaseChat Overview and Summary
The Tribunal found that the builder had indeed breached the statutory warranties. The evidence showed that the work completed was not of the required standard and that the materials used were substandard. The Tribunal concluded that the builder had not taken reasonable care to ensure that the work was carried out in a workmanlike manner and that the materials used were of good quality. As a result, the Tribunal ordered the builder to pay the homeowners compensation for the defects found. The amount of $17,475.22 was determined to be the appropriate compensation for the breach of statutory warranties.
The Tribunal also outlined the process for any potential applications regarding costs. The builder or the homeowners could apply for costs associated with the proceedings, but both parties had to submit their documents and submissions by specific deadlines. If either party wished to be heard in person regarding the costs, they had to notify the Tribunal by a certain date. Otherwise, the decision on costs would be made based on the written submissions.
Orders
Orders of the court
The Tribunal makes the following orders:
1. The builder is to pay the homeowners the amount of $17,475.22 immediately.
2. In the event that either party intends to make submissions in relation to costs, the party making the costs application is to give to the other party and the Tribunal, either in person or by post, any documents and submissions they intend to rely on in relation to the costs application by 27 October 2017.
3. The parties are to provide to the other party and the Tribunal, either in person or by post, any documents and submissions in response to a costs application by 10 November 2017.
4. The issue of costs will be decided on the papers. In the event that the parties wish to be heard in person they must advise the Tribunal on or before 15 November 2017. If no further submissions are received the Tribunal will proceed to make a decision on the papers.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.