Gas Pipelines (Pipeline Corridor) Ulverstone Order 2014 (TAS)

Case
No judgment structure available for this case.

Gas Pipelines (Pipeline Corridor) Ulverstone Order 2014

I make the following order under section 70B of the Gas Pipelines Act 2000 .14 October 2014

MATTHEW GROOM

Minister for Energy

1Short titleThis order may be cited as the Gas Pipelines (Pipeline Corridor) Ulverstone Order 2014 . 2CommencementThis order takes effect on the day on which its making is notified in the Gazette. 3InterpretationIn this order – Act means the Gas Pipelines Act 2000 . 4Planning corridor (1)  In this clause – pipeline means the pipeline that – (a) is referred to in the pipeline licence granted under section 10 of the Act to Tas Gas Networks Pty Ltd on 28 May 2012, as amended; and (b) extends from – (i) the Ulverstone Offtake Facility and terminates at the point situated at 429,562.4E and 5,441,913.0N; and (ii) the point situated at 429,562.4E and 5,441,913.0N and terminates at the Simplot Plant in Mason Street, Ulverstone; and (c) is shown bounded by a heavy, black, broken line on Plan 9756 in the Central Plan Register, a reduced copy of which is set out, by way of illustration only, in Schedule 1 to this order. (2)  A planning corridor is declared in respect of the pipeline. (3)  The planning corridor declared in respect of the pipeline – (a) extends along the length of the pipeline and is – (i) for so much of the pipeline as is referred to in paragraph (b)(i) of the definition of pipeline in subclause (1) of this clause – 150 metres wide on each side of the pipeline; and (ii) for so much of the pipeline as is referred to in paragraph (b)(ii) of the  definition of pipeline  in subclause (1) of this clause – 38 metres wide on each side of the pipeline; and (b) extends – (i) away from the end of the pipeline situated at the Ulverstone Offtake Facility in a semicircle with a radius of 150 metres from the centre-line at that end of the pipeline; and (ii) away from the end of the pipeline situated at the Simplot Plant in Mason Street, Ulverstone in a semicircle with a radius of 38 metres from the centre-line at that end of the pipeline. (4)  For the purposes of subclause (3)(a) of this clause, the width of each side of the planning corridor in respect of the pipeline is measured – (a) from the centre-line of the pipeline; and (b) at a right angle from the centre-line of the pipeline. Schedule 1Plan

Clause 4

Displayed and numbered in accordance with the Rules Publication Act 1953.

Notified in the Gazette on 22 October 2014

This order is administered in the Department of State Growth.

EXPLANATORY NOTE

(This note is not part of the order) This order, made under the

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

0