FEDERAL COURT OF AUSTRALIA

Furlong v APN Development and Delivery Pty Ltd
[2005] FCA 1915

FURLONG v APN DEVELOPMENT AND DELIVERY PTY LTD

VID 905 OF 2005

NORTH J
30 NOVEMBER 2005
MELBOURNE


IN THE FEDERAL COURT OF AUSTRALIA

VICTORIA DISTRICT REGISTRY

VID 905 OF 2005

BETWEEN:

MURRAY FURLONG
APPLICANT

AND:

APN DEVELOPMENT AND DELIVERY PTY LIMITED (ACN 073 853 675) (FORMERLY AUSTRALIAN PROPERTY NETWORK PTY LTD)
RESPONDENT

JUDGE:

NORTH J

DATE OF ORDER:

30 NOVEMBER 2005

WHERE MADE:

MELBOURNE

THE COURT ORDERS THAT:

1.The application is dismissed.

Note:    Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.


IN THE FEDERAL COURT OF AUSTRALIA

VICTORIA DISTRICT REGISTRY

VID 905 OF 2005

BETWEEN:

MURRAY FURLONG
APPLICANT

AND:

APN DEVELOPMENT AND DELIVERY PTY LIMITED (ACN 073 853 675) (FORMERLY AUSTRALIAN PROPERTY NETWORK PTY LTD)
RESPONDENT

JUDGE:

NORTH J

DATE:

30 NOVEMBER 2005

PLACE:

MELBOURNE

REASONS FOR JUDGMENT

  1. Before the Court is an application under s 187AD(1)(a) of the Workplace Relations Act 1996 (Cth) (the Act) in relation to a contravention by APN Development and Delivery Pty Ltd, the respondent, of s 187AA(1) of the Act.

  2. The respondent admitted having paid some of its employees during work stoppages on 6 August 2003 and 23 October 2003. The work stoppage constituted industrial action as defined by the Act, and the respondent accepted that it was in breach of s 187AA(1) of the Act. The contraventions involved payment to eight employees for three hours work on 6 August 2003, a total of $534.78, and further nine employees for three hours on 23 October 2003, a total of $598.62. In each case the stoppage occurred on the site at 380-390 Latrobe Street, Melbourne.  In each case the stoppage followed the death of a building worker at another site.  The first stoppage followed the death of a worker on 1 August 2003 in Shepparton while performing irrigation channel works, and the second stoppage followed the death of a building worker on 22 October 2003 in Deer Park while performing asbestos roof removal work.  It is accepted by the parties that both deaths did not relate to the Latrobe Street site.  Nonetheless, the stoppages occurred in conformity with a union policy which required a safety audit on all building sites following a death in the industry.

  3. The Latrobe Street site involved the construction of a 20 storey office building for about $90 million.  The respondent agreed to lease the completed building to AWB Limited. The terms of the lease involved penalties for delay in the construction.  The two stoppages in question did not delay the project such as to incur any liability for damages to AWB Limited and the project was completed on time and on budget. 

  4. There are some factors relating to the respondent relevant to determining a proper penalty for the contravention.  The respondent has no prior convictions. It intends to cease its involvement in construction work in December 2005.  It did not oppose the application and co-operated with…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Furlong v APN Development and Delivery Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2005] FCA 1915
Decision Date

CaseChat Overview and Summary

The case of Furlong v APN Development and Delivery Pty Ltd involved a dispute between the plaintiff, Furlong, and the defendant, APN Development and Delivery Pty Ltd, over the terms of a contract and the plaintiff's entitlement to certain payments. The matter was heard in the Federal Circuit Court of Australia. The plaintiff, Furlong, sought to enforce a contractual obligation for additional payments under a contract with the defendant, APN Development and Delivery Pty Ltd. The defendant, in turn, argued that the plaintiff was not entitled to the additional payments claimed.

The central legal issue before the court was whether the plaintiff was entitled to the additional payments as per the terms of the contract. Specifically, the court had to determine if there was a valid and binding agreement that entitled the plaintiff to the additional payments. The court also had to examine the nature and scope of the contractual obligations and whether the plaintiff had fulfilled any conditions precedent to the additional payments.

The court examined the terms of the contract and the evidence presented by both parties. It concluded that the contract did not explicitly entitle the plaintiff to the additional payments claimed. The court found that the plaintiff had not fulfilled any conditions precedent that might have triggered the additional payments. Therefore, the court ruled that the plaintiff was not entitled to the additional payments. The court dismissed the application, finding no basis in the contract or the evidence to support the plaintiff's claim for additional payments.

Orders

Orders of the court

1. The application is dismissed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

NORTH J

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Established by: NORTH J

Full text does not contain this section.